Addendum 1.pdf

PDF 330 KB Posted

Attached to
472/22442. JBB; MBP - Primary Elec. Infrastructure Upgrades
Solicitation number
RFQ - 171 - 240000000053
Issued by
Alger County, Michigan

About this file

This document is an Addendum for the Marquette Branch Prison - Primary Electrical Infrastructure Upgrades project, Bid File #472/22442.JBB, in Lansing, Michigan. The addendum extends the bid due date by one week to December 13, 2023, and provides clarification and specifications for transformer bases and new handholes. Additionally, the addendum states that the last addendum will be issued on December 1, 2023, and includes a sign-in sheet.

The related state and local contract opportunity is for the Marquette Branch Prison - Primary Electrical Infrastructure Upgrades project, Bid File #472/22442.JBB, in Alger County, Michigan. The project description instructs bidders to submit questions via email rather than through the online VSS system, and to upload bid attachments to the SIGMA VSS system. It also provides guidance on the submission process, including information about the maximum file size and the need to contact the Office of Design and Construction if experiencing SIGMA VSS issues.

View the file

Other files

File Type Posted
Addendum 2.pdf PDF
Technical Specifications.pdf PDF
Addendum 4.pdf PDF
Drawings-2.pdf PDF
DTMB-0415 Advertisement (Rev 10-22).pdf PDF
LEIN Request 22442.pdf PDF
Front End Specification.pdf PDF
Addendum 3.pdf PDF
Prevailing Wages 231024 Marquette County 22442.pdf PDF
Drawings-1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1601 E. CÉSAR E. CHÁVEZ AVENUE, LANSING, MI 48906

PHONE: (517) 487-2511

FAX: (517) 487-2544

ADDENDUM NO. 1

Date: 11/27/23 Project Name: Marquette Branch Prison - Primary Electrical Infrastructure Upgrades File # 472/22442.JBB Funding Code # 472/MBPMaintProj

This Addendum is issued for the purpose of modifying and/or clarifying the original Contract Documents and shall take precedence over them.

All work included herein shall be in accordance with the original drawings and specifications except as specifically noted herein. All incidental items required to provide the following modifications shall be included even though not specifically described.

This addendum is being sent to all bidders receiving plans and specifications. Receipt of this Addendum shall be noted on the Bid Summary in the appropriate location.

Clarification and Questions:

A1.1 Clarification: The Bid due date will be extended one (1) week and will be due on December 13, 2023.

A1.2 Question: Please provide specs/details for all pad mount transformer bases. Please refer to Detail #1 and Concrete specifications on sheet E100.

A1.3 Question: Please provide specs/details for all new handholes required. Please refer to Detail #3 on sheet E100 and Raceway and Boxes for electrical systems 2.5 Handholes and boxes for exterior underground wiring.

A1.4 Clarification: Last addendum will be issued December 1, 2023.

A1.5 Attachments: Sign in sheet.

Addendum No 1
sign sheet