About this file

This Addendum 3 document is a revised Invitation to Bid issued by Sharon Housing Trust, Inc. for siding, windows, doors, trim, and paint work at three residential apartment buildings located at 91, 93, and 95 North Main Street in Sharon, Connecticut. The scope of work includes removal and replacement of approximately 85 windows (including 12 basement windows), six apartment front doors, one basement door, all vinyl siding and accessories, exterior trim, metal wrap, porch work, building modifications at 93 North Main Street, soffit and vent replacement, and chimney limewashing. The project also requires Connecticut-licensed asbestos and lead abatement contractors to handle hazardous materials identified in the 2023 Limited Hazmat Survey Report and 2024 Lead Management Plan. A mandatory site walk is scheduled for 10:00 a.m. on October 20, 2026, with a deadline for bid questions on October 21, 2026, and responses provided on October 23, 2026. The bid due date has been extended to 4:00 p.m. on November 6, 2026, with contractor selection anticipated by November 13, 2026. Add Alternate pricing is requested for front entry steps and railings at 91 and 95 North Main Street and for removal and replacement of the Bilco door and areaway foundation at 93 North Main Street.

Bidders must submit a fixed-price base bid and optional add alternate pricing electronically to LindsayL@thehousingcollective.org. The base bid includes a $75,000 window allowance for approximately 85 units with dollar-for-dollar contract adjustment based on actual invoiced costs. The minimum required qualifications include five years of relevant residential exterior renovation experience, Connecticut Home Improvement Contractor license, workers' compensation and general liability insurance with minimum $1,000,000 per occurrence, and EPA Lead-Safe Certified Firm status. No bid bond, payment bond, or performance bond is required, and the project is exempt from sales and use tax. State and federal prevailing wage rates are not applicable. Bidders must provide time-and-materials hourly rates for concealed rot and sheathing repair, with material markup percentages, though concealed conditions work is excluded from the fixed-price bid. The contract includes a minimum one-year workmanship warranty, manufacturer product and finish warranties, and work restrictions limiting hours to 7:30 a.m. to 5:30 p.m., Monday through Friday. Windows are identified as long-lead items with anticipated installation in early 2027, weather permitting.

View the file

Other files

File Type Posted
39372_Oct_26_26_solicitation_doc.pdf PDF
Addendum3_REVISED_Owner_Responses_Final.pdf PDF
39372_Nov_19_26_solicitation_doc.pdf PDF
39372_Nov_4_26_solicitation_doc.pdf PDF
39372_Nov_10_26_solicitation_doc.pdf PDF
39372_Nov_18_26_solicitation_doc.pdf PDF
VendorChangeDetailsReport_39372_v2_Oct_29_26.pdf PDF
39372_Nov_2_26_solicitation_doc.pdf PDF
SHT_919395_Bid_Drawings_20261009.pdf PDF
HazMat report 91 93 95.pdf PDF
39372_Nov_9_26_solicitation_doc.pdf PDF
39372_Oct_20_26_solicitation_doc.pdf PDF
39372_Nov_6_26_solicitation_doc.pdf PDF
39372_Oct_29_26_solicitation_doc.pdf PDF
39372_Nov_11_26_solicitation_doc.pdf PDF
39372_Nov_3_26_solicitation_doc.pdf PDF
39372_Oct_28_26_solicitation_doc.pdf PDF
Addendum2_SHT_DateChange.pdf PDF
39372_Nov_12_26_solicitation_doc.pdf PDF
Invitation to Bid_Windows_Siding_Doors_Sharon Homes_FINAL_20261009.pdf PDF
39372_Nov_13_26_solicitation_doc.pdf PDF
SNM Ex 04.8.c 2 Lead Mgmt Plan 91-95 North Main Street Sharon.pdf PDF
20261020_SHT_SiteWalk_Windows_Questions_Final2.pdf PDF
24127.003 91-95 North Main Street Sharon CT ACM OandM Plan.pdf PDF
SHT_919395_Preliminary_Window_Door_Schedule_20261009.pdf PDF
39372_Nov_17_26_solicitation_doc.pdf PDF
39372_Nov_5_26_solicitation_doc.pdf PDF
39372_Oct_15_26_solicitation_doc.pdf PDF
39372_Oct_30_26_solicitation_doc.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Invitation to Bid for Siding, Windows, Doors, Trim, and Paint Sharon Housing Trust, Inc.

Sharon Homes Apartments

91, 93, & 95 North Main Street Sharon, CT

Request Date: October 9, 2026

Revised per Addendums 1 & 3, as of October 28, 2026 Revisions shown in Red

Bid Due Date is being extended: Bids must be received by 4:00 p.m. on November 6, 2026

Table of Contents I. Overview II. Property Description III. Timeline for Bid Process IV. Minimum Required Qualifications V. Submission Instructions VI. Scope of Services – Windows and Doors VII. Scope of Services – Siding, Exterior Trim, Metal Wrap, and Porches VIII. Scope of Services – 93 North Main Street Building Modifications IX. Scope of Services – Add Alternate X. General Requirements (All Work) XI. Bid Form

I. Overview Sharon Housing Trust, Inc. (SHT) will receive bids from qualified contractors for Siding, Windows, Doors, Trim, and Paint work at 91, 93, and 95 North Main Street in Sharon, CT. The work consists of removing and replacing all existing windows, siding, and exterior trim; the six

(6) apartment front doors; the basement door at 95 North Main Street; porch work; and the Building Modifications at 93 North Main Street. SHT also requests pricing for an Add Alternate for the front entry steps at 91 and 95 North Main Street and the Bilco door and areaway foundation at 93 North Main Street. SHT requests that the following be presented:

1. A base bid for the removal and replacement of all windows, the six (6) apartment front doors, and the basement door at 95 North Main Street; removal of all existing vinyl siding, vinyl accessories, existing fanfold backer board, and painted metal trim wrap;

installation of a new weather-resistive barrier and new fanfold backer board; installation of new CertainTeed MainStreet vinyl siding, CertainTeed vinyl window and door casing, and new aluminum trim wrap at porch posts, porch beams, fascia, and rake; porch work;

all Hazardous-material abatement required for the work, performed by Connecticut-licensed abatement contractors; replacement of all soffits and other exterior vents;

replacement of the vinyl porch ceilings at 93 and 95 North Main Street; painting of the porch canopy gable ends and ceilings at 91 North Main Street; limewashing of the cinderblock chimney at 95 North Main Street; and the 93 North Main Street Building Modifications A–F, including the new porch entry steps, as specified below.

2. An Add Alternate, priced as two separate items: (A) removal and replacement of the front entry steps and railings at 91 and 95 North Main Street; and (B) removal and replacement of the Bilco door and its areaway foundation at 93 North Main Street, as specified below.

Bidders may, but are not required to, price the Add Alternate. A bid that omits the Add

Alternate will not be considered non-responsive. The low bidder will be determined on the Base Bid. SHT may award either Add Alternate item to the Base Bid contractor or separately.

A mandatory site walk is scheduled for 10:00 a.m. on October 20, 2026. Attendance is required to submit a bid.

You must email LindsayL@thehousingcollective.org to be added to the interest list to receive updates and addenda related to this Invitation to Bid.

This project does not require a bid bond or payment and performance bonds. This project is exempt from sales and use tax; bidders shall exclude sales and use tax from their bids. State and federal prevailing wage rates and reporting are not required. Contractor shall maintain workers ’ compensation and commercial general liability insurance meeting the requirements below and shall provide certificates of insurance before award. State-funded requirements for an Affirmative Action Plan, applicable procurement requirements and goals, and compliance with and approval by the Connecticut Commission on Human Rights and Opportunities (CHRO) are required.

The owner reserves the right to reject any and all bids or to waive any informalities in the bidding. No bid shall be withdrawn by the bidding contractor for a period of 90 days subsequent to the opening of bids without the consent of the owner.

Addendum No. 1 (Owner Responses to Requests for Information) and Addendum No 3 (REVISED Owner Responses to Requests for information) are part of the bid documents. This Invitation to Bid and the Bid Form have been revised to incorporate it. All scope added by Addendum No. 1 and Addendum No. 3 are included in the Base Bid. The bid due date has been extended to November 6, 2026.

II. Property Description Sharon Homes are 6 affordable rental apartments in 3 separate, two-story buildings. All units are fully occupied. There are approximately 85 windows (including 12 basement windows), six (6) apartment front doors, and one (1) basement door at 95 North Main Street, across the 3 buildings.

A preliminary window schedule is included as a separate attachment, together with the bid drawings (Sheets T-001 and A-200 through A-202, Bid Set dated October 9, 2026). Where the drawings conflict with this Invitation to Bid or the window schedule, this Invitation to Bid and the window schedule govern. Where Addendum No. 1 and Addendum No. 3 conflict with this Invitation to Bid, the window schedule, or the drawings, the Addendum governs. Contractors are responsible for confirming all quantities and field measurements before ordering materials. The 2023 Limited Hazmat Survey Report (Big East Environmental, Project #23622.01) and Operations and Maintenance Plan for Asbestos-Containing Materials, and the 2024 Lead Management Plan, are available to bidders and shall be reviewed before bidding. The 2023 survey identified lead paint in all three buildings and asbestos-containing joint compound at 91 North Main Street, asbestos-containing window glazing at 95 North Main Street, and assumed asbestos-containing vermiculite in the attic at 95 North Main Street. The assessment also identified suspect PCB-containing window glazing and window and door caulking at all three buildings; these materials were not sampled. The Contractor is responsible for all hazardous-material abatement required for the work, and this work is included in the Base Bid. Asbestos abatement shall be performed by a Connecticut-licensed asbestos abatement contractor, and any lead abatement by a Connecticut-licensed lead abatement contractor; either may be the contractor or its subcontractor. The contractor shall provide all required notifications and permits, workers protection, air monitoring and clearance required by regulation, and transport and disposal of mailto:LindsayL@thehousingcollective.org hazardous waste in accordance with applicable regulations, and shall coordinate sequencing. The existing windows at 95 North Main Street with asbestos-containing window glazing (approximately 24 units identified in the 2023 survey) shall be removed intact, without disturbing the glazing, by the licensed asbestos abatement contractor. Suspect PCB-containing window glazing and window and door caulking shall be sampled before it is disturbed; any material confirmed to contain PCBs shall be removed and disposed of in accordance with the EPA and Connecticut DEEP requirements. Bidders shall list all hazardous-materials assumptions. Painted surfaces, including the existing cedar shingle siding, window trim, and wood concealed beneath existing metal trim wrap, shall be presumed to contain lead-based paint. Cutting back shingles at window openings, removing metal trim wrap, and any other work that disturbs painted surfaces is renovation work, not abatement. Bidders shall include this work as part of their base price. All work to be completed in accordance with the work-practice requirements of 40 CFR § 745.85.

All three buildings are under the purview of the State Historic Preservation Office (SHPO). The existing cedar shingle siding and any underlying wood porch columns, beams, and trim shall be preserved during removal of the vinyl siding and metal trim wrap and installation of the new work.

III. Timeline for Bid Process Invitation to Bid issued: 10/09/2026 Mandatory site walk: 10:00 a.m., 10/20/2026 Deadline for submitting bid questions: 10/21/2026 Responses provided to bid questions: 10/23/2026 Bids due: 4:00 p.m., 11/6/2026 Contractor selected by: 11/13/2026

IV. Minimum Required Qualifications

1. Five years of relevant residential exterior renovation, siding, and window installation experience.

2. Home Improvement Contractor license by the State of Connecticut.

3. Workers Compensation Insurance.

4. General liability insurance with a minimum of $1,000,000 in coverage per occurrence.

5. Bidder shall be an EPA Lead-Safe Certified Firm and shall use Certified Renovators in accordance with 40 CFR §§ 745.89 and 745.90 and the work-practice requirements of 40

CFR § 745.85.

V. Submission Instructions Submit your bid electronically to LindsayL@thehousingcollective.org no later than 4:00 p.m. on November 6, 2026.

Bid packages shall include the completed revised Bid Form; Connecticut HIC license; certificates of workers ’ compensation and general liability insurance; EPA Lead-Safe Certified Firm documentation; three professional references for comparable occupied residential work; a list of all exclusions and assumptions; and the bidder’s earliest available start date and estimated construction duration.

VI. Scope of Services – Windows and Doors

• Except for the window material allowance and concealed rot, sheathing, framing, or hazardous-material work specifically identified as time-and-materials or excluded below, provide a complete fixed-price bid for all labor, supervision, materials, fasteners, flashing, mailto:LindsayL@thehousingcollective.org sealants, equipment, access, temporary protection, cleanup, dumpster fees, and debris removal required for a complete installation. Scope shall include:

• Remove each existing window completely to the rough opening, including existing frame components that must be removed for a full-frame installation, and dispose of debris.

• At each window opening, remove all existing painted metal trim wrap, vinyl J-channel, and exterior wood trim. Cut back the existing cedar shingles as required and install flat, continuous blocking so that the window flange, flashing, and exterior casing lineal bear on a true, flat surface.

• Install full-frame, new-construction-style windows (not insert/replacement windows), using integral installation flanges where provided by the selected window product.

• Windows on the elevation of each building facing North Main Street, as identified on the Sheet T-001 key plan, shall be Andersen E-Series or 500 Series full-frame windows. All other windows, including basement windows, shall be Andersen 100 Series full-frame windows. Lite patterns shall match the elevation drawings; grilles shall be simulated divided lites. SHT will make final product selections at ordering under the window allowance and may select an equivalent product where a scheduled unit is unavailable. Contractor shall field-verify every rough opening and final unit size before ordering. Rough openings shall not be enlarged. A window may be up to 1 inch smaller in height or width only. Contractor shall be responsible for ordering correct windows and, in the event that a window needs to be re-ordered due to not fitting, shall provide that window free of charge.

• Provide all manufacturer-required installation flanges, shims, fasteners, sill-pan or sill flashing, jamb flashing, head flashing/drip cap, compatible sealants, and a continuous interior perimeter air seal. Integrate flashing with the new WRB specified below.

• Install closed cell non-expanding foam insulation between window jamb and rough opening.

• Before ordering, confirm with SHT the operation, handing, interior and exterior color, grille pattern, screens, hardware, glazing, and any special window requirements shown on the final window schedule. Provide insect screens and standard manufacturer hardware for all operable windows unless the schedule states otherwise (screens and hardware are part of window allowance).

• Windows serving sleeping rooms shall meet the emergency escape and rescue opening requirements of the Connecticut State Building Code, or its replacement-window provisions where they apply. Each bedroom shall have at least one compliant window. Where an existing opening is too small, install the largest standard double-hung unit that fits the existing rough opening; do not enlarge openings. Contractor shall verify each sleeping-room window, obtain the building inspector’s approval before ordering, and notify SHT of any unit that cannot comply.

• Windows in bathrooms shall have tempered glazing.

• At windows in finished living spaces, trim interior with 1x4 casing, 5/4 bullnose sill, and 1x4 apron; interior trim boards to be finger-jointed pine. Basement and unfinished attic windows do not receive interior trim.

• Where necessary, fabricate and install extension jambs from 1-inch nominal finger-jointed pine stock.

• Fill fastener holes, caulk joints, spot-prime bare wood and filler as required, and paint interior trim with two finish coats of Benjamin Moore Regal Select; paint color and sheen to be selected by SHT.

• Patch, sand, prime, and paint interior drywall disturbed by the work to match the adjacent finish. Where a spot repair will not reasonably match, paint the affected wall plane from corner to corner.

• Install all windows in accordance with the window manufacturer’s current written installation instructions, including required flashing, sealing, shimming, insulation and fastening.

• Front Doors: Remove and dispose of the existing front entry door, frame, threshold, and exterior and interior trim at each of the six (6) apartment front doors: 91 North Main Street D- 1 and D-2; 93 North Main Street D-2 and D-3; 95 North Main Street D-1 and D-2. Door D-1 at 93 North Main Street is replaced by a window under Building Modification B. Rear doors D-4 and D-5 are not included. These are the apartment entry doors; no storm doors are included. Existing porch screen doors are removed and not replaced (Sheet Note 4).

• Furnish and install new prehung fiberglass entry doors, smooth skin, 4-panel Shaker style, insulated core, in a rot-resistant composite frame with adjustable sill and compression weatherstripping. Basis of design: Therma-Tru Smooth-Star Shaker, or approved equal.

Field-verify each opening and size units to fit the existing rough openings without enlarging them. Handing and swing to match existing unless directed otherwise by SHT.

• Provide an ANSI/BHMA Grade 2 entry lockset and a single-cylinder deadbolt at each door.

Finish and keying as directed by SHT.

• Provide sill pan flashing and integrate door head, jamb, and sill flashing with the new WRB.

Trim door exteriors with the CertainTeed casing lineal specified for windows, with head flashing/drip cap. Trim door interiors to match the window interior trim specified above.

• Prime where not factory-finished, and paint both faces of each door with two finish coats of exterior paint; color by SHT.

• Each apartment shall have a secure, lockable entry door at the end of every workday.

• Basement Door at 95 North Main Street: Remove and dispose of the existing partial-height basement door, frame, and trim. Furnish and install a new flush, unglazed, insulated galvanized steel door in a galvanized steel frame, approximately 3'-0" wide x 4'-0" high (custom size; field-verify), with weatherstripping, sill, and a keyed lockset (keying as directed by SHT). Provide sill pan flashing integrated with the new WRB and trim the exterior with the CertainTeed casing lineal specified for windows. Prime and paint with two finish coats of exterior paint; color by SHT.

VII. Scope of Services – Siding, Exterior Trim, Metal Wrap, and Porches

• In addition to the window work, remove and dispose of all vinyl siding and vinyl accessories

(J-channel, starter strips, corner posts, and undersill trim) on all three buildings. The existing cedar shingle siding shall remain in place.

• Install new fanfold foam backer board over the new WRB on all walls of all three buildings, of a thickness sufficient to bridge the existing shingle courses and provide a flat, continuous substrate for the vinyl siding (minimum 3/8 inch). Where fanfold backer board is currently installed behind the vinyl siding, remove and dispose of it.

• After stripping each wall, inspect exposed and accessible cedar shingles, trim, and framing (intact shingles need not be removed for inspection) and promptly notify SHT of concealed deterioration. No time-and-material repair shall proceed without SHT’s written authorization.

Photograph concealed conditions before repair and before they are covered.

• Hydrogap, or approved equal as the weather-resistive barrier, installed over the existing cedar shingles on all walls. Tape seams and penetrations with manufacturer-approved accessories and integrate the WRB continuously with window, door, roof-to-wall, and other flashing.

• Basis of design for vinyl siding: CertainTeed MainStreet Double 4-inch clapboard. Color to be selected by SHT. Provide starter strip, corner posts, undersill trim, and all other siding accessories from the same manufacturer. Install fasteners, fastener spacing, laps, and expansion clearances in accordance with CertainTeed’s current written installation instructions. No substitutions without SHT’s written approval.

• Trim all window and exterior door exteriors with CertainTeed 3-1/2-inch vinyl window and door casing lineal at the head, jambs, and sill, with the starter and accessories required by CertainTeed, installed in accordance with CertainTeed’s current written installation instructions. Siding shall terminate into the lineal’s receiving channel or the accessory CertainTeed specifies for that lineal; surface-applied J-channel shall not be used as window trim. Install head flashing/drip cap above each head lineal, integrated with the WRB, and maintain required drainage paths at window heads and sills. Color to be selected by SHT. No metal trim coil or metal wrap shall be installed at any window.

• Install new vinyl outside and inside corner posts from the same siding manufacturer, sized for the selected siding profile. Provide corrosion-resistant cap/Z-flashing over horizontal trim and at transitions where water can enter; integrate all flashing with the WRB.

• Remove existing painted metal trim wrap at all fascia and rake boards. Inspect the underlying wood and notify SHT of deterioration in accordance with the concealed-conditions provisions above. Re-cover all fascia and rake boards with new factory-finished aluminum trim coil, custom-bent to profile, color to be selected by SHT, fastened with color-matched, corrosion-resistant fasteners.

• Soffits (all buildings): Remove and dispose of all existing soffit panels, soffit vents, and soffit trim on all three buildings. Install new vinyl soffit from the same manufacturer as the siding (CertainTeed), with vented panels and matching trim, installed in accordance with the manufacturer’s current written instructions and coordinated with the new fascia wrap; color to be selected by SHT. Provide at least the existing net free attic ventilation area and do not block attic ventilation openings. Notify SHT of concealed deterioration of the soffit framing in accordance with the concealed-conditions provisions above.

• Remove existing painted metal trim wrap at all porch posts and porch beams. Inspect the underlying wood and notify SHT of deterioration in accordance with the concealed-conditions provisions above. Re-wrap all porch posts and beams with new factory-finished aluminum trim coil, custom-bent to fit, color to be selected by SHT, fastened with color-matched, corrosion-resistant fasteners. Hold the bottom edges of post wraps clear of porch floors so that water drains and is not trapped.

• Detach and reinstall gutters and leaders as required for the work. Replace all existing exterior wall vents on all three buildings with new vents. At lights, receptacles, hose bibs, vents, and other wall penetrations, provide CertainTeed mounting blocks or the manufacturer-specified accessory, and remove, reset, and reflash fixtures. Electrical work shall be performed by a Connecticut-licensed electrician.

• Porches (all buildings): Perform porch work in accordance with Sheet Notes 1 through 8 on Sheets A-200 through A-202 and Addendum No. 1 and Addendum No. 3. Existing porch structure, roofs, and decking remain. Remove all porch screen panels and screen doors and do not reinstall. At 93 and 95 North Main Street, the existing half-height solid porch walls remain and receive new WRB, fanfold backer board, and vinyl siding. Replace all porch lattice and skirting with PVC or composite lattice (no wood) in a perimeter trim frame, color to match the new siding. Notify SHT of loose or rotted deck boards; repair or replacement only with SHT’s written authorization at the time-and-material rates in the Bid Form.

• Porch Ceilings (93 and 95 North Main Street): Remove and dispose of the existing vinyl porch ceilings and install new vinyl ceiling panels with matching trim; color to be selected by

SHT.

• Porch Canopies (91 North Main Street): The canopy roofs and shingles remain (Sheet Note 2). Remove the existing metal wrap at the canopy posts and beam and re-wrap in new aluminum (Sheet Note 6), and re-wrap the fascia and rake in aluminum as specified above.

Prepare and paint the canopy gable ends and canopy ceilings with two finish coats of exterior paint, color to match the new siding.

• Chimney (95 North Main Street): Clean and limewash the existing cinderblock chimney with Romabio limewash, applied in accordance with the manufacturer’s instructions; color to be selected by SHT.

VIII. Scope of Services – 93 North Main Street Building Modifications

• Perform Building Modifications A through F at 93 North Main Street as shown and noted on

Sheet A-201. This work is included in the Base Bid. Modification F (new porch entry steps) shall be constructed to the step specification in Add Alternate Item A below. The new front porch entry steps at 93 North Main Street (Modifications C and F) are included here only and shall not be priced elsewhere.

IX. Scope of Services – Add Alternate

• Add Alternate Item A – Front Entry Steps and Railings (91 and 95 North Main Street):

Remove and dispose of the existing wood front entry steps, stringers, landings, and railings serving doors D-1 and D-2 at 91 North Main Street and doors D-1 and D-2 at 95 North Main Street, per Sheet Note 7. Rear and secondary steps are not included. New steps shall remain within the existing footprint; field-verify dimensions.

• Construct new steps and landings with pressure-treated framing on footings as required by code. Riser heights and tread depths shall be uniform and shall comply with the Connecticut State Building Code. Provide closed risers. Provide handrails and guards where required by code; handrails shall be graspable.

• Treads, risers, and landing decking: composite decking, Trex or Azek, or approved equal;

color by SHT. Stringer spacing, fasteners, and fascia per the decking manufacturer’s stair requirements.

• Railings: composite or PVC railing system, Trex or Azek, or approved equal, compatible with the decking; color by SHT.

• Maintain safe access to each apartment at all times. Provide temporary steps where permanent steps are not complete at the end of a workday.

• Add Alternate Item B – Bilco Door at 93 North Main Street: Remove and dispose of the existing basement bulkhead door and the deteriorated areaway foundation walls and sill, to sound material.

• Rebuild the areaway foundation walls and sill in concrete or grouted masonry, parged, level, and sized to the new door manufacturer’s requirements.

• Furnish and install a new steel basement door, Bilco Classic Series or approved equal, sized to the rebuilt areaway, factory-primed and finish-painted; color by SHT. Flash the top flange to the building wall, integrated with the WRB and siding, in accordance with the manufacturer’s instructions. Complete this work before siding is installed on the adjacent wall.

• If either Add Alternate item is awarded to a separate contractor, the Base Bid contractor shall coordinate sequencing and access with that contractor.

X. General Requirements (All Work) Quote Should Not Include:

Concealed rot, sheathing, or framing repair is excluded from the fixed-price bid and will be performed only with SHT’s written authorization at the time-and-material rates and material markup stated in the Bid Form.

• Insulation. Cellulose insulation will be installed from the exterior by others under a separate contract (see Other Conditions).

Quotes Should Include:

• All materials specified in this Invitation to Bid.

• All hazardous-material abatement for the work, performed by Connecticut-licensed asbestos and lead abatement contractors, including removal of the asbestos-glazed windows at 95 North Main Street, sampling and handling of suspect PCB materials, required notification and permits, air monitoring and clearance required by regulation, and transport and disposal. (See section II)

• $75,000 allowance for the actual invoiced purchase price and freight for windows, covering the approximately 85 units on the attached preliminary window schedule, including screens and standard hardware. Window installation labor and all installation materials are included elsewhere in the fixed-price bid. Contractor shall provide supplier invoices, and the Contract Sum shall be adjusted dollar-for-dollar for the difference between the allowance and actual invoiced cost, with no additional markup.

• All fasteners, WRB, flashing membranes, sealants, backer rod/low-expansion window foam, trim accessories, ventilation/drainage materials, and incidental materials required for a complete installation.

• Removal of all windows, doors, siding, and other debris (contractor shall provide dumpster).

• Sweeping and cleaning disturbed interior areas; raking clean exterior areas.

• Time and materials rates, including markup if any, for replacement of sheathing and rot uncovered underneath siding and metal trim wrap, and for authorized porch deck board repair.

• Any equipment necessary to complete work.

• All permit applications, permit coordination, required inspections, scaffolding/lifts, temporary protection, and access equipment required to complete the work. Include permit fees in the bid unless SHT states by addendum that a fee will be waived or paid directly.

• A written construction schedule showing anticipated start date, estimated duration, sequencing by building/unit, and long-lead material procurement. Bidder shall identify any owner decisions or submittals required before ordering.

Other Conditions:

• SHT shall inspect concealed rot or deterioration with the Contractor after siding is removed.

Contractor shall not cover authorized concealed repairs until SHT has had a reasonable opportunity to inspect the completed repair.

• Time-and-material work shall be documented on daily tickets showing labor hours and materials, signed by the Contractor and SHT’s representative.

• Disruption to tenants shall be minimized. Contractor shall complete removal, weatherproofing, installation, interior trim, and required cleanup for all windows in each apartment before moving to the next apartment, unless SHT approves otherwise. Contractor shall provide at least 48 hours’ notice before entering or commencing work in any occupied unit.

• Protect tenant furnishings, floors, landscaping, roofing, paving, and adjacent finishes from dust, debris, water intrusion, and damage. Maintain safe tenant access and required exits.

Remove tools, loose debris, and hazardous materials from tenant-accessible areas at the end of each workday.

• Contractor shall be responsible for daily cleanup and final cleaning of all work areas, including HEPA vacuuming and lead-safe cleaning where required by applicable lead regulations.

• All windows, doors, and siding shall be installed to manufacturers’ specifications.

• Each building and every window opening shall be left weather-tight and secure at the end of each workday and at all times when work is unattended, using temporary protection where permanent work is incomplete.

• Work shall only be performed between 7:30 a.m. and 5:30 p.m., Monday through Friday, unless SHT gives prior written approval for work outside those hours.

• Provide a minimum one-year workmanship warranty from the date of SHT’s final acceptance and deliver all manufacturer product and finish warranties to SHT at closeout.

• Cellulose insulation will be installed from the exterior by others under a separate contract.

Contractor shall coordinate sequencing and access with that work as directed by SHT.

• Windows are expected to be long-lead items, and window installation may occur in early 2027, weather permitting. Other scope may proceed in advance. The construction schedule will be finalized with the selected Contractor.

BID FORM

Sharon Homes – Siding, Windows, Doors, Trim, and Paint

91, 93, 95 North Main Street, Sharon, CT 06069 Revised per Addendum No. 1 and Addendum No. 3

Owner: Sharon Housing Trust, Inc.

P.O. Box 1168, Sharon, CT 06069

The undersigned, having familiarized themselves with the local conditions affecting the cost of work, and with the information contained in the Invitation to Bid, all attachments and all addenda, for the project as listed above, hereby proposes to furnish all labor, materials, equipment and services required to complete this work to the fullest extent and intent of all the work described for the following detailed amounts as follows:

BID SCHEDULE OF VALUES

Base Bid

Element Quantity Unit Price Total

Removal and replacement of all windows. Include all labor, materials except windows, and debris removal.

(Fixed Price) Removal of the asbestos-glazed windows at 95 North Main Street is priced in the Hazardous-Material Abatement line. Includes installing new windows at those openings.

1 $ $

Remove all existing vinyl siding and accessories, and existing fanfold; install specified WRB, new fanfold backer board on all walls, CertainTeed MainStreet vinyl siding, corner posts, and accessories. Include all labor, materials, access, and debris removal. (Fixed Price)

1 $ $

Exterior window trim: remove existing metal wrap, J-channel, and exterior wood trim; prepare openings; install CertainTeed casing lineals and head flashing. Include all labor, materials, and debris removal. (Fixed Price)

1 $ $

Remove existing painted metal trim wrap at porch posts, porch beams, fascia, and rake; install new factory-finished aluminum trim coil. Include all labor, materials, access, and debris removal. (Fixed Price)

1 $ $

Porch work per Sheet Notes 1–8 and Addendum No. 1 and Addendum No. 2: remove porch screen panels and screen doors; WRB, fanfold, and vinyl siding at solid porch walls;

replace lattice and skirting; replace vinyl porch ceilings at 93 and 95; paint canopy gable ends and ceilings at 91.

Include all labor, materials, and debris removal. (Fixed Price)

1 $ $

Soffits, Vents, and Chimney (Addendum No. 1): remove and replace all soffits with new vinyl soffit, including vented panels and trim, and replace all other exterior vents (all buildings); limewash cinderblock chimney at 95 North Main Street. Include all labor, materials, and debris removal. (Fixed Price)

1 $ $

93 North Main Street Building Modifications A–F (Sheet A-201), including new porch entry steps (Modification F).

Include all labor, materials, and debris removal. (Fixed Price)

1 $ $

Remove and replace six (6) apartment front doors, including frames, hardware, flashing, interior and exterior trim, and painting. Include all labor, materials, and debris removal. (Fixed Price)

6 $ $

Remove and replace partial-height basement door and frame at 95 North Main Street, including hardware, flashing, trim, and painting. Include all labor, materials, and debris removal. (Fixed Price)

1 $ $

Trim interior of windows in finished living spaces, paint, patch sheetrock where disturbed. Include all labor, materials, and debris removal. (Fixed Price).

1 $ $

Hourly labor rate(s) for authorized concealed rot, sheathing, framing, and trim repair. Identify crew composition and applicable hourly rates. Within quantity, provide non-binding estimate of number of hours necessary. Rates only; not included in the Grand Total.

$ N/A

Hazardous-Material Abatement (Addendum No. 1): all asbestos and lead abatement required for the work, by Connecticut-licensed abatement contractors, including removal and disposal of approximately 24 asbestos-glazed windows at 95 North Main Street and sampling and handling of suspect PCB materials. Include notifications, permits, required monitoring, transport, and disposal.

(Fixed Price)

1 $ $

Window allowance 1 $75,000 $75,000

Grand Total $

Add Alternate (optional – see Section I)

Element Quantity Unit Price Total

Add Alternate Item A: Remove and replace front entry steps, landings, and railings at 91 North Main Street (D-1, D-2) and 95 North Main Street (D-1, D-2). Include all labor, materials, and debris removal. (Fixed Price)

1 $ $

Add Alternate Item B: Remove and replace Bilco door and areaway foundation at 93 North Main Street. Include all labor, materials, and debris removal. (Fixed Price)

1 $ $

Add Alternate Total $

Markup on materials provided during time and materials work _____% Addenda received and acknowledged: No. ____ through No. ____

Date: ______________________________

By: _________________________________________________________________________ Print name and title, and sign

Name of Company: ____________________________________________________________

Address: _____________________________________________________________________

File details come from the government source that posted it. Updated .