About this file

This document is Addendum 4 for the Barry State Game Area - New Pole Barn contract opportunity (File Number 751/22020.JLM) issued by the Michigan Department of Technology, Management and Budget (DTMB) State Facilities Administration Design and Construction Division. The addendum revises the project specifications, including adding prevailing wage requirements per 2023 PA 10 and requirements for contractor/subcontractor records and payroll. The bid opening date is 2/14/2024. The contract opportunity involves the construction of a new pole barn at the Barry State Game Area.

The addendum requires contractors and subcontractors to comply with state prevailing wage requirements, including paying workers no less than the prevailing wage and fringe benefit rates in the locality, and prohibits retaliation against workers who report violations. Contractors and subcontractors must maintain detailed payroll and employment records that will be subject to inspection by the state. Failure to acknowledge this addendum may result in the bid being rejected.

View the file

Other files

File Type Posted
751-22020.JLM_Pre-Bid Sign-in Sheet.pdf PDF
Advertisement 22020.pdf PDF
Drawings 22020_Part2.pdf PDF
751-22020.JLM_Barry SGA_Geotech Report.pdf PDF
Addendum 2 Bid Summary.pdf PDF
Addendum 2.pdf PDF
Specifications 22020.pdf PDF
Addendum 1.pdf PDF
Addendum 1 Drawings.pdf PDF
Drawings 22020_Part1.pdf PDF
Addendum 3.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 12/17)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

CONSTRUCTION BID ADDENDUM NO. 4

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

2/7/2024

PROJECT NAME

Barry State Game Area – New Pole Barn

FILE NUMBER

751/22020.JLM

PROFESSIONAL

NFE Engineers

PROJECT DIRECTOR

Josiah Meyers

BID OPENING DATE:

2/14/2024

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

1. Revise Project Specifications as indicated below:

Add 00100:

26. PREVAILING WAGE: The Bidding Documents include either the a ached Appendix V of prevailing rates of wages and fringe benefits for all classes of Construc on Mechanics called for in the Bid and resul ng Contract, if any, or the a ached current prevailing wage determina on issued by the U.S. Department of Labor, as applicable depending on the funding source(s).

Replace 00700-2.5 with:

2.5 Prevailing Wages and Access to Payroll Records:

2.5.1 Prevailing Wages:

To the extent applicable, Contractor will comply with state (2023 PA 10, MCL 408.1101 to 408.1126) prevailing wage requirements.

State Prevailing Wages-The following provisions of this Ar cle 7.15 apply when 2023 PA 10 applies.

Prevailing Wage and Fringe Benefits--The rates of wages and fringe benefits to be paid to each class of Construc on

Mechanic by DB En ty and Subcontractors, shall not be less than the wage rates and fringe benefit rates prevailing in the locality in which the work is performed.

Nondiscrimina on, Nonretalia on- Contractor or a Subcontractor shall not discharge, discipline, retaliate against, or otherwise discriminate against a Construc on Mechanic, or threaten to do any of these things, because the

Construc on Mechanic reported or was about to report a viola on or suspected viola on of the act.

Construc on Mechanics under this Contract are intended beneficiaries of the contractual prevailing wage, fringe benefit, and nondiscrimina on nonretalia on requirements of the Contract. Any such Construc on Mechanic aggrieved by failure of a contractor or subcontractor to pay prevailing wages or benefits as specified in the Contract, or by viola on of sec on 7 of 2023 PA 10, in addi on to any other remedies provided by law, may bring an ac on in a court of competent jurisdic on against such contractor or subcontractor for damages or injunc ve relief and may be awarded reinstatement or other appropriate relief, and all damages sustained, together with actual costs and a orney fees at trial and on appeal.

Contractor and Subcontractors shall keep posted on the construc on site, in a conspicuous place, a copy of all prevailing wage and fringe benefit rates prescribed in this Contract and shall keep an accurate record showing the name and occupa on of and the actual wages and benefits paid to each Construc on Mechanic employed by it in connec on with the Contract. This record shall be available for reasonable inspec on by the State.

2.5.2 Payroll: The Contractor and its Subcontractors must maintain and keep, in accordance with generally accepted accoun ng principles, records pertaining to the bidding, award and performance of the Work, including, but not limited to cer fied payroll, employment records and all data used in es ma ng the Contractor’s prices for the Bid, Change Order, proposal or claim. The Owner or its representa ve must have access to those records, must have the right to interview the Contractor’s employees and must be provided with appropriate facili es for the purpose of inspec on, audit/review and copying for five years a er final payment, termina on, or date of final resolu on of any dispute, li ga on, audit excep on or appeal. The payroll and other employment records of workers assigned to the site must contain the name and address of each worker, correct wage classifica on, rate of pay, daily and weekly number of hours worked, deduc on made, and actual wages paid. The Contractor must maintain records that show:

(a) the an cipated costs or actual costs incurred in providing such benefits, (b) that commitment to provide such benefits is enforceable, and (c) that the plan or program is financially responsible and has been communicated in wri ng to the workers affected.

Delete 00800 STATE-FUNDED PROJECT PREVAILING WAGE REQUIREMENTS #1 & #2.

2.

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

PROFESSIONAL: Karl Ruiter DATE: 2/7/2024

APPROVED BY:

PROJECT DIRECTOR: Josiah Myers DATE: 2/7/2024