This is Addendum 2 to the Invitation to Bid (ITB B-2-26-42) issued by Brevard County Purchasing Services for cooling tower refurbishment at the County Service Complex – Merritt Island facility located at 2575 North Courtenay Parkway, Merritt Island, Florida 32953. The addendum provides clarifications to 40 questions submitted by prospective bidders regarding project scope, timeline, equipment specifications, and operational requirements. Key project components include removal and replacement of structural steel, cooling tower fill, cooling tower fan motor, and four pump motors. The contractor must provide temporary cooling at no additional expense to the County throughout the refurbishment process and coordinate with the existing building controls contractor (Trane) to reestablish controls. The existing cooling tower is a 125-ton unit with a flow rate of 375 GPM, and the existing chiller is a 125-ton unit with a 300 GPM flow rate. The existing condenser water pumps are Baldor EM3313T 10 HP motors operating at 460 volts, 3-phase, 60 Hz. Crane operations for tower removal must not affect facility ingress/egress and require pre-approval of exact locations and the contractor's safety plan. Bid opening remains scheduled for October 6, 2026 at 11:00 a.m., and all other terms and conditions from the original bid package remain unchanged.
The addendum clarifies that liquidated damages shall apply to Substantial Completion and Final Completion milestones rather than the November 26, 2026 EECBG deadline, though the County will request a deadline extension from EECBG closer to that date if necessary. The contractor is responsible for all water treatment chemicals to bring the condenser water loop back to County specification after refurbishment, using Premiere products through the County's existing Trane contract. All new structural steel exposed to exterior conditions must be hot-dipped galvanized per ASTM A123, and the contractor is responsible for preventing interruption to existing piping penetration sealants and repairing any damage to roof structure or weather sealants at no expense to the County. The project is funded through the Energy Efficiency and Conservation Block Grant (EECBG) Program, which triggers prevailing wage and Build America, Buy America Act (BABAA) compliance requirements. The contractor must obtain an active Class A Air Conditioning Contractor or Mechanical Contractor license and E-Verify registration, provide a 5% bid bond at submission, and furnish one-year equipment and one-year workmanship warranties from Substantial Completion. Contact information is provided for Trane's controls account manager (Nathan Bloom) and local roofing contractors (Tech Systems, Hamilton Roofing, and Apex Roofing USA) should coordination be necessary.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum_4.pdf | ||
| Addendum_3.pdf | ||
| Add_2__RevisedDrawingSheetM101.pdf | ||
| Add_2_PreBid_Sign_In.pdf | ||
| Addendum_1.pdf | ||
| Inv__Specs.pdf | ||
| Attachment_D__Substitution_Form.pdf | ||
| Attachment_B__Mechanical_Roof_Plan.pdf | ||
| Attachment_A__Draft_Contract.pdf | ||
| Attachment_C__Structural_Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Purchasing Services 2725 Judge Fran Jamieson Way
Building C, Room 303 Viera, Florida 32940
County Service Complex – Merritt Island - Cooling Tower Refurbishment
B-2-26-42 September 15, 2026
ADDENDUM 2
TO ALL PROSPECTIVE BIDDERS
This is an Addendum to and shall be considered as part of the original bid package for the above-mentioned bid. Please acknowledge receipt of Addendum 2 in space provided on Price Sheet. Bidders are requested to acknowledge receipt of this addendum with their bid.
CLARIFICATION TO QUESTIONS RECEIVED:
Question 1: Has an extension already been requested or anticipated from EECBG to accommodate the procurement and construction timeline?
Answer: No, an extension has not been requested but the County will request one closer to the EECBG deadline.
Question 2: If no extension is anticipated, how should bidders interpret the November 26, 2026 deadline in relation to the stated 90+30 day schedule?
Answer: If no extension is granted from EECBG, then the construction duration stated in Section 2 of the Invitation to Bid shall apply.
Question 3: Will liquidated damages or other penalties be tied to the November 26, 2026 date, or to the Substantial/Final Completion milestones as defined in the schedule section?
Answer: Liquidated damages shall apply to the Substantial/Final Completion milestones.
Question 4: What voltage/phase/amperage of power is available for the temporary cooling tower hook up?
Answer: The Contractor shall field verify the power source available for temporary cooling. The Contractor also has the option to use a generator.
Question 5: Will an entire panel outage be required to get power for the temporary cooling tower and pump?
Answer: A long-term panel outage is not anticipated.
Question 6: If there is not enough power to run the temporary tower and pump should the contractor provide a generator for this effort?
Answer: Yes.
Question 7: During the walkdown, it was discussed that the temporary CW would connect directly to the chiller since temporary connections were not available, with that being said, please confirm that a temporary pump will also be required?
Answer: Cooling shall be provided by the Contractor at all times at no additional expense to the County.
Question 8: What is the maximum duration of outage allowed for installing the temporary cooling tower? Is additional temporary cooling required during this transition period?
Answer: Any outage should be minimal. See response to Question 7.
Question 9: Are new pump and cooling tower fan motors to be laser aligned per manufacturer's recommendations upon completion?
Answer: The Contractor is responsible for installation of equipment in accordance with manufacturers’ requirements for all equipment installed. The Contractor may not bypass requirements unless given written consent by manufacturer stating reason installation step is not required.
Question 10: Does the condenser water loop need to have the chemical treatment brought back into county spec after refurbished tower is re installed? Much of the system water with existing chemical will be lost during the process of removing the existing and installing a temporary tower. Will the county take care of all water treatment?
Answer: Yes, the condenser water loop chemical treatment needs to be brought back to County specification after refurbishment by the Contractor. No, the Contractor shall be responsible for all water treatments.
Question 11: Who is the county's current chemical treatment vendor/product for the cooling tower?
Answer: Premiere through the County’s contract with Trane.
Question 12: What is the existing model and specs of the condenser water pumps scheduled to have replacement motors?
Answer: Baldor EM3313T 10 HP 230/460 V 60 Hz 3 Phase
Question 13: Is any new condenser water piping/components required or only on an as needed basis to remove and reinstall the cooling tower?
Answer: No additional piping is expected, existing tower to be reconnected to existing systems once re-installed on new structure.
Question 14: Does the temporary tower and pump need to be connected to the existing building controls? Will monitoring or full control of temp tower and pump be required?
Answer: Yes, they need to be connected to the existing building controls. The Contractor will be required to monitor the controls.
Question 15: Who is the current building controls contractor?
Answer: Trane
Question 16: What voltage/phase are the pumps with motors to be replaced?
Answer: 460/3/60
Question 17: What is the capacity/flow rates of the existing chiller and cooling tower? We need a basis to quote a temporary cooling tower too.
Answer: The existing cooling tower is a 125-ton unit. Flow rate is 375 GPM. The existing chiller is a 125-ton unit. Flow rate is 300 GPM.
Question 18: Will value engineering options be entertained for this project as an alternate bid price?
Answer: The County is considering an alternate bid. If an alternate bid is added, an Addendum will be issued.
Question 19: Please provide a basis of design or performance requirements for the "Seacoast" coating required inside of the refurbished tower? The “Seacoast coating” cure time may dictate rental duration on temporary tower if it exceeds 24 hours cure time.
Answer: The Contractor shall submit for approval of the UV Treated Polymer for fill.
Manufacturer to provide coating from factory with replacement tower.
Question 20: What will the extent of commissioning be on this project? Is a third-party agent required?
Answer: For the refurbishment, commissioning does not apply. The Contractor shall coordinate with Trane to reestablish the controls.
Question 21. Where is the nearest Potable water hookup to feed the existing cooling tower make up water?
Answer: First floor in the Mechanical Room
Question 22: We believe the crane to remove the existing cooling tower will need to be set up in front of the main building entrance on the north side. Will this effort to remove the existing cooling tower need to take place during off hours as to not to affect the operations of the facility?
Answer: Crane operations shall not affect the ingress/egress of the facility. Exact locations of any crane operations, any alternate building access options, and the Contractor’s safety plan will be need to pre-approved by the County prior to construction. It is the County’s intention to allow Crane operations during regular hours.
Question 23: Where make up water will come from to service the temporary cooling tower?
Answer: See response to Question 21.
Question 24: What is timeframe for tower removal and crane set up due to facility operations and crane location at front entrance?
Answer: See response to Question 22.
Question 25: I am not seeing a specific scope of work for the roof, except possibly Keynote 1 on Drawing M-102, which states to provide new seals on the cooling tower. Can you please confirm whether the four support penetrations and seven utility penetrations in that area are also required to be resealed as part of this project?
Answer: There is no scope of work for the roof other than Keynote 1 on Drawing M-
102. The Contractor is to prevent interruption to existing piping penetration sealants through existing roof structure. Any damage to roof structure or weather sealant shall be the Contractor’s responsibility to repair at no expense to the County. Existing piping penetrations through roof is not considered to be in the scope.
Question 26: Where is the electrical panel for the cooling tower located?
Can we get pictures of the panel and panel schedule?
Are we able to tie into this panel for the temporary cooling tower?
Answer: 1st floor Mechanical Room No Yes
Question 27: It was mentioned that parts of the building are in use 24/7. What will be the preferred time for doing any shutdowns? Will temporary spot coolers be required for critical areas during the shutdown?
Answer: Standard working hours are 7:00am to 5:00pm. Work outside of the Standard Working hours such as a shutdown shall require 24-hour advance notice to the County. See response to Question 7 regarding temporary cooling.
Question 28: Will you be looking for a bid to replace the tower with a new unit?
Answer: See response to Question 18.
Question 29: How many motors are you looking to replace?
Answer: The Contractor shall replace 4 pump motors. Please see Revised Drawing Sheet M-101.
Question 30: What is the electrical service used on the existing unit? Breaker size & voltage?
Answer: The cooling tower fan is 30 amp, 240 vac, 7.5 hp.
Question 31: What steel is being replaced? The ones directly under the tower only or also the others under those? A total of (3) or (6)?
Answer: All horizontal members shall be replaced by the Contractor. Please see Drawing Sheet S-101 for additional information.
Question 32: Is there a list of vendors at the site visit?
Answer: See Attached Pre-Bid Sign In Sheet.
Question 33: Is the unit controlled by a t-stat or BAS?
Answer: BAS
Question 34: If BAS what brand & POC?
Answer: Trane Nathan Bloom
Account Manager Controls III Trane Commercial – Florida Team 2301 Lucien Way Suite 430 Maitland FL 32751
Service Main Line: +1407-660-1111 Cell: +1407-509-7141
Question 35: If you entertain a new unit is Marley the only brand or equivalent?
Answer: Not at this time. If the County adds a bid alternate, an Addendum will be issued.
Question 36: Is there a list of the equipment the tower supplies cooling for?
Answer: No
Question 37: Can we get another site visit to get more information?
Answer: Not at this time. If the County adds a bid alternate, then another pre-bid/walk-through meeting will be scheduled.
Question 38: Are just motors being replaced or the pumps as well?
Answer: Motors and pumps
Question 39: Do you have a roofing contractor that works on your building? If so, POC please.
Answer: Tech Systems 321-259-2246 Hamilton Roofing 321-729-0548 Apex Roofing USA 954-660-5234
Question 40: Specifications for the paint on the new beams?
Answer: Please see the General Steel Repair Notes on Drawing Sheet S-101.
The Bid Opening date remains October 06, 2026 no later than 11:00 a.m.
All other terms and conditions remain unchanged.
Sincerely, Mary Bowers Purchasing Manager
END OF ADDENDUM 2