This document is an Addendum to Request for Proposals (RFP) #38F-19 for a Traction Power Sub Meter Pilot Project issued by the Massachusetts Bay Transportation Authority (MBTA). The RFP seeks proposals for a sub-metering pilot project, with a site visit scheduled for April 2, 2019 and responses due on April 17, 2019. The contract execution is estimated for April 30, 2019 with a service start date of May 8, 2019. The RFP covers Suffolk County and the City of Boston in Massachusetts.
The Addendum provides clarification on the RFP calendar, including a pre-bid conference call on March 25, 2019 and the deadline for submitting questions on April 8, 2019, with the MBTA's official answers published on April 10, 2019. The Addendum also notes that the site visit will be limited to attendees of the pre-bid meeting. Pricing terms, set-asides, funding sources, and other salient financial information are not provided in the Addendum.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BTA Lo go, Charles D. Baker, Governor, Karyn E. Polito, Lieutenant Governor, Stephanie Pollack, MassDOT Secretary & CEO, Luis Manuel Ramírez, General Manager & CEO, MassDOT logo
Massachusetts Bay Transportation Authority
Ten Park Plaza, Suite 3910, Boston, MA 02116 www.mbta.com
March 20, 2019
SUBJECT: RFP # 38F-19 Traction Power Sub Meter Pilot Project
Addendum No. 1
Dear Bidders:
Please be advised that the above has been amended and/or clarified herein. All references in
RFP #38F-19 Traction Power Sub Meter Pilot Project. The Site visit will be April 2, 2019.
TABLE 2-1: RFP CALENDAR – Traction Power Sub Metering Pilot Project
Procurement Activity Date Time
RFP issued 3/18/2019 C.O.B.
Pre-bid conference call 605-562-0400, Code 2295149 3/25/2019 11:00 a.m.
Site Visit – only available to attendees of Pre-Bid meeting, we will limit the number within the substation room.
4/2/2019
8:30 -12:00
Deadline for submission of Proposer questions to
COMMBUYS
4/8/2019
2:00 p.m.
Official Answers for Bid Q&A published by MBTA on
COMMBUYS
4/10/2019
2:00 p.m.
Response Due Date
Public Opening at MBTA Offices
10 Park Plaza Suite 2810
Boston, MA 02116
4/17/2019
2:00 p.m.
Contract Execution (estimated) 4/30/2019
Service Start Date (estimated) 5/8/2019
Acknowledgment of this Addendum must be so noted on your proposal submittal.
ALL ELSE REMAINS AS PREVIOUSLY STATED.
Sincerely, John de Lalla