ATTACH_1_Amendment_0002_-_Section_C_Replacement_Pages.pdf
PDF 30 KB Posted
- Attached to
- Mahogany Grove Group Campground Reconstruction Project Federal contract opportunity
- Solicitation number
- AG-0261-S-13-0012
About this file
Amend 0002 - ATTACH 1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ATTACH_2_-_Amendment_0002_-_Mahogany_Specifications_04-10-2013.pdf | ||
| Amend_002_-_AG-0261-S-13-0012.pdf | ||
| Amend_001_-_AG-0261-S-13-0012.pdf | ||
| 03-05-13_Mahogany_Grove_RFP.pdf | ||
| ATT_3_-_NV100034_Highway_01-04-13.pdf | ||
| ATT_2_-_Mahogany.dwgs.Final.12.11.2012.signed.pdf | ||
| ATTACH_5_-_Mahogany_Grove_Construction_Cost_Estimate_Breakdown.xlsx | XLSX spreadsheet | |
| ATT_1_-Mahogany.Spec.FINAL.12.7.2012_-2.pdf | ||
| ATT_4_-Mahogany_Grove_Past_Performance_Questionnaire.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0002 AG-0261-S-13-0012 Section C Replacement Pages Mahogany Grove Group Campground Reconstruction Project
PART I - THE SCHEDULE
SECTION C - DESCRIPTION/SPECIFICATIONS
MAHOGANY GROVE GROUP CAMPGROUND RECONSTRUCTION PROJECT
C-1 SCOPE OF CONTRACT
A. This project consists of reconstructing an existing group campground area, and constructing a new trailhead and trail. Including the construction and installation of asphalt roads, gates, water system, kiosks, bulletin boards, toilet buildings, group sites, dumpster pads, concrete paths, aggregate paths, signs, site furniture, obliteration and removal of existing features, scarification and seeding disturbed areas in the Spring Mountains National Recreation Area located on the Humboldt-Toiyabe National Forest.
C-2 PROJECT LOCATION
A. The project is located in the Spring Mountains National Recreation Area of the Humboldt-Toiyabe National Forest, Clark County, Nevada, in Section 7 & 8, T19 S, R57E. It is located approximately 40 miles North-West of Las Vegas, NV.
C-3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction sites will be closed to the public during construction but open to authorized government employees. The Contractor will be responsible for signing, limiting public access, and safety of public and/or government employees in the area.
2. The Contractor is responsible for the security or the Contractor’s equipment and materials.
3. Utilities are not available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.
4. No fuel storage on site is permitted. Fuel trucks must be equipped with spill containment kits and portable berms that meet all state and federal regulations. A spill containment plan must be submitted and approved prior to construction.
5. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work. Toilet facilities shall be provided at a rate of one stool for every 10 workers assigned or working on site. Contract may use the existing toilets located throughout the campground in lieu of temporary toilet facilities until these toilets are removed.
6. All construction equipment shall be pressure washed before entering the Site. The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
7. Water service to the Clark County Youth Camp cannot be interrupted for more than 24 hours at any time during the construction of the project. Plan construction operations so that interruptions are a maximum of 1 hour if possible.
8. Due to restrictions by the Migratory Bird Treaty Act, heavy machinery may not be operated between the dates of May 20 and July 20. Staking and other non-disruptive activities are allowed during that timeframe. A bird survey will be completed on or around June 1 and contractors may be allowed into the site with heavy machinery before July 21 if nesting birds are not found in the area.
C-4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Nevada Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
Amendment 0002 AG-0261-S-13-0012 Section C Replacement Pages Mahogany Grove Group Campground Reconstruction Project
C-5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work or housing) on site.
1. The Trailhead parking area shall be used as the primary staging and storage area. The Contractor should make it a priority to complete the excavation and embankment of the Trailhead parking area first, so this area can be utilized as the staging area.
B. Overnight camping will be allowed on site.
C-6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
C-7 GOVERNMENT FURNISHED PROPERTY
A. Government Furnished Property (GFP) will be provided to the Contractor.
B. The Government will provide the following items to the Contractor at the assigned work location as needed:
• Survey Control Sheets (Specification 010250)
• 3 CXT Double Rocky Mountain vault toilet buildings with porch and chase (Specification
133460)
• 34 concrete picnic tables, Outdoor Creations, Model 104S (Specification 129410)
• 12 concrete benches w/custom etching Outdoor Creations, Model 408, (Specification 129410)
• 6 concrete fire rings, Outdoor Creations, Model 304, (Specification 129410)
• 6 concrete serving tables, Outdoor Creations, Model 102, (Specification 129410)
• Pulverized asphalt (Specification 322706)
• Padlocks (Specification 323116)
C-8 START DATE
Summer 2013
C-9 CONTRACT TIME
Project must be completed by December 31, 2013.
C- 10 GENERAL SPECIFICATIONS
See Section J for the list of General Specifications that are incorporated into this solicitation and any resultant contract.
C-11 DRAWINGS
See Section J for the listing of Drawings that are incorporated into this solicitation and any resultant contract.
| 1. Construction sites will be closed to the public during construction but open to authorized government employees. The Contractor will be responsible for signing, limiting public access, and safety of public and/or government employees in the area. |
| 2. The Contractor is responsible for the security or the Contractor’s equipment and materials. |
| 3. Utilities are not available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service. |
| 4. No fuel storage on site is permitted. Fuel trucks must be equipped with spill containment kits and portable berms that meet all state and federal regulations. A spill containment plan must be submitted and approved prior to construction. |
| 5. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work. Toilet facilities shall be provided at a rate of one stool for every 10 workers assigned or working on site. Contract may use the exi... |
| 6. All construction equipment shall be pressure washed before entering the Site. The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and... |
| 7. Water service to the Clark County Youth Camp cannot be interrupted for more than 24 hours at any time during the construction of the project. Plan construction operations so that interruptions are a maximum of 1 hour if possible. |
| 8. Due to restrictions by the Migratory Bird Treaty Act, heavy machinery may not be operated between the dates of May 20 and July 20. Staking and other non-disruptive activities are allowed during that timeframe. A bird survey will be completed on o... |
| 1. The Trailhead parking area shall be used as the primary staging and storage area. The Contractor should make it a priority to complete the excavation and embankment of the Trailhead parking area first, so this area can be utilized as the staging ar... |
| C- 10 GENERAL SPECIFICATIONS |
| C-11 DRAWINGS |