Questions_ _Answers2.pdf
PDF 288 KB Posted
- Attached to
- Mt. Hebron Barracks Complex Construction Federal contract opportunity
- Solicitation number
- AG-9AC7-S-13-0112
About this file
Questions Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend4_plus_summary.pdf | ||
| Updated_Maps_Pkg.pdf | ||
| Rev._Sections_08710_09650_11451.pdf | ||
| Questions_ _Answers4.pdf | ||
| CA9_dvb_080913.pdf | ||
| Mt_Hebron_Amendment_3.pdf | ||
| Amend2_MtHebronBarracks.pdf | ||
| newSF_24.pdf | ||
| Amendment_2FAR_clauses.pdf | ||
| NewM_HebronBarracksDrawings_24x36.pdf | ||
| RevSchedule.pdf | ||
| SF30_Amendment1.pdf | ||
| Questions_ _Answers.pdf | ||
| RevSECTION_02050.pdf | ||
| RevSec08710_pg175.pdf | ||
| SF_24_Bid_Bond.pdf | ||
| Contract_Transmittal_Form.pdf | ||
| Mt_Hebron_Barracks_Complex_Final_Specifications.pdf | ||
| CA9_rev_12 _071913.pdf | ||
| Updated_Mt_Hebron_Barracks_Complex_11x17_Drawings.pdf | ||
| AG-9AC7-S-13-0112.pdf | ||
| Updated_Mt_Hebron_Barracks_Complex_24x36_Drawings.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mt Hebron Barracks Complex
AG-9AC7-S-13-0112
Questions and Answers – 8/2/2013
Q1: The drawings (Sheet A3.1, West Elevation/4) makes reference to a “SEAMLESS GUTTER”.
The specification does not seem to address the gutter/downspout system directly. The specified Metal Sales and McElroy roof systems are not available with seamless gutters. The gutter system they utilize is available in maximum 40’ sections. A seamless gutter system would require a custom on-site fabrication that would be more costly.
Is the Government willing to consider a gutter system with sealed joints, If so, what is the minimum acceptable material length: 20, 30, 40 feet?
A.1: The government specifies a seamless gutter system; the Metal Sales and McElroy roof systems mentioned refers to Section 07400, Metal Roofing as they are known manufacturers of the metal roofing material that meet the specifications. These manufacturers are not referenced in specification 07700 2.01 D & E describing the Gutters and Downspouts. The requirement at 07700 is to match roof color and finish with no specific manufacturer addressed.
Q2: The bid bond in the contract documents has an expiration date that is in 2012. Can you please forward the bid bond that you would like us to use
A.2: GSA updated the form after the solicitation was issued and extended the expiration date of the form; no changes were made. The updated form is uploaded with this amendment however if bid guarantees are already in process the previous version of the form is acceptable..
NOTE: It was discovered that the original 24 x 36 drawings only had page 1 formatted to print at that size. The file was reformatted and posted on 7/30/13 to print at the designated size.
No changes were made to the drawings.