ATT 1 - Specs

View the file

Other files for this federal contract opportunity

Other files attached to Mahogany Grove Group Campground Reconstruction Project, newest first.
File Type Posted
Amend_002_-_AG-0261-S-13-0012.pdf PDF
ATTACH_1_Amendment_0002_-_Section_C_Replacement_Pages.pdf PDF
ATTACH_2_-_Amendment_0002_-_Mahogany_Specifications_04-10-2013.pdf PDF
Amend_001_-_AG-0261-S-13-0012.pdf PDF
ATTACH_5_-_Mahogany_Grove_Construction_Cost_Estimate_Breakdown.xlsx XLSX spreadsheet
03-05-13_Mahogany_Grove_RFP.pdf PDF
ATT_3_-_NV100034_Highway_01-04-13.pdf PDF
ATT_4_-Mahogany_Grove_Past_Performance_Questionnaire.pdf PDF
ATT_2_-_Mahogany.dwgs.Final.12.11.2012.signed.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA FOREST SERVICE

Mahogany Grove Group Campground

Reconstruction Project Specifications

Spring Mountains National Recreation Area Humboldt Toiyabe National Forest

12/7/2012

Final (12.7.2012)

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1

Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

MAHOGANY GROVE GROUP CAMPGROUND RECONSTRUCTION PROJECT

(Final 12.7.2012)

1.1 SCOPE OF CONTRACT

A. This project consists of reconstructing an existing group campground area, and constructing a new trailhead and trail. Including the construction and installation of asphalt roads, gates, water system, kiosks, bulletin boards, toilet buildings, group sites, dumpster pads, concrete paths, aggregate paths, signs, site furniture, obliteration and removal of existing features, scarification and seeding disturbed areas in the Spring Mountains National Recreation Area located on the Humboldt-Toiyabe National Forest.

1.2 PROJECT LOCATION

A. The project is located in the Spring Mountains National Recreation Area of the Humboldt-Toiyabe National Forest, Clark County, Nevada, in Section 7 & 8, T19 S, R57E. It is located approximately 40 miles North-West of Las Vegas, NV.

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. Construction sites will be closed to the public during construction but open to authorized government employees. The Contractor will be responsible for signing, limiting public access, and safety of public and/or government employees in the area.

2. The Contractor is responsible for the security or the Contractor’s equipment and materials.

3. Utilities are not available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.

4. No fuel storage on site is permitted. Fuel trucks must be equipped with spill containment kits and portable berms that meet all state and federal regulations. A spill containment plan must be submitted and approved prior to construction.

5. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work. Toilet facilities shall be provided at a rate of one stool for every 10 workers assigned or working on site. Contract may use the existing toilets located throughout the campground in lieu of temporary toilet facilities until these toilets are removed.

6. All construction equipment shall be pressure washed before entering the Site.

The removal of mud and debris from treds, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2 running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

7. Water service to the Clark County Youth Camp cannot be interrupted for more than 24 hours at any time during the construction of the project. Plan construction operations so that interruptions are a maximum of 1 hour if possible.

1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Nevada Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

1.5 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work or housing) on site.

1. The Trailhead parking area shall be used as the primary staging and storage area.

The Contractor should make it a priority to complete the excavation and embankment of the Trailhead parking area first, so this area can be utilized as the staging area.

B. Overnight camping will be allowed on site.

1.6 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.7 START DATE

A. Spring 2013

1.8 CONTRACT TIME

A. Project must be completed by December 31, 2013.

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3

1.9 SPECIFICATIONS

Section 010250 - Construction Staking Section 011250 - Measurement And Payment With Asphalt Section 011900 - Mobilization Section 013300 - Submittal Procedures Section 014100 - Quality Control Section 023701 - Sediment And Erosion Control Measures Section 024100 - Waste Material Disposal Section 024102 - Removal And Disposal Of Existing Structures And Obstructions Section 026460 - Concrete Dumpster Pad Section 033000 - Cast-In-Place Concrete Section 033020 - Concrete From Packaged Dry Mix For Minor Structures Section 033520 - Concrete Waterway Section 033545 - Colored Concrete Paths Section 101400 - Signs Section 101410 - Site Identification Sign Relocation Section 129410 - Group Sites Section 133430 - Stone Slab Bench Section 133460 - Double Vault Comfort Station Installation Section 221100 - Water Distribution Systems Section 221102 - Curb Valves And Boxes Section 221105 - Frost Proof Hydrants Section 311000 - Clearing And Grubbing Section 312000 - Earthwork Section 312100 - Project Site Preparation And Grading Section 312225 - Excavation & Embankment Section 321200 - Hot-Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 321206 - Loose Rock Riprap Section 322100 - Tent Pads Section 322205 - Barrier Rocks Section 322625 - Recycled Plastic Wheelstops Section 322640 - Pavement Marking Section 322706 - Asphalt Pavement Pulverizing Section 323116 - Road Closure Gates Section 323119 - Ornamental Metal Barrier Fence Section 323230 - Segmental Retaining Walls Section 329206 - Seeding Section 332228 - Culvert Pipe And Pipe Arches

END OF SECTION C

SEPTEMBER 2012

CONSTRUCTION STAKING 010250-1

USDA FOREST SERVICE, R-4

Mahoghany.Specs.FINAL.11.19.2012

SECTION 010250 - CONSTRUCTION STAKING

PART 1 - GENERAL

1.1 SUMMARY

A. This work shall consist of the construction staking of roads, parking lots, parking spurs, family units, paths, stairways, culverts, retaining walls, buildings, and utilities in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.

1.2 QUALITY CONTROL

A. Construction staking shall be accomplished under the direction of a Licensed Civil Engineer or Land Surveyor closely associated and familiar with construction staking;

periodic visits to the project site are required.

1.3 MEASUREMENT AND PAYMENT

A. Measurement shall be lump sum for surveying and staking the project through all phases of construction.

PART 2 - PRODUCTS

2.1 GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS

A. The Government will provide the contractor with a set of survey control sheets showing horizontal and vertical control for site to be staked. The Government will provide the Contractor with layout information that will include:

1. Control Points - Northing, Easting, Existing Elevations.

2. Roads, Spurs, Parking Areas - Northing, Easting and Finish Elevations for subgrade centerline and edge of roads, spurs, parking areas.

3. Pathways and Trailways - Northing, Easting and Finish Elevations for subgrade centerline.

4. Buildings, Other Structures, Group Sites and Tent Pads- Northing, Easting and

Finish Elevations for corners of buildings, other structures (fencing, etc), Group Sites and Tent Pads.

5. Utility Lines – Northing and Easting for centerline of utilities (Water).

6. Segmented Retaining Walls

CONSTRUCTION STAKING 010250-2

a. Northing, Easting, and Finish Elevations for Subgrade at intersection with face or back of wall, and Hinge Points at intersection of finished grade with face or back of wall.

2.2 STAKES

A. Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable.

Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:

1. Roads, parking lots, and parking spurs -Orange

2. Waterlines, utilities, and culverts -Blue

3. Family Units, group units, stairs, and paths -Red

4. Buildings, excavation and grading -Yellow

5. Segmented Retaining walls -Blue/White Striped

2.3 SURVEY NOTE PAPER AND BOOKS

A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract. The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.

B. Accuracy requirements:

1. Minimum position close; 1/1000

2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)

3. Cross section and slope stake precision:

C. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.

D. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross section points will not exceed: 1.0 ft.

CONSTRUCTION STAKING 010250-3

E. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%. Clearing limits: 1.0 ft.

3.2 ESTABLISING AND REFERENCING IMPROVEMENT LOCATIONS

A. Access Roads, Parking Spurs, and Parking lots:

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established.

Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles as shown on the drawings.

2. Slope stakes shall be set at 50-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points. Slope stakes shall be set at 25 foot intervals around curves having a radius less than 100 feet.

B. Group Units, Family Units and Tent Pads

1. Slope stakes shall be established at the corners of family units. Slope stakes shall be written to reference the sub-grade grade of the unit or pad being staked.

C. Paths and Trails

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established.

Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles as shown on the drawings.

2. Slope stakes shall be set at 25-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points.

D. Culverts

1. Slope stakes and slope reference stakes shall be set at all culvert locations. A culvert reference stake and hub shall be set on the centerline of the culvert 10 feet from each end or beyond the clearing limit, whichever is greater. The following shall be recorded on these stakes:

a. The actual field measured length

b. The vertical and horizontal distance from hubs to the invert at the ends of the culvert.

E. Waterline, Sewerline, & other Utilities

1. Waterline, Sewerline, & other Utilities shall be staked at the locations shown on the drawings with the specified minimum burial depth. Waterline and sewerline elevations shall be accurately staked to provide for drainage as indicated on the drawings. Grade stakes shall be established as necessary to provide the control for the construction work.

CONSTRUCTION STAKING 010250-4

F. Drainfields

1. Construction stakes shall be established at ends of each drain line. Stakes shall identify the finish elevation of each drain line, bottom of gravel trench, and width of trench.

G. Buildings

1. Slope stakes and slope stake references shall be established at each corner and as necessary to provide adequate construction control.

H. Segmented Retaining Walls

1. Construction stakes shall be established at start and end of wall, corners, stairs, and at maximum 25 feet along wall. Stakes shall establish top of wall, bottom of wall, and finish grade at top of wall and bottom of wall.

2. Additional stakes shall be established at required stepping of wall (top and bottom). Note - Top of wall shall be a minimum of 2 inches above finish grade and bottom of wall shall be a minimum of 12 inches below finish grade.

3.3 DISCREPANCIES

A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.

3.4 VERTICAL CONTROL

A. Vertical control for construction shall be as referenced on the Drawings.

3.5 MARKING STAKES

A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;

PI Point of Intersection of tangents PC Point of curvature POC Point on curve Pt Point of tangency POT Point on tangent RP Reference point P P-line (preliminary location line) L L-line (final location line) BM Bench mark TBM Temporary bench mark

CONSTRUCTION STAKING 010250-5

BT Begin taper (any) ET End taper (any) C Cut F Fill L Centerline D Ditch W Width

3.6 SURVEY NOTES

A. All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.

B. Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey was performed, and survey data or sketched that cannot be electronically recorded. The party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.

END OF SECTION 010250

March 2013

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-1

USDA FOREST SERVICE, R-4

Mahoghany.Specs.FINAL.11.19.2012

SECTION 011250 - MEASUREMENT AND PAYMENT WITH ASPHALT

PART 1 - GENERAL

1.1 SUMMARY

A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

1.2 DETERMINATION OF QUANTITIES

A. The following measurements and calculations shall be used to determine contract quantities for payment.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

7. For bituminous material, volumes will be measured at 60°F or will be corrected to the volume at 60°F by using ASTM D1250 for asphalts. Emulsified asphalt will

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-2

be measured at 60°F, or measured by converting the gallonage at another temperature to gallonage at 60°F by means of the following formula:

Gallons at 60°F = Gallons at A°F 1+0.00025 (A°F - 60°F)

* A°F is the temperature of the material at the time the gallonage is measured.

a. For vehicular shipments, net certified scale weights or weights based on certified volumes will be used as a basis of measurement. Measurements will be adjusted when bituminous material has been lost from the vehicle or the distributor, has been wasted, or has otherwise not been incorporated into this work. Determining true weights of hauling vehicles shall be made by weighing the empty vehicles at least once a day at the times the CO directs.

Each vehicle shall bear a plainly legible identification mark.

b. When bituminous materials are shipped, net certified weights, or volume corrected for loss of foaming, can be used for computing quantities.

B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

1. Acre: Make longitudinal and transverse measurements for area computations horizontally.

2. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

3. Cubic Yard (CY): A measurement computed by one of the following methods:

a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

4. Each (EA): One complete unit, which may consist of one or more parts.

5. Gallons (GAL): The quantity shall be measured by any of the following methods:

a. Measured volume in container.

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-3

b. Metered volume by approved metering system.

c. Commercially package volume.

6. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

7. Linear Foot (LF): Measurement of work along its length from point-to-point;

parallel to the base or foundation. Do not measure overlaps.

8. Lump Sum (LS): One complete unit.

9. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

10. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

11. Square Foot (SF): Measured on a plane parallel to the surface being measured.

12. Square Yard (SY): Measured on a plane parallel to the surface being measured.

13. Ton: Measured as a short ton consisting of 2,000 pounds.

1.4 METHOD OF MEASUREMENT

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.

5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-4

1.5 PRICE ADJUSTMENT (for Out-of-Specification Bituminous Materials)

A. Bituminous materials are defined as all types and grades of asphalt cement, liquid asphalt, emulsified asphalt, and dust oil.

B. If bituminous material fails one or more test requirements, and the Contracting Officer determines it is in the public interest to accept the material at a reduced price, the price reduction shall be based on the test results giving the largest percent price adjustment.

The contractor may remove and replace the defective material or accept the adjustment.

C. The price reduction shall apply to all pay items affected.

D. Price adjustment will be based on samples taken in duplicate in accordance with AASHTO T40 under the supervision of the Contracting Officer. Samples shall be sent to an authorized laboratory. The laboratory shall test one of each duplicate sample and retain the other. When any test result is not within the specification limits, the laboratory shall immediately notify the Contractor, the supplier, and the Contracting Officer. The Contractor, after notifying the Contracting Officer, may check test the retained sample.

E. If the retained sample tests satisfactorily, the material will be accepted. If the retained sample also fails, the following schedule of price adjustments shall apply. The average of test values for the two samples will determine the basis for price adjustment, except when test results on the samples differ by more than the applicable AASHTO or ASTM Repeatability Unit; then, the test result numerically nearest the specification requirement will be used. (A repeatability unit is defined as D2S or D2S% limit for single operator precision described in ASTM C670.)

F. The schedule of price adjustments shall not apply to the following tests:

Test AASHTO Test Method Spot Test T102 Particle Charge T59 Ductility T51

G. Bituminous materials failing to meet specifications for these tests shall be removed and replaced.

H. See Table 011250-1 for the schedule of price adjustments for bituminous materials that do not meet specifications.

MEASUREMENT AND PAYMENT WITH ASPHALT 011250-5

Table 011250-1

Schedule of Price Adjustments for Out-of-Specification Bituminous Materials.

Application

Deviation from Specification Limit Measured in Reproducibility Units*.

Less than 1 1 but less than 2

2 but less than 3

3 or more

Price reduction applicable to bituminous base course and pavement mixture or to seal coat and bituminous material paid for as a separate item.

0% 5% 25% Remove & Replace

Price reduction applicable to bituminous material paid for as a separate item.

0% 10% 25% Remove & Replace

* A reproducibility unit is defined as D2S or D2S% limit for multi-laboratory precision described in ASTM recommended practice C670.

The Sieve Test (AASHTO T59) results may be exempt from the Schedule of Price Adjustments provided the contractor's quality assurance program includes checking the uniformity of bituminous spread rates in increments no greater than 1 foot over the width of the spray bar and variation between increments is no greater than 5 percent.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

MOBILIZATION 011900-1

USDA FOREST SERVICE, R-4

Mahoghany.Specs.FINAL.11.19.2012

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

SUBMITTAL PROCEDURES 013300-1

USDA FOREST SERVICE, R-4

Mahoghany.Specs.FINAL.11.19.2012

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, Test Reports and other miscellaneous submittals.

See Table 013300-1 for a summary of required submittals.

B. See other specification section within this package for additional requirements on submittals.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

SUBMITTAL PROCEDURES 013300-2

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

SUBMITTAL PROCEDURES 013300-3

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Notation of dimensions established by field measurement.

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control”

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

SUBMITTAL PROCEDURES 013300-4

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution. Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required

SUBMITTAL PROCEDURES 013300-5

submittals for the project - the table is to assist the Contractor and may not be all inclusive – additional submittals may be required by specific specifications:

1.

TABLE 013300-1

Spec.

Section Section Title Subsec tion Required Submittal

Section C Section C 1.4 A Traffic Control and Signing Plan 014100 Quality Control 1.3 A Contractor quality control plan 014100 Quality Control 1.3 B Permits, Licenses, and Certificates 014100 Quality Control 1.3 C Test and inspection reports 014100 Quality Control 1.3 D As-Built drawings 023701 Sediment and Erosion Control

Measures 1.2A Sediment and Erosion Control

Plan 033000 Cast-in-Place Concrete 1.3 A Product Data

033000 Cast-in-Place Concrete 1.3 B Design Mix 033000 Cast-in-Place Concrete 1.3C Shop Drawings 033000 Cast-in-Place Concrete 1.3 D Quality Control Test Reports 033000 Cast-in-Place Concrete 1.3 E Concrete Color Sample 033000 Cast-in-Place Concrete 1.3F Expansion and Contraction Joint

Plan 033540 Colored Concrete Sidewalk 1.2A Product Sample 101400 Signs 1.3A Sign List 129410 Group Sites 1.2A Product Data 221100 Water Distribution Systems 1.3A Product Data 221100 Water Distribution Systems 1.3B Disposal Plan 221100 Water Distribution Systems 1.3C Operation & Maintenance Data 221100 Water Distribution Systems 1.3D Operation & Maintenance Manual 321200 Hot-Mix Asphalt Paving 1.2A Product Data 321200 Hot-Mix Asphalt Paving 1.2B Job Mix Design 321200 Hot-Mix Asphalt Paving 1.2C Material Certificate 321200 Hot-Mix Asphalt Paving 3.9 In-place Density and Thickness

Test Results 321204 Crushed Aggregate Base or Surface

Course 1.2A Aggregate Source, Gradation and

Material Properties

321204 Crushed Aggregate Base or Surface Course

1.2B Compaction Test Results

321206 Loose Rock Riprap 1.2 Rock Source and Properties 322625 Recycled Plastic Wheelstops 1.3A Product Data 322625 Recycled Plastic Wheelstops 1.3B Shop Drawings 322640 Pavement Markings 1.3A Product Data 323119 Ornamental Metal Barrier Fence 1.3A Product Data 323119 Ornamental Metal Barrier Fence 1.3B Shop Drawings 323119 Ornamental Metal Barrier Fence 1.3C Samples

SUBMITTAL PROCEDURES 013300-6

Spec.

Section Section Title Subsec tion Required Submittal

323119 Ornamental Metal Barrier Fence 1.3D Maintenance Data 323230 Segmental Retaining Wall 1.3A Product Data 323230 Segmental Retaining Wall 1.3B Samples 323230 Segmental Retaining Wall 1.3C Qualification Data 323230 Segmental Retaining Wall 1.3D Design Submittal 323230 Segmental Retaining Wall 1.3E Product Test Reports 323230 Segmental Retaining Wall 1.3F Product Certificates 329206 Seeding 2.1 Seed Mix 332228 Culvert Pipe and Pipe Arches 1.3A Culvert Pipe Schedule 332228 Culvert Pipe and Pipe Arches 1.3B Shop Drawings 332228 Culvert Pipe and Pipe Arches 1.3C Fabricators Certification

END OF SECTION 013300

QUALITY CONTROL 014100-1

USDA FOREST SERVICE, R-4

Mahoghany.Specs.FINAL.11.19.2012

SECTION 014100 - QUALITY CONTROL

PART 1 - GENERAL

1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.

1.2 QUALITY CONTROL

A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.

B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:

1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.

2. Testing agency will re-test and re-inspect corrected work.

C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.

1.3 SUBMITTALS

A. Contractor Quality Control Plan

B. Permits, Licenses, and Certificates

C. Test and Inspection Reports

D. As-Built Drawings

1.4 MEASUREMENT AND PAYMENT

A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.

QUALITY CONTROL 014100-2

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 QUALITY CONTROL SYSTEM

A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.

3.2 CONTRACTOR QUALITY CONTROL PLAN

A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.

1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.

2. The Government reserves the right to require changes in the plan during the contract period as necessary.

3. No change in the approved plan may be made without written concurrence by the Contracting Officer.

4. At a minimum, the plan shall include the following:

a. A list of personnel responsible for quality control and assigned duties.

Include each person's qualifications.

b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.

c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

d. Methods of performing, documenting, and enforcing quality control of all work.

e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.

3.3 TEST AND INSPECTION REPORTS

A. Submit three copies of complete test results no later than three calendar days after the test was performed.

B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.

C. Testing and Inspection Reports shall include the following:

1. Date of issue.

2. Project title and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples, tests, or inspections.

5. Names of individuals performing tests and inspections.

QUALITY CONTROL 014100-3

6. Reference Specification Section(s).

7. Complete test or inspection data.

8. Test and inspection results and an interpretation of test results.

9. Ambient conditions at time sample was taken, tested, or inspected.

10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.

11. Name and signature of laboratory inspector.

12. Recommendations on retesting and reinspecting.

3.4 PERMITS, LICENSES, AND CERTIFICATES

A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.

3.5 AS-BUILT DRAWINGS

A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions. These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.

3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS

A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:

B.

TABLE 014100-1

Item

Subsection Certification or Test Required

Frequency

033000 2.12 Mixing and Delivery Each Truck 033000 3.13 Concrete – Slump, Air, Temperature 1 composite per truck load delivered 033000 3.13 Concrete - Compression Test

Specimens at 7 days and 28 days (see spec)

221100 3.2P HDPE Pipe - Bent Strap Test Once Daily 221100 3.7A Hydrostatic Testing of Water

System See Spec.

221100 3.7B Pressure and Leakage Test – Water Line

See Spec.

QUALITY CONTROL 014100-4

221100 3.8A Bacteriological Examination After disinfection, before use 221300 3.11A System Test See Spec.

221300 3.11B Leak Test Prior to Backfill 221300 3.12A Residual Head Test Until Passing 221300 3.12B Leakage Test Until Passing 231126 3.10 LPG Pipe Test, Inspect, & Purge See Spec.

312000 3.13I Tracer Wire Conductivity Test Until Passing 312000 3.19 Compaction Test – at Pipe Zone One per 750 Feet of

Trench 312000 3.19 Compaction Test – at Pipe Zone One test – at each road and parking area crossing

312000 3.19 Compaction Test – above Pipe Zone

One per 750 Feet of Trench

312000 3.19 Compaction Test – above Pipe Zone

One test every other lift – at each road & parking crossing 312000 3.19 Compaction Test – Exterior

Concrete Slabs One per 400 sf, minimum of 1 per slab

312000 3.19 Compaction Test – Backfill/Fills and Subgrade under Buildings foundation and slab

One test per lift at each building

312000 3.19 Compaction Test – Backfill/Fills Septic Tanks and Vaults

One test for each Septic Tank or Vault

312000

323230

3.19

3.7A

Compaction Test – Backfill Segmented Walls

One test every other lift for every 100 feet of wall length 312000 3.14 Tracer Wire Conductivity Test Until Passing 312225 3.12B Moisture-Density Relationship One Test for Each

Soil Type Encountered

312225 3.12B & 1.3B

Compaction – Road Embankment (Method 4)

One test every 500

sq. yd. of embankment per every other lift (24 inch depth) 312225 3.12B &

1.3B Compaction – Road Embankment

(Method 4) One test every 50 sq.

yd. of embankment per lift in segmented wall areas.

QUALITY CONTROL 014100-5

312225 3.12B Compaction – Subgrade One test every 500

sq. yd. of subgrade 321200 3.7B Gradation and Asphalt Content One per 700 tons or

Min. of 1 per Project 321200 3.7C Field Density Tests – Asphalt One test for every

750 sq. yd. of pavement

321200 3.7D Thickness Tests – Asphalt One test for every 750 sq. yd. of pave-ment 321204 3.4A Compaction Tests – Road Base and

Surface Course One test for every

300 sq. yd. of Aggregate

321204 3.4A Compaction Tests – Aggregate Base for Concrete Slabs

One test for each group unit

321204 3.4A Compaction Tests – Aggregate Base for Concrete Slabs

One test for each pre-fab building pad

323230 1.4 Preinstallation Conference for Segmented Retaining Wall

Prior to beginning work

323230 3.7 Compaction Tests – Segmental Retaining Wall

One tests every other backfill lift per 100 feet of wall 332228 3.6C Compaction Tests One test for every

12 inches of lift placed

END OF SECTION 014100

SEDIMENT AND EROSION CONTROL MEASURES 023701-1

USDA FOREST SERVICE, R-4

Mahoghany.Specs.FINAL.11.19.2012

SECTION 023701 - SEDIMENT AND EROSION CONTROL MEASURES

PART 1 - GENERAL

1.1 The work under this section consists of furnishing all necessary labor, equipment, materials, and performing all operations in connection with construction sediment and control measures.

A. General

1. All erosion and sediment control measures are to be placed prior to any disturbance caused by grading and or excavation and shall conform to the requirements of the appropriate regulatory agency for the State.

2. The Contractor shall be solely responsible for ensuring that erosion and sediment control measures are implemented and maintained at the site.

3. Soil disturbing activities include but are not…