Addendum 3 Question 2 SAMPLE CAD PROJECT PLAN.xlsx
XLSX spreadsheet 34 KB Posted
- Solicitation number
- NSP7149 Z1
- Issued by
- Blaine County, Nebraska
About this file
This document is an Addendum for the Computer Aided Dispatch and Mobile Data System contract opportunity issued by the Nebraska State Patrol (NSP). The addendum provides a sample project plan detailing the tasks, timelines, and resource requirements for implementing the new CAD system. Key activities include creating virtual machines, establishing VPN access, completing system documentation, developing interfaces, performing data conversion, conducting system builds and testing, and providing training. The contract opportunity is open to qualified vendors to provide the requested CAD and mobile data solutions for the State of Nebraska and Blaine County.
The sample project plan indicates a comprehensive implementation effort spanning over 16 months, with a mix of onsite and remote work. Pricing details are not provided in this addendum, but the contract opportunity indicates it may not be an exclusive arrangement, allowing the State to contract with multiple vendors. The project is funded by the State of Nebraska, and the contract term and renewal options are not specified in this document.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Report Data
| Booking Start Date | Booking Title | Date Range (scheduled) | Column1 | Hours |
| Sample Project Plan |
| May 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 5/27/24 | Create VMs per Server Spec Sheet | 2.4 | Remote | 12 |
| June 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 6/17/24 | Establish VPN Access | 0.2 | Remote | 1 |
| 6/17/24 | Interface Review/Documentation | 1.6 | Remote | 8 |
| 6/24/24 | Complete Server as-built Documentation | 2 | Remote | 10 |
| September 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 9/2/24 | Write Up Selected Vendor Interface ICD's | Remote | 24 | |
| 9/9/24 | Complete Selected Vendor Interface ICD's and Review with Customer | Remote | 16 | |
| 9/16/24 | Review and Address Redlines for Selected Vendor Interface ICD's | Remote | 4 | |
| 9/16/24 | Data Conversion Scope Review | 2.8 | Remote | 14 |
| October 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 10/7/24 | Development: Set ups Selected Vendor Interfaces | Remote | 32 | |
| 10/14/24 | Development: Data conversion work | Remote | 32 | |
| 10/28/24 | CAD Server Staging | 2.4 | Remote | 12 |
| November 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 11/4/24 | Map Build 1 | 8 | Remote | 40 |
| 11/18/24 | Prep System Build 1 | 1.6 | Remote | 8 |
| 11/18/24 | Map Data Analysis and Report | 4.8 | Remote | 24 |
| 11/25/24 | Map Data Analysis and Report | 5.33 | Remote | 26.65 |
| December 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 12/2/24 | System Build 1 (Onsite) | 6.4 | Onsite | 32 |
| 12/2/24 | Development: interfaces | Remote | 16 | |
| 12/16/24 | Map Build 2 | 8 | Remote | 40 |
| 12/16/24 | Ticket Resolution | 1.6 | Remote | 8 |
| 12/23/24 | Prep System Build 2 | 4 | Remote | 20 |
| January 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 1/6/25 | System Build 2 (Onsite) | 6.4 | Onsite | 32 |
| 1/27/25 | Prep System Build 3 | 1.6 | Remote | 8 |
| February 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 2/3/25 | System Build 3 (Onsite) | 6.4 | Onsite | 32 |
| 2/10/25 | COTS Interface Installation - Production Environment | 6.4 | Remote | 32 |
| 2/10/25 | Data conversion load and validation testing | 0.8 | Remote | 4 |
| March 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 3/3/25 | Tech Lead Health Check | 1.6 | Remote | 8 |
| 3/3/25 | COTS Interface Installation - DR Environment | 4 | Remote | 20 |
| 3/3/25 | COTS Interface Installation - Test Environment | 4 | Remote | 20 |
| 3/10/25 | SysAdmin Intro Workshop (Onsite) | 4.8 | Onsite | 24 |
| 3/17/25 | SysAdmin Core 1 Workshop (Onsite) | 4.8 | Onsite | 24 |
| 3/24/25 | System Configuration Workshop 1 (Onsite) | 6.4 | Onsite | 32 |
| 3/31/25 | Data conversion load 2 and validation testing | 7.5 | Remote | 37.5 |
| April 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 4/7/25 | Config 1 Follow-up Wk2 | 4.8 | Remote | 24 |
| 4/7/25 | Install/Setup ProQA | 1.6 | Remote | 8 |
| 4/7/25 | Analytics Initial Install Follow-up/Prep for Training | 3.2 | Remote | 16 |
| 4/14/25 | System Configuration Workshop 2(Onsite) | 6.4 | Onsite | 32 |
| 4/21/25 | Config 2 Follow-up Wk1 | 4.8 | Remote | 24 |
| 4/28/25 | Prep Mobile Law Config Workshop 1 | 0.4 | Remote | 2 |
| 4/28/25 | Install/Initial Config Mobile | 3.2 | Remote | 16 |
| May 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 5/5/25 | System Configuration Workshop 3 (Onsite) | 6.4 | Onsite | 32 |
| 5/5/25 | Mobile Law Config Workshop 1 (Onsite) | 4.8 | Onsite | 24 |
| 5/12/25 | Map Build 2 Follow-up | 1.6 | Remote | 8 |
| 5/19/25 | Config 3 Follow-up Wk1 | 4.8 | Remote | 24 |
| 5/19/25 | Mobile Law Workshop 1 Follow-up/Initial Delivery | 8 | Remote | 40 |
| 5/26/25 | Config 3 Follow-up Wk2 | 6 | Remote | 30 |
| 5/26/25 | Prep Mobile Law Config Workshop 2 | 0.5 | Remote | 2.5 |
| June 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 6/2/25 | Mobile Law Config Workshop 2 (Onsite) | 4.8 | Onsite | 24 |
| 6/2/25 | Ticket Resolution | 1.6 | Remote | 8 |
| 6/2/25 | Map Build 3 | 8 | Remote | 40 |
| 6/9/25 | Mobile Law Workshop 2 Follow-up/Final Delivery | 8 | Remote | 40 |
| 6/23/25 | Site Config Doc | 1.6 | Remote | 8 |
| 6/30/25 | Internal Selected Vendor Testing | 6 | Remote | 30 |
| July 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 7/7/25 | Onsite Customer Functional Testing Wk1 | 8 | Onsite | 40 |
| 7/7/25 | Stage DR Servers | 6.4 | Remote | 32 |
| 7/14/25 | Onsite Customer Functional Testing Wk2 | 8 | Onsite | 40 |
| 7/21/25 | Address Blocker Defects | 6.4 | Remote | 32 |
| 7/28/25 | Prep/Alignment for TTT | 0.8 | Remote | 4 |
| 7/28/25 | Analytics SysAdmin and User Training | 1.6 | Remote | 8 |
| August 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 8/4/25 | Data Refresh Training | 3.2 | Remote | 16 |
| 8/4/25 | Mobile TTT Law (Onsite) | 6.4 | Onsite | 32 |
| 8/11/25 | 4 weeks End Users Training (Onsite) | 8 | Onsite | 40 |
| September 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 9/15/25 | Readiness Review Checklist Creation | 1.6 | Remote | 8 |
| 9/29/25 | Customer Readiness Review | 0.4 | Remote | 2 |
| October 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 10/6/25 | Onsite Cutover | 8 | Onsite | 40 |
| 10/13/25 | Post Customer Support Wk1 | 8 | Remote | 40 |
| 10/20/25 | Post Cutover Support Wk2 (Remote) | 6.4 | Remote | 32 |
| 10/27/25 | 30 Day Reliability Support (Wk3) | 8 | Remote | 40 |
| November 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 11/3/25 | 30 Day Reliability Support (Wk4) | 8 | Remote | 40 |
| 11/10/25 | Finalize Site Config/Handoff to Customer Support | 1.8 | Remote | 9 |
| 11/10/25 | Finalize Site Config/Handoff to Customer Support | 1.8 | Remote | 9 |