Addendum 4.pdf

PDF 193 KB Posted

Attached to
472/22442. JBB; MBP - Primary Elec. Infrastructure Upgrades
Solicitation number
RFQ - 171 - 240000000053
Issued by
Alger County, Michigan

About this file

This document is Addendum 4 to the Marquette Branch Prison - Primary Electrical Infrastructure Upgrades project, File # 472/22442.JBB, in Lansing, Michigan. The addendum provides clarifications and responses to questions from bidders, including the location of a 60kVA transformer, the scope of work for replacing primary feeders and cables, available laydown space, the location of a "cage" panel, and whether a handhole should be changed to a two-position switch. The related state and local contract opportunity involves the same project and provides instructions for submitting questions and proposals electronically through the SIGMA VSS system.

The addendum and contract opportunity indicate that the project involves upgrading the primary electrical infrastructure at the Marquette Branch Prison, with bids due by a 2:00 pm deadline. The contract will be awarded by the State of Michigan, and the project is located in Alger County. Bidders are advised to submit questions via email rather than through the VSS system, and to notify the Office of Design and Construction if they experience issues with the electronic submission process.

View the file

Other files

File Type Posted
Addendum 2.pdf PDF
Technical Specifications.pdf PDF
Drawings-2.pdf PDF
DTMB-0415 Advertisement (Rev 10-22).pdf PDF
LEIN Request 22442.pdf PDF
Front End Specification.pdf PDF
Addendum 3.pdf PDF
Prevailing Wages 231024 Marquette County 22442.pdf PDF
Addendum 1.pdf PDF
Drawings-1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1601 E. CÉSAR E. CHÁVEZ AVENUE, LANSING, MI 48906

PHONE: (517) 487-2511

FAX: (517) 487-2544

ADDENDUM NO. 4

Date: 12/08/23

Project Name: Marquette Branch Prison - Primary Electrical Infrastructure Upgrades

File # 472/22442.JBB

Funding Code # 472/MBPMaintProj

This Addendum is issued for the purpose of modifying and/or clarifying the original Contract

Documents and shall take precedence over them.

All work included herein shall be in accordance with the original drawings and specifications except as specifically noted herein. All incidental items required to provide the following modifications shall be included even though not specifically described.

This addendum is being sent to all bidders receiving plans and specifications. Receipt of this

Addendum shall be noted on the Bid Summary in the appropriate location.

Clarification and Questions:

A4.1 Question: Can you please provide the location of this 60kva xfmr.

Response: This transformer is in the powerhouse.

ADDENDUM NO. 4

A4.2 Question: Are the primary feeder and cables being removed and replaced under provisionary allowance? Is there a page in the specs that shows me exactly what is expected to come from that allowance?

Response: All primary feeders are being replaced unless noted otherwise as a part of the base bid for the project. The allowance is for future changes to the project.

A4.3 Question: Is there space for laydown of materials?

Response: Yes, the Northeast corner of the facility, outside the secure will have space for laydown of material as well as jobsite trailers

A4.4 Question: Where is the location of the “cage” panel is?

Response: Located in basement of Admin Building, within 200’of transformer

A4.5 Question: Should handhole in Aerial line ahead of PMH be changed to a two position switch.

Response: Yes

End of Addendum 4