Addendum 7 Traction Power Sub Meter RFP .pdf
PDF 364 KB Posted
- Solicitation number
- BD-19-1206-40000-40000-36461
- Issued by
- Suffolk County, Massachusetts
About this file
This document is an Addendum to RFP #38F-19 Traction Power Sub Meter Pilot Project, issued by the Massachusetts Bay Transportation Authority (MBTA). The addendum provides updates and clarifications to the original RFP, including a revised response due date of May 22, 2019 at 3:00 p.m. for the public opening at the MBTA offices in Boston, Massachusetts. The RFP seeks proposals for a traction power sub-meter pilot project, with the addendum specifying additional materials required, such as a LAN switch model with certain features and a 4-port 1GB module.
The RFP is for a state and local contract opportunity in Massachusetts, specifically in Suffolk County and the city of Boston. Acknowledgment of the addendum is required in the proposal submittal, and all other terms of the RFP remain as previously stated.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BTA Lo go, Charles D. Baker, Governor, Karyn E. Polito, Lieutenant Governor, Stephanie Pollack, MassDOT Secretary & CEO, Luis Manuel Ramírez, General Manager & CEO, MassDOT logo
Massachusetts Bay Transportation Authority
Ten Park Plaza, Suite 3910, Boston, MA 02116 www.mbta.com
May 16, 2019
SUBJECT: RFP # 38F-19 Traction Power Sub Meter Pilot Project
Addendum No. 7
Dear Bidders:
Please be advised that the above has been amended and/or clarified herein. All references in
RFP #38F-19 Traction Power Sub Meter Pilot Project.
1. New Opening Time below in red:
Response Due Date
Public Opening at MBTA Offices
10 Park Plaza Suite 2810
Boston, MA 02116
05/22/2019
3:00 p.m.
2. Switch specification:
Specification Section 01010- Summary of Work provides a general description of materials to be provided and labor to performed at each site. Part 1.3.E describes the materials and labor required at Washington Village. Add the following materials to this section:
LAN Switch
Model Total 10/100/1000 or Multigigabit copper ports
Default AC power supply
Available
PoE power
Cisco
StackWise-
Cisco
StackPower
C9300-
24T
24 350W AC Yes Yes
With L2 license and DNA essentials (see table 8 and 9 from link below https://www.cisco.com/c/en/us/products/collateral/switches/catalyst-9300-series-switches/data_sheet-c78-738977.html#SoftwareRequirements
And add a 4 port 1GB module populated with 2 Cisco SFP
C9300-NM-4G 9300 Series 4x 1G Network Module
1000BASE-LX/LH long-wavelength; with DOM https://www.cisco.com/c/en/us/products/collateral/switches/catalyst-9300-series-switches/data_sheet-c78-738977.html#SoftwareRequirements https://www.cisco.com/c/en/us/products/collateral/switches/catalyst-9300-series-switches/data_sheet-c78-738977.html#SoftwareRequirements
Acknowledgment of this Addendum must be so noted in your proposal submittal.
ALL ELSE REMAINS AS PREVIOUSLY STATED.
Sincerely, John de Lalla
John de Lalla, Sourcing Executive
File details come from the government source that posted it. Updated .