About this file

This is an Addendum document issued by the Florida Department of Environmental Protection (FDEP) for the New ECAT Facility Project in Escambia County, Florida. The addendum establishes area-specific soil management requirements for all excavation, grading, filling, and related earthwork activities within designated work zones. The project involves infrastructure installation for a new ECAT facility that will support an Administration Building, Bus Wash, Fuel Depot, and Maintenance Building along Clarinda Lane in Pensacola, Florida, between Pace Boulevard and Palafox Street. The licensed Underground or Utility Contractor selected for this CDBG-DR funded project must adhere to strict soil segregation protocols outlined in the addendum.

The key contractual requirement stipulates that soil excavated from designated areas—specifically identified as the Blue Area and Orange Area on project plans—must remain segregated within their respective zones throughout all phases of work. Soil may only be transported outside its designated area if it is removed from the project site entirely and disposed of at an approved landfill or other legally authorized facility. The contractor bears full responsibility for maintaining soil separation and is prohibited from commingling soils between designated areas. Any unauthorized relocation or commingling of soils must be corrected by the contractor at no additional cost to the Owner, establishing clear accountability for compliance with environmental and groundwater delineation standards established by FDEP.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FDEP Groundwater Delienation Area

Area-Specific Soil Management:

All excavation, grading, filling, and related earthwork shall be performed within the designated work area shown on the Plans.

Soil excavated or removed from one designated area shall not be relocated to or mixed with soil from another designated area.

Soil removed from the Blue Area shall remain within the Blue Area. Soil removed from the Orange Area shall remain within the Orange Area. Excavated soil may only be transported outside its respective desig-nated area if its removed from the project site and properly disposed of at an approv-ed landfill or other legally authorized disposal facility.

The contractor shall be responsible for main-taining the separation of soils throughout all phases of the Work and shall not commingle soils between designated areas. An unauth-orized relocation or commingling of soils shall be corrected by the Contractor at no additional cost to the Owner.

Mary Bush Rectangle

Mary Bush Line

Mary Bush Line

Mary Bush Line

Mary Bush Line

Mary Bush Line

Mary Bush Line

Mary Bush Line

File details come from the government source that posted it. Updated .