Amend4_plus_summary.pdf
PDF 1 MB Posted
- Attached to
- Mt. Hebron Barracks Complex Construction Federal contract opportunity
- Solicitation number
- AG-9AC7-S-13-0112
About this file
Amendment 4 plus summary
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Updated_Maps_Pkg.pdf | ||
| Rev._Sections_08710_09650_11451.pdf | ||
| CA9_dvb_080913.pdf | ||
| Questions_ _Answers4.pdf | ||
| Mt_Hebron_Amendment_3.pdf | ||
| Amend2_MtHebronBarracks.pdf | ||
| newSF_24.pdf | ||
| Questions_ _Answers2.pdf | ||
| Amendment_2FAR_clauses.pdf | ||
| NewM_HebronBarracksDrawings_24x36.pdf | ||
| RevSchedule.pdf | ||
| SF30_Amendment1.pdf | ||
| RevSec08710_pg175.pdf | ||
| Questions_ _Answers.pdf | ||
| RevSECTION_02050.pdf | ||
| SF_24_Bid_Bond.pdf | ||
| Contract_Transmittal_Form.pdf | ||
| Updated_Mt_Hebron_Barracks_Complex_11x17_Drawings.pdf | ||
| AG-9AC7-S-13-0112.pdf | ||
| Updated_Mt_Hebron_Barracks_Complex_24x36_Drawings.pdf | ||
| Mt_Hebron_Barracks_Complex_Final_Specifications.pdf | ||
| CA9_rev_12 _071913.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mt Hebron Barracks Complex
AG-9AC7-S-13-0112
Summary of Changes for Amendment 4
The following specifications are revised: Remove and replace pages 216-217, 175
Section 11451 revised the range and vent hoods
Section 08710 revised (Part 3.03)
The following specification is added: (New pages 189 a – 189b)
Section 09650 is added regarding the rubber wall base
The following drawings are revised, remove and replace A2.1 A9.1 C6.0 E1.0 E3.0 E4.0 E6.0 M1.0 P1.0 P2.0 S2.0 S2.1
Summary of Drawing Revisions
Architectural drawings revised the finish schedule and revised the finish designations in the utility room and the 3 storage closets off the hallway
The M1.0 drawing replaces the original version, the only difference is inclusion the wall furnace in the equipment schedule and deletes equipment that was shown as NIC.
Civil drawing clarified the accessible parking, removed the tactile surface from the curb and added wheel stops to all parking stalls
Electrical drawings revised building feeders and the size of the bonding wire to the gas and water lines
The plumbing drawings (P1.0 & P2.0) revised the floor drain and trap primer systems
The structural drawings revised the slab depressions for the floor drains in the restrooms
Davis Bacon Wages – CA130009 , 8/9/2013, Rev 13 – Remove and replace wage determination.