Att 4 Specification - Concrete Formwork
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WASTEWATER IMPROVEMENTS CNF
SECTION 03100 - CONCRETE FORMWORK
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Formwork for cast-in place concrete, with shoring, bracing and anchorage.
B. Openings for other work.
C. Form accessories.
D. Form stripping.
1.2 RELATED SECTIONS
A. Section 03200-Concrete Reinforcement.
B. Section 03300 - Cast-in-Place Concrete.
1.3 REFERENCES
A. ACI 301 - Structural Concrete for Buildings.
B. ACI 318 - Building Code Requirements for Reinforced Concrete.
C. ACI 347 - Recommended Practice For Concrete Formwork.
D. PS 1 - Construction and Industrial Plywood.
1.4 DESIGN REQUIREMENTS
A. Design, engineer and construct formwork, shoring and bracing to conform to code requirements; resultant concrete to conform to required shape, line and dimension.
1.5 QUALITY ASSURANCE
A. Perform work in accordance with ACI 347 and 301 standards.
1.6 MEASUREMENT AND PAYMENT
A. No separate measurement or payment will be made for work specified in this section.
PART 2 - PRODUCTS
2.1 WOOD FORM MATERIALS
A. Forms shall be smooth, clean, mortar tight and have sufficient strength to resist deflection under the loads imposed by the concrete Plywood shall be provided in the largest practical sizes to minimize joints. Plywood: U.S. Product Standard PS 1 (for Softwood Plywood, Construction and Industrial), grade-stamped, "B-B Ply form" Class II Ext. DFPA for concealed surfaces, "HDO-Ext" for exposed-to-view faces or faces to be painted, 3/4-inch thick. Furnish in largest practicable sizes to minimize number of joints. Douglas Fir species; medium density overlaid one side; sound undamaged sheets with clean, true edges or any lumbers of sufficient strength to hold the concrete in place.
A. Lumber: Douglas Fir species; Number 2 grade; with grade stamp clearly visible.
2.2 FORMWORK ACCESSORIES
A. Form Ties: Snap-off type, galvanized metal, fixed length, cone type, 1 inch back break dimension, free of defects that could leave holes larger than 1 inch in concrete surface.
B. Form Release Agent: Colorless mineral oil which will not stain concrete, or absorb moisture.
C. Corners: Chamfered, wood strip type; 3/4 x 3/4 inch size; maximum possible lengths.
D. Nails, Spikes, Lag Bolts, Through Bolts, Anchorages: Sized as required, of sufficient strength and character to maintain formwork in place while placing concrete.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify lines, levels and centers before proceeding with formwork. Ensure that dimensions agree with drawings.
3.2 EARTH FORMS
A. Hand trim sides and bottom of earth forms. Remove loose soil prior to placing concrete.
3.3 ERECTION - FORMWORK
A. Erect formwork, shoring and bracing to achieve design requirements, in accordance with requirements of ACI 301.
B. Provide bracing to ensure stability of formwork. Shore or strengthen formwork subject to overstressing by construction loads.
C. Arrange and assemble formwork to permit dismantling and stripping. Do not damage concrete during stripping. Permit removal of remaining principal shores.
D. Align joints and make watertight. Keep form joints to a minimum.
E. Obtain approval before framing openings in structural members which are not indicated on Drawings.
F. Provide chamfer strips on external corners of walls.
G. Coordinate this section with other sections of work which require attachment of components to formwork.
H. If formwork is placed after reinforcement resulting in insufficient concrete cover over reinforcement before proceeding, request instructions from Contracting Officer.
3.4 APPLICATION - FORM RELEASE AGENT
A. Apply form release agent on formwork in accordance with manufacturer's recommendations.
B. Apply prior to placement of reinforcing steel, anchoring devices, and embedded items.
C. Do not apply form release agent where concrete surfaces will receive applied coverings which are affected by agent. Soak inside surfaces of untreated forms with clean water. Keep surfaces coated prior to placement of concrete.
3.5 INSERTS, EMBEDDED PARTS, AND OPENINGS
A. Provide formed openings where required for items to be embedded in passing through concrete work.
B. Locate and set in place items which will be cast directly into concrete.
C. Coordinate with work of other sections in forming and placing openings, slots, sleeves, bolts, anchors, other inserts, and components of other Work.
D. Provide temporary ports or openings in formwork where required to facilitate cleaning and inspection. Locate openings at bottom of forms to allow flushing water to drain.
E. Close temporary openings with tight fitting panels, flush with inside face of forms, and neatly fitted so joints will not be apparent in exposed concrete surfaces.
3.6 FORM CLEANING
A. Clean forms as erection proceeds, to remove foreign matter within forms.
B. Clean formed cavities of debris prior to placing concrete.
C. Flush with water or use compressed air to remove remaining foreign matter. Ensure that water and debris drain to exterior through clean-out ports.
D. During cold weather, remove ice and snow from within forms. Do not use de-icing salts. Do not use water to clean out forms, unless formwork and concrete construction proceed within heated enclosure. Use compressed air or other means to remove foreign matter.
3.7
FORMWORK TOLERANCES
A. Construct formwork to maintain tolerances required by ACI 301.
3.8 FIELD QUALITY CONTROL
A. Section 01400 - Quality Control: Field inspection.
B. Inspect erected formwork, shoring, and bracing to ensure that work is in accordance with formwork design, and that supports, fastenings, wedges, ties, and items are secure.
C. Do not reuse wood formwork more than 2 times for concrete surfaces to be exposed to view. Do not patch formwork.
3.9 FORM REMOVAL
A. Do not remove forms or bracing until concrete has gained sufficient strength to carry its own weight and imposed loads.
B. Loosen forms carefully. Do not wedge pry bars, hammers, or tools against finish concrete surfaces scheduled for exposure to view.
C. Store removed forms in manner that surfaces to be in contact with fresh concrete will not be damaged. Discard damaged forms.
END OF SECTION 03100
CONCRETE FORMWORK Section 03100-4