This document is an Addendum to the bidding documents for the Renovate Armory Building 3 project, located at the Michigan National Guard Building 3 in Camp Grayling, Grayling, MI, with the file number 511/20058.CAK. The addendum clarifies that the contractor must provide roof saddles and crickets to direct water to the roof drains, as shown in the reissued drawing A-107. The bid opening date is July 12, 2023, at 2:00 pm EST.
The contract opportunity is for the state of Michigan, with the project located in Crawford County. The project involves the renovation of Armory Building 3 at the Camp Grayling facility.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 (Rev 12/17)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION BID ADDENDUM NO. 2
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL BIDDERS
DATE ISSUED
7/10/2023
PROJECT NAME
Renovate Armory Building 3
FILE NUMBER
511/20058.CAK
PROFESSIONAL
GH Forbes Associates Architects
PROJECT DIRECTOR
Chris Kulhanek
BID OPENING DATE:
7/12/2023 at 2:00pm EST
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
1. Find attached question and answer regarding roof saddles.
ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
PROFESSIONAL: GH Forbes Associates Architects DATE: 7/7/2023
APPROVED BY:
PROJECT DIRECTOR: Maria Alvaro DATE: 7/7/2023 http://www.michigan.gov/SIGMAVSS
8 1 6 E a s t 4 t h S t r e e t , R o y a l O a k , M I 4 8 0 6 7 w w w . g h f a a . c o m 2 4 8 . 5 4 2 . 7 8 6 6
ADDENDUM No. 2
Project: Renovate Armory Building 3 Location: Michigan National Guard Building 3, Camp Grayling, Grayling, MI File #: 511/20058.CAK
DMVA #: 26B1520017
Date: July 10th, 2023
Questions and Answers
Question 1: Please clarify if you want tapered saddles between roof drains and outside roof drains for water flow. Drawings only show it on detail 1 on A-502, those drains are against the wall and all others are in the middle of the roofs and show no roof saddles.
Answer 1: Yes, provide roof saddles and crickets to direct water to roof drains.
Refer to reissued A-107.
END OF ADDENDUM