Addendum 3 Question 2 SAMPLE CAD PROJECT PLAN.xlsx
XLSX spreadsheet 34 KB Posted
- Solicitation number
- NSP7149 Z1
- Issued by
- Blaine County, Nebraska
About this file
The file is an Addendum 3 Question 2 Sample CAD Project Plan Excel spreadsheet for the Nebraska State Patrol's (NSP) Computer Aided Dispatch (CAD) and Mobile Data System procurement. The comprehensive project plan outlines a detailed implementation timeline spanning from May 2024 to November 2025, covering key activities such as VM creation, VPN access establishment, server documentation, interface development, system builds, environment installations, configuration workshops, testing, training, and post-cutover support. The project is structured with remote and onsite tasks, including multiple system build phases, interface installations across production, disaster recovery, and test environments, and systematic workshops for system configuration and mobile law enforcement capabilities.
The project plan aligns with the RFP's requirements for a statewide CAD system serving approximately 482 sworn and 240 civilian staff with an expected 350 mobile users across multiple communication centers. The implementation involves complex technical integrations with over 20 existing interfaces, including Active Directory, AVL systems, body-worn cameras, crash reporting, eCitation, E911, and various state and national law enforcement databases. The five-year contract with potential five one-year renewals includes comprehensive data conversion of seven years of historical incident and premise data, with a focus on creating a multi-jurisdictional CAD environment compliant with NENG NG-911 standards. The project plan demonstrates a methodical approach to system implementation, with specific milestones for configuration, testing, training, and final cutover scheduled for October 2025.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Report Data
| Booking Start Date | Booking Title | Date Range (scheduled) | Column1 | Hours |
| Sample Project Plan |
| May 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 5/27/24 | Create VMs per Server Spec Sheet | 2.4 | Remote | 12 |
| June 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 6/17/24 | Establish VPN Access | 0.2 | Remote | 1 |
| 6/17/24 | Interface Review/Documentation | 1.6 | Remote | 8 |
| 6/24/24 | Complete Server as-built Documentation | 2 | Remote | 10 |
| September 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 9/2/24 | Write Up Selected Vendor Interface ICD's | Remote | 24 | |
| 9/9/24 | Complete Selected Vendor Interface ICD's and Review with Customer | Remote | 16 | |
| 9/16/24 | Review and Address Redlines for Selected Vendor Interface ICD's | Remote | 4 | |
| 9/16/24 | Data Conversion Scope Review | 2.8 | Remote | 14 |
| October 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 10/7/24 | Development: Set ups Selected Vendor Interfaces | Remote | 32 | |
| 10/14/24 | Development: Data conversion work | Remote | 32 | |
| 10/28/24 | CAD Server Staging | 2.4 | Remote | 12 |
| November 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 11/4/24 | Map Build 1 | 8 | Remote | 40 |
| 11/18/24 | Prep System Build 1 | 1.6 | Remote | 8 |
| 11/18/24 | Map Data Analysis and Report | 4.8 | Remote | 24 |
| 11/25/24 | Map Data Analysis and Report | 5.33 | Remote | 26.65 |
| December 2024 | ||||
| Week Of | Task | Onsite or Remote | ||
| 12/2/24 | System Build 1 (Onsite) | 6.4 | Onsite | 32 |
| 12/2/24 | Development: interfaces | Remote | 16 | |
| 12/16/24 | Map Build 2 | 8 | Remote | 40 |
| 12/16/24 | Ticket Resolution | 1.6 | Remote | 8 |
| 12/23/24 | Prep System Build 2 | 4 | Remote | 20 |
| January 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 1/6/25 | System Build 2 (Onsite) | 6.4 | Onsite | 32 |
| 1/27/25 | Prep System Build 3 | 1.6 | Remote | 8 |
| February 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 2/3/25 | System Build 3 (Onsite) | 6.4 | Onsite | 32 |
| 2/10/25 | COTS Interface Installation - Production Environment | 6.4 | Remote | 32 |
| 2/10/25 | Data conversion load and validation testing | 0.8 | Remote | 4 |
| March 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 3/3/25 | Tech Lead Health Check | 1.6 | Remote | 8 |
| 3/3/25 | COTS Interface Installation - DR Environment | 4 | Remote | 20 |
| 3/3/25 | COTS Interface Installation - Test Environment | 4 | Remote | 20 |
| 3/10/25 | SysAdmin Intro Workshop (Onsite) | 4.8 | Onsite | 24 |
| 3/17/25 | SysAdmin Core 1 Workshop (Onsite) | 4.8 | Onsite | 24 |
| 3/24/25 | System Configuration Workshop 1 (Onsite) | 6.4 | Onsite | 32 |
| 3/31/25 | Data conversion load 2 and validation testing | 7.5 | Remote | 37.5 |
| April 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 4/7/25 | Config 1 Follow-up Wk2 | 4.8 | Remote | 24 |
| 4/7/25 | Install/Setup ProQA | 1.6 | Remote | 8 |
| 4/7/25 | Analytics Initial Install Follow-up/Prep for Training | 3.2 | Remote | 16 |
| 4/14/25 | System Configuration Workshop 2(Onsite) | 6.4 | Onsite | 32 |
| 4/21/25 | Config 2 Follow-up Wk1 | 4.8 | Remote | 24 |
| 4/28/25 | Prep Mobile Law Config Workshop 1 | 0.4 | Remote | 2 |
| 4/28/25 | Install/Initial Config Mobile | 3.2 | Remote | 16 |
| May 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 5/5/25 | System Configuration Workshop 3 (Onsite) | 6.4 | Onsite | 32 |
| 5/5/25 | Mobile Law Config Workshop 1 (Onsite) | 4.8 | Onsite | 24 |
| 5/12/25 | Map Build 2 Follow-up | 1.6 | Remote | 8 |
| 5/19/25 | Config 3 Follow-up Wk1 | 4.8 | Remote | 24 |
| 5/19/25 | Mobile Law Workshop 1 Follow-up/Initial Delivery | 8 | Remote | 40 |
| 5/26/25 | Config 3 Follow-up Wk2 | 6 | Remote | 30 |
| 5/26/25 | Prep Mobile Law Config Workshop 2 | 0.5 | Remote | 2.5 |
| June 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 6/2/25 | Mobile Law Config Workshop 2 (Onsite) | 4.8 | Onsite | 24 |
| 6/2/25 | Ticket Resolution | 1.6 | Remote | 8 |
| 6/2/25 | Map Build 3 | 8 | Remote | 40 |
| 6/9/25 | Mobile Law Workshop 2 Follow-up/Final Delivery | 8 | Remote | 40 |
| 6/23/25 | Site Config Doc | 1.6 | Remote | 8 |
| 6/30/25 | Internal Selected Vendor Testing | 6 | Remote | 30 |
| July 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 7/7/25 | Onsite Customer Functional Testing Wk1 | 8 | Onsite | 40 |
| 7/7/25 | Stage DR Servers | 6.4 | Remote | 32 |
| 7/14/25 | Onsite Customer Functional Testing Wk2 | 8 | Onsite | 40 |
| 7/21/25 | Address Blocker Defects | 6.4 | Remote | 32 |
| 7/28/25 | Prep/Alignment for TTT | 0.8 | Remote | 4 |
| 7/28/25 | Analytics SysAdmin and User Training | 1.6 | Remote | 8 |
| August 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 8/4/25 | Data Refresh Training | 3.2 | Remote | 16 |
| 8/4/25 | Mobile TTT Law (Onsite) | 6.4 | Onsite | 32 |
| 8/11/25 | 4 weeks End Users Training (Onsite) | 8 | Onsite | 40 |
| September 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 9/15/25 | Readiness Review Checklist Creation | 1.6 | Remote | 8 |
| 9/29/25 | Customer Readiness Review | 0.4 | Remote | 2 |
| October 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 10/6/25 | Onsite Cutover | 8 | Onsite | 40 |
| 10/13/25 | Post Customer Support Wk1 | 8 | Remote | 40 |
| 10/20/25 | Post Cutover Support Wk2 (Remote) | 6.4 | Remote | 32 |
| 10/27/25 | 30 Day Reliability Support (Wk3) | 8 | Remote | 40 |
| November 2025 | ||||
| Week Of | Task | Onsite or Remote | ||
| 11/3/25 | 30 Day Reliability Support (Wk4) | 8 | Remote | 40 |
| 11/10/25 | Finalize Site Config/Handoff to Customer Support | 1.8 | Remote | 9 |
| 11/10/25 | Finalize Site Config/Handoff to Customer Support | 1.8 | Remote | 9 |