ADDENDUM #3 04.BOE.26 LC BROOKS ADMIN BLDG.pdf

PDF 376 KB Posted

Attached to
CCPS - Window and Partial HVAC Replacement at Brooks Administration Building
Solicitation number
BPM054976
Issued by
Calvert County, Maryland

About this file

Summary

Addendum No. 3 is a contract modification document issued by the Board of Education of Calvert County, Maryland on February 20, 2026, for the Window and Partial HVAC Replacement project at Brooks Administration Building located at 1305 Dares Beach Road, Prince Frederick, Maryland. The addendum responds to bidders' questions regarding contract specifications and clarifies project scope, specifically addressing refrigerant piping serving equipment BS-4 and VRT-25 through 32 in the IT department, with continuation of piping detailed on drawing M3.01. The addendum confirms that Calvert County Public Schools will not hold a separate prime contract for asbestos abatement work; instead, asbestos-related activities identified in the contract documents are included as part of the bidding contractor's work and must be performed in accordance with specification sections 02 41 19, 02 84 00, and the project phasing plan. Non-friable asbestos-containing materials may be encapsulated in lieu of removal as specified, particularly floor tile mastic in interior areas which may remain in place and be covered. The bid date, time, and location remain unchanged by the issuance of this addendum, and contractors must acknowledge receipt of the addendum on their proposal forms to avoid disqualification.

The project is phased across five phases with an anticipated Notice to Proceed of March 16, 2026, requiring substantial completion within 222 calendar days and final acceptance within an additional unspecified timeframe. Phase 1 runs from June 15 to August 7, 2026, focusing on ceiling removal, HVAC modifications, and selective window and door replacement. Phases 2 through 5 span from August 10 through October 23, 2026, completing remaining window and door replacements and associated interior finishes. The contractor must maintain existing building operations throughout construction and comply with environmental regulations regarding refrigerant recovery and hazardous materials management. All work must adhere to detailed construction progress documentation requirements, including CPM scheduling, daily reports, and coordination with the owner's continuing occupancy of the building.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Web Accessibility Message

Some sections of this document were not created by Calvert County Public Schools and cannot be made accessible. If you should require assistance in obtaining details or information contained within this document, please contact the Calvert County Public Schools Board of Education at 443-550-8000.

Jana L. Smith-Post, President Lisa M. Grenis, Vice President Melissa M. Goshorn Paul E. Harrison Joseph L. Marchio Allison E. Jones, Student Member

1305 Dares Beach Road Dr. Marcus Newsome Prince Frederick, MD 20678 Superintendent of Schools P 443-550-8000 • F 410-286-1358 www.calvertnet.k12.md.us

20 FEBRUARY 2026

ADDENDUM NO. 3

WINDOW AND PARTIAL HVAC REPLACEMENT

AT

BROOKS ADMINISTRATION BUILDING

PSC #04.BOE.26 LC

This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents, as noted below.

Acknowledge receipt of this Addendum in the space provided on the Contractor Proposal Form. Failure to acknowledge addendum may disqualify bidder.

The bid date, time for receipt of bid, and location, remain unchanged by issuance of this addendum.

RESPONSES TO BIDDERS’ QUESTIONS:

Addendum Item No.

Description

AD3.001 Question:

Response:

On drawing M2.03, Note 3 indicates the refrigerant piping is to be temporarily capped in one phase and then completed in a future phase.

Additionally, note 1 states that refrigerant sizes are to be per the manufacturer’s recommendation. However, it is not clear what equipment this piping is serving. Could you please confirm which equipment this piping is serving?

The piping serves BS-4 and VRT-25 thru 32 in the IT department. Refer to drawing M3.01 for continuation of piping.

20 FEBUARY 2026

ADDENDUM NO. 3 PAGE 2 of 2

RESPONSES TO BIDDERS’ QUESTIONS (Continued):

AD3.002 Question:

Response:

See below from addendum #2. Will CCPS hold the “separate prime contract” for the abatement work?

Specification Section 02 41 19, 1.9D. Hazardous Materials:

Asbestos-containing materials are known to be present in the building. A separate prime contract for Asbestos’ Abatement is a component of the Work. Asbestos will be abated in phases in accordance with the project phasing plan found in Division 1 Section “Construction Progress Documentation”.

1. If suspected hazardous materials are encountered that are not identified as part of the Asbestos Abatement Contract, do not disturb; immediately notify Architect and Owner. A report on the presence of hazardous materials is on file for review and use.

Examine report to become aware of locations where hazardous materials are present.

No. Calvert County Public Schools will not hold a separate prime contract for asbestos abatement associated with this Project.

Asbestos-related work identified in the Contract Documents is included in the Work of the bidding Contractor and shall be performed in accordance with Specification Section 02 41 19, Section 02 84 00, and the project phasing plan.

The Contract Documents identify certain asbestos-containing materials as non-friable and permit encapsulation of those materials in lieu of removal, as specified. In particular, asbestos-containing floor tile mastic identified in interior areas can remain in place and be covered, as indicated on the Drawings and specified in Section 02 84 00. Also see Marked Floor Plans located on pages 10-13 of the Hazardous Materials Evaluation (Asbestos and Lead Based Paint) Report, following 02 84 00.

Specification language addressing hazardous materials encountered outside of the identified asbestos abatement scope, referenced in the question applies only to previously unidentified or suspect materials not documented in the Contract Documents. If such materials are encountered, the Contractor shall not disturb the material and shall notify the Architect and Owner in accordance with the specifications.

Bidders are responsible for reviewing the Drawings, hazardous materials report, and all applicable specification sections for complete requirements.

END OF ADDENDUM

ADDENDUM #2 04.BOE.26 LC BROOKS ADMIN BLDG.pdf
CCPS Brooks Admin - Bidding - ADD2 - Sealed.pdf
C101 - SITE PLAN
D1.1 - DEMOLITION NOTES AND CEILING PLANS
A1.1 - OVERALL FLOOR PLANS
00 40 00 Revised Contractor Proposal Form R1.pdf
Legal Firm Name
Address
City, State, Zip
Date
WINDOW AND PARTIAL HVAC REPLACEMENT
AT
BROOKS ADMINISTRATION BUILDING
1305 DARES BEACH ROAD PRINCE FREDERICK, MD 20678
01 32 00 Construction Progress Documentation R1.pdf
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule
2. Daily construction reports
3. Field condition reports
4. Special reports
B. Related Sections: The following Sections contain requirements that relate to this Section:
1. Division 1 Section “Project Coordination”
2. Division 1 Section "Applications for Payment" for submitting the Schedule of Values
3. Division 1 Section "Project Meetings" for submitting and distributing meeting and conference minutes
4. Division 1 Section "Quality Requirements" for submitting a schedule of tests and inspections
5. Division 1 Section "Project Record Documents" for submitting Project Record Documents at Project closeout
6. Division 1 Section “Submittals” for procedural requirements regarding the Submittal Schedule
7. Division 1 Section “Temporary Facilities & Controls” for the various stages of Construction relative to temporary heat which must be identified on the Contractor’s Construction Schedule.
1.3 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish dates.
2. Predecessor activity is an activity that must be completed before a given activity can be started.
B. Critical Path Method (CPM): A method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of the Proj...
C. Critical Path: The longest continuous chain of activities through the network schedule that establishes the minimum overall Project duration and contains no float.
D. Event: The starting or ending point of an activity.
E. Float: The measure of leeway in starting and completing an activity.
1. Float is not for the exclusive use or benefit of either the Owner or the Contractor. Extensions of the time to interim milestone dates or the Contract Completion Date, under the Contract, will be granted only to the extent that equitable time adju...
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the following activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
G. Major Area: A story of construction, a separate building, or a similar significant construction element.
H. Milestone: A key or critical point in time for reference or measurement.
I. Network Diagram: A graphic diagram of a network schedule showing activities and activity relationships.
1.4 SUBMITTALS
A. Qualification Data: For firms and persons specified in "Quality Assurance" Article and in-house scheduling personnel to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and ...
B. Preliminary Construction Schedule: Submit one (1) copy in an acceptable format as determined by the Architect.
C. Contractor’s Construction Schedule: Submit one (1) paper Gantt Chart and one (1) electronic copy in its native format.
D. CPM Reports: The Contractor's Construction Schedule shall be a CPM Schedule. Concurrent with the CPM Schedule, submit three (3) printed copies of each of the following computer-generated reports. The format for each activity in the reports shall ...
1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of preceding and succeeding activities for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of all activities sorted in ascending order of total float.
E. Daily Construction Reports: Submit two (2) copies at weekly intervals.
F. Field Condition Reports: Submit two (2) copies at time of discovery of differing conditions.
G. Special Reports: Submit two (2) copies at time of unusual event.
1.5 QUALITY ASSURANCE
A. Scheduling Professional Qualifications: The Contractor’s Construction Schedule shall be composed and maintained by an individual having been employed for at least five years primarily as a CPM scheduler or an individual certified as a Planning and ...
B. Prescheduling Conference: Conduct conference at the Project site to comply with requirements in Division 1 Section "Project Meetings". Review methods and procedures related to the Preliminary Construction Schedule and Contractor's Construction Sch...
1. Discuss constraints, including phasing, work stages, area separations and interim milestones.
2. Review delivery dates for Owner-furnished products.
3. Review time required for review of submittals and resubmittals.
4. Review requirements for tests and inspections by independent testing and inspecting agencies.
5. Review time required for completion and startup procedures.
6. Review and finalize the list of construction activities to be included in the schedule.
7. Review submittal requirements and procedures.
8. Review procedures for updating schedules.
1.6 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities.
B. Coordinate the Contractor's Construction Schedule with the Schedule of Values, List of Subcontracts, Submittal Schedule, Progress Reports, Applications for Payment and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.7 OWNER'S PRELIMINARY PROJECT PHASING NARRATIVE
A. Except for the normal summer and holiday schedules, the Brooks Administration Building will remain in operation, and the building will remain open to the public. As a result, the Owner has proposed a detailed Phasing Plan. It is understood that t...
Substantial Completion of each of the phases designated herein is considered Milestones to the overall Schedule and is subject to the provisions of Article 8 – “Time” of the General Conditions.
Total Project Duration: The Agreement will include a stipulation that the Work be substantially complete (as defined in the Contract) within 222 calendar days, and that completion of ALL punch list work and Final Acceptance of the Work be achieved wit...
1. Anticipated NTP: 03/16/2026.
2. Phase 1: 06/15/2026 – 08/07/2026
a. Phase 1 – General: Phase 1 Goal is to complete the ceiling removal within the designated basement and main floor areas, specific HVAC and electrical scope, as well as select window and door replacement.
i. Phase 1 scope to include:
1) Temporary Facilities
2) Ceiling removal in designated basement and main floor areas
3) Select HVAC hot water demolition and capping
4) Select HVAC ductwork removal
5) Installation of new indoor HVAC ductwork, equipment and piping as indicated (ductwork Phases 1A-1D | equipment Phase 1D*).
6) Selective window/door demolition
7) Selective floor finish demolition
8) Wall and floor patch and repair as required
9) Selective installation of new windows/doors
10) Selective installation of new floor finish
11) Selective installation of new ACT ceilings
12) Installation of new exterior HVAC equipment support structure (Phases 1A-1D).
13) Rebalance of AHU-2
14) Installation of new outdoor HVAC equipment (Phase 1D*).
3. Phase 2: 08/10/26 – 09/04/2026
a. General: Phase 2 goal is to complete the lower and main and upper level select window and door demolition and replacement, as well as complete the select HVAC and Electrical work within the designated spaces.
b. Phase 2 scope to include:
1) Selective window/door demolition
2) Selective floor finish demolition
3) Wall and floor patch and repair as required
4) Selective installation of new windows/doors
5) Installation of new indoor HVAC ductwork, equipment and piping as indicated
6) Selective installation of new floor finish
7) Selective installation of new ACT ceilings
4. Phases 3 through 5: 09/08/26 – 10/23/2026
a. General: Phases 3 - 5 goal is to complete the balance of select window and door demolition and replacement within the designated spaces.
b. Phases 3-5 scope to include:
1) Selective window/door demolition
2) Selective floor finish demolition
3) Wall and floor patch and repair as required
4) Selective installation of new windows/doors
5) Selective installation of new floor finish
6) Selective installation of new ACT ceilings
1.8 CONTRACTOR’S CONSTRUCTION SCHEDULE, GENERAL
1.9 POST AWARD ACTIVITIES
1.10 CONSTRUCTION SCHEDULE CONTENT
1.11 UPDATING OF CONSTRUCTION SCHEDULE/PROGRESS REPORTS
1.12 RECOVERY SCHEDULE.
1. The Contractor shall prepare a limited duration recovery schedule, incorporating the best available information from Subcontractors and others which shall permit a return to the Construction Schedule at the earliest possible time. The Contractor s...
2. Within two (2) days after submission by the Contractor of a recovery schedule, the Contractor shall participate in a conference with the Owner, to review and evaluate the recovery schedule. Within two (2) days of the conference, the Contractor sha...
3. The Contractor shall confer continuously with the Owner to assess the effectiveness of the recovery schedule. As a result of this conference:
1.13 SCHEDULE REVISIONS
1.14 FLOAT TIME
1.15 SCHEDULE OF INSPECTIONS AND TESTS
A. Prepare a schedule of inspections, tests, and similar services required by the Contract Documents. Submit the schedule within 10 days of the date established for commencement of the Work.
B. The schedule shall be in tabular form and shall include, but not be limited to, the following:
1. Specification Section number
2. Description of the test
3. Identification of applicable standards
4. Identification of test methods
5. Number of tests required
6. Time schedule or time span for tests
7. Entity responsible for performing tests
8. Requirements for taking samples.
9. Unique characteristics of each service

C. Distribute the schedule to the Owner, Architect, and each party involved in performance of portions of the Work where inspections and tests are required.

1.16 REPORTS
A. Daily Construction Reports: Prepare Daily Construction Reports recording the following information concerning events at the Project site:
1. List of subcontractors at Project site
2. Approximate count of personnel at Project site
3. High and low temperatures and general weather conditions
4. Accidents
5. Meetings and significant decisions
6. Unusual events (refer to special reports)
7. Stoppages, delays, shortages, and losses
8. Meter readings and similar recordings
9. Emergency procedures
10. Orders and requests of authorities having jurisdiction
11. Change Orders received and implemented
12. Construction Change Directives received
13. Services connected and disconnected
14. Equipment or system tests and startups
15. Partial Completions and occupancies
16. Substantial Completions authorized
B. Field Correction Reports: When the need to take corrective action that requires a departure from the Contract Documents arises, prepare a detailed report. Include a statement describing the problem and recommended changes. Indicate reasons the Co...
C. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, ...
D. Material Location Reports: At weekly intervals, prepare a comprehensive list of materials delivered to and stored at the site. The list shall be cumulative, showing materials previously reported plus items recently delivered. Include with the lis...
1.17 SPECIAL REPORTS
A. General: Submit Special Reports directly to the Owner within one day of an occurrence. Distribute copies of reports to parties affected by the occurrence and to the Architect.
B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at the Project site, whether or not related directly to the Work, prepare and submit a Special Report. List chain of events, persons participating, response by Con...
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
3825 024119 Selective Demolition R1.pdf
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Demolition and removal of selected portions of a building or structure.
2. Demolition and removal of selected site elements.
3. Salvage of existing items to be reused or recycled.
B. Related Sections include the following:
1. Division 1 Section "Summary of Work" for restrictions on use of the premises and Owner-occupancy requirements,
2. Division 1 Section “Construction Progress Documentation” for Owner occupancy requirements and phasing requirements.
3. Division 1 Section "Cutting and Patching" for cutting and patching procedures.
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.
B. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and deliver to Owner to remain Owner’s property where noted.
C. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated.
D. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.
E. Dismantle: To remove by disassembling or detaching an item from the surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.
1.4 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain th...
1. Carefully salvage in a manner to prevent damage and promptly return to Owner.
1.5 PRE-INSTALLATION MEETINGS
A. Pre-demolition Conference: Conduct conference at Project site to comply with Division 1 Section “Project Meetings”.
1. Inspect and discuss condition of construction to be selectively demolished.
2. Review structural load limitations of existing structure.
3. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.
4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.
5. Review areas where existing construction is to remain and requires protection.
1.6 INFORMATIONAL SUBMITTALS
A. Qualification Data: For refrigerant recovery technician.
B. Schedule of Selective Demolition Activities: Indicate the following:
1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's on-site operations are uninterrupted.
2. Interruption of utility services. Indicate how long utility services will be interrupted.
3. Coordination for shutoff, capping, and continuation of utility services.
4. Coordination of Owner's continuing occupancy of portions of existing building and of Owner's partial occupancy of completed Work.
C. Pre-demolition Photographs or Video: Show existing conditions of adjoining construction, including finish surfaces, that might be misconstrued as damage caused by demolition operations. Submit before Work begins.
D. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerants, stating that all refrigerants that was present was recovered and that recovery was performed according to EPA regulations. Include...
E. Warranties: Documentation indicating that existing warranties are still in effect after completion of selective demolition.
1.7 CLOSEOUT SUBMITTALS
A. Inventory: Submit a list of items that have been removed and salvaged.
1.8 QUALITY ASSURANCE
A. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.
1.9 FIELD CONDITIONS
A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.
B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.
C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.
D. Hazardous Materials: Asbestos-containing materials are known to be present in the building. A separate prime contract for Asbestos Abatement is a component of the Work. Asbestos will be abated in phases in accordance with the project phasing plan...
1. If suspected hazardous materials are encountered that are not identified as part of the Asbestos Abatement Contract, do not disturb; immediately notify Architect and Owner. A report on the presence of hazardous materials is on file for review and ...
E. Storage or sale of removed items or materials on-site is not permitted.
F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.
1.10 WARRANTY
A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties. Notify warrantor before p...
B. Notify warrantor on completion of selective demolition and obtain documentation verifying that existing system has been inspected and warranty remains in effect. Submit documentation at Project closeout.
1.11 COORDINATION
A. Arrange selective demolition schedule so as not to interfere with Owner's operations.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ASSE A10.6 and NFPA 241.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting selective demolition operations.
B. Review Project Record Documents of existing construction or other existing condition and hazardous material information provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.
C. Survey of Existing Conditions: Record existing conditions by use of preconstruction photographs or video.
1. Inventory and record the condition of items to be removed and salvaged. Provide photographs or video of conditions that might be misconstrued as damage caused by salvage operations.
3.2 PREPARATION
A. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment according to 40 CFR 82 and regulations of authorities having jurisdiction.
3.3 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.
B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.
1. Owner will arrange to shut off indicated services/systems when requested by Contractor.
2. Arrange to shut off utilities with utility companies.
3. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.
4. Disconnect, demolish, and remove plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.
a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.
b. Equipment to Be Removed: Disconnect and cap services and remove equipment.
c. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.
d. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.
e. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.
3.4 PROTECTION
A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.
2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.
3. Provide temporary enclosure at exterior window locations as necessary to provide secure closure of the facility until new window units are installed.
4. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.
5. Cover and protect furniture, furnishings, and equipment that have not been removed.
6. Comply with requirements for temporary enclosures, dust control, heating, and cooling specified in Division 1 Section "Temporary Facilities and Controls."
B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontro...
1. Strengthen or add new supports when required during progress of selective demolition.

C. Remove temporary barricades and protections where hazards no longer exist.

3.5 SELECTIVE DEMOLITION, GENERAL
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.
2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hamm...
3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppr...
5. Maintain fire watch during and for at least two hours after flame-cutting operations.
6. Maintain adequate ventilation when using cutting torches.
7. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.
8. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.
9. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
10. Dispose of demolished items and materials promptly.
B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
C. Removed and Salvaged Items:
1. Clean salvaged items.
2. Pack or crate items after cleaning. Identify contents of containers.
3. Store items in a secure area until delivery to Owner.
4. Transport items to Owner's storage area designated by Owner.
5. Protect items from damage during transport and storage.
D. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse.
2. Pack or crate items after cleaning and repairing. Identify contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition, clea...

3.6 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS
A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and...
B. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, and then remove masonry between saw cuts.
C. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished and then break up and remove.
3.7 DISPOSAL OF DEMOLISHED MATERIALS
A. Remove demolition waste materials from Project site [and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction.
1. Do not allow demolished materials to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

B. Burning: Do not burn demolished materials.

3.8 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
3.9 SELECTIVE DEMOLITION SCHEDULE
A. Remove: Perform selective demolition as noted on Drawings.
ADDENDUM #1 04.BOE.26 LC BROOKS ADMIN BLDG.pdf
00 40 00 Revised Contractor Proposal Form.pdf
Legal Firm Name
Address
City, State, Zip
Date
WINDOW AND PARTIAL HVAC REPLACEMENT
AT
BROOKS ADMINISTRATION BUILDING
1305 DARES BEACH ROAD PRINCE FREDERICK, MD 20678