This is an Electrical Project Manual for the Escambia County Area Transit Facility (Project No. 2613) located at 100 Clarinda Lane in Pensacola, Florida, prepared by Architectural Design Group, Inc. The document establishes the electrical specifications and requirements for the new ECAT Facility infrastructure project, which includes an Administration Building, Bus Wash, Fuel Depot, and Maintenance Building. The electrical work encompasses underground raceways, common work results, raceways and boxes, and conduit identification systems. The contractor is responsible for providing and installing fully functional electrical systems, including all minor details necessary for system operation, and must ensure compliance with Florida Building Codes, Pensacola city codes, and Escambia County standards. All materials must be new and free of defects, with equipment warranty required for a minimum of one year from factory supervised startup or substantial completion, whichever is later, and contractor warranty for one year from substantial completion. Shop drawings must be submitted electronically in PDF format and reviewed by the Engineer prior to fabrication or installation, with the contractor bearing costs for resubmittals beyond the first review.
The specifications require the electrical contractor to coordinate all work with other trades and maintain daily record drawings documenting changes and deviations from contract specifications. Underground conduit installations must be buried a minimum of 24 inches below finished grade with red flagging tape and tracer wire for identification, and all conduits must be labeled at both ends with intended system and destination information. The contractor must obtain all required permits and pay associated fees, notify the Construction Manager of scheduled inspections seven working days in advance, and conduct a site survey prior to bidding to understand utility routing complexities and phasing requirements. Substitution requests for alternate manufacturers must be submitted at least ten days prior to bid day, with any approved substitutions requiring the contractor to pay for associated architectural and engineering design changes. The project requires completion of as-built drawings and marked-up specifications upon project closeout.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Escambia County Project No. 2613 Area Transit Facility 100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
ELECTRICAL TABLE OF CONTENTS 260000 - 1
ELECTRICAL TABLE OF CONTENTS
SECTION TITLE PAGES
260500 Common Work Results 11 260533 Raceways and Boxes 3 260553 Identification 1
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 1
SECTION 260500 – COMMON WORK RESULTS
PART 1 - GENERAL
1.1 SCOPE
A. The work under this section includes basic electrical requirements, which are applicable to all Division 26 sections.
B. Overview of Work
1. Underground Raceways
C. In these documents, “Contractor” refers to the Electrical Contractor and all their subcontractors, unless listed otherwise. The division of Work with the electrical scope is the responsibility of the lead Electrical Contractor.
D. The Contractor is responsible for providing and installing fully functional systems.
E. If the Work is shown on the drawings or noted in the specifications, it shall be included by the Contractor.
F. If equipment is provided by the Contractor, it shall be installed by the Contractor, unless noted otherwise.
G. Drawings are necessarily diagrammatic by their nature and are not intended to show every connection in detail or every conduit in its exact location. Carefully investigate structural and civil conditions and coordinate the separate trades in order to avoid interference between the various phases of Work.
H. Install the Work complete, including minor details necessary to perform the function indicated. Review pertinent Drawings and adjust the Work to conditions shown. Where discrepancies occur between Drawings, Specifications, and actual field conditions, immediately notify the Architect and Engineer for interpretations.
I. All sizes as given are minimum except as noted.
J. All materials shall be new (unless noted or stated otherwise) and free of defect.
K. All work shall be subject to the Architect’s, Engineer’s, and Owner’s observations from the commencement of work until the acceptance of the completed work.
1.2 RELATED WORK
A. Applicable provisions of Division 0 and Division 1 govern work under this Section.
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 2
1.3 REFERENCES
A. All work shall conform to the most current version of all applicable codes and standards or the version adopted by the jurisdiction.
B. Codes
1. Florida Building Codes
2. State or City Codes for Pensacola, Florida.
C. Standards
1. Escambia County Published Standards
D. Governing Bodies
1. Owner’s Insurance Company
2. State Fire Marshall
3. AHJ – Authority Having Jurisdiction
4. UL - Underwriters Laboratories
1.4 SUBMITTALS
A. The review of Shop Drawings by the Engineer is for general conformance with the design concept of the project and general compliance with the information given in the Contract Documents. Corrections or comments made on the shop drawings during this review do not relieve the contractor from compliance with the requirements of the Plans and Specifications. Approval of a specific item shall not include approval of an assembly of which the item is a component. The Contractor is responsible for: dimensions to be confirmed and correlated at the jobsite; information that pertains solely to the fabrication processes or to the means, methods, techniques, sequences and procedures of construction; coordination with the Work of all trades; and for performing all work in a safe and satisfactory manner.
B. Refer to individual technical Specification sections for specific submittal requirements.
C. Submission of Shop Drawings electronically in .PDF format is required.
D. If hard copies of shop drawings are required for this project, coordinate the quantity with the Architect and General Contractor. Provide one (1) copy for the Engineer’s records.
E. The Engineer will review one (1) resubmittal for each product. If additional resubmittals are required, the Contractor shall be responsible to bear the cost for the Engineer to recheck and handle the additional shop drawing submittals. Documents will not be reviewed until payment is agreed upon.
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 3
F. Contractor may request electronic files from the Engineer if needed to complete their Shop Drawings.
An Electronic File Request Form will be sent to the contractor if files are requested and must be completed and signed before the AutoCAD files are released to the Contractor.
G. All submittals for equipment and materials shall be reviewed and approved by the Engineer prior to the fabrication or release by the contractor. This includes the coordination of equipment between trades. The release, purchase, installation or fabrication of any items prior to the contractor receiving an approved shop drawing will be at the contractor’s own risk. Any rework that results will be provided by the contractor at no cost to the Owner or design team.
H. Submittals must be reviewed and approved by the Contractor before submitting to the Engineer.
I. Submittals shall be grouped to include complete submittals of related systems, products, and accessories in a single submittal. Mark dimensions and values in units to match those specified. Include wiring diagrams of electrically powered equipment.
1.5 ELECTRONIC DOCUMENT RELEASE
A. Electronic versions of the bid documents will be made available to the contractors for use during the bidding process and to help generate fabrication drawings for various systems. A summary of the requirements for the various document types is listed below:
1. PDF
a. Contact the Construction Manager or Architect to obtain a PDF version of the Bid Documents. No Document Release Form is required.
2. AutoCAD
a. KEDbluestone Engineering can provide an AutoCAD version of the bid documents for the contractor to use for generating shop drawings and fabrication drawings. This will include plan drawings with the architectural background. The contractor is responsible for incorporating any modifications that occur during bidding by all disciplines. Details and schedules will not be included.
b. A document release form (see attached) will be required to be completed by the contractor to determine the version of AutoCad and drawings required. No fee is associated with these drawings.
3. REVIT
a. The REVIT drawings will be converted to AutoCAD and then transferred to the contractor.
b. KEDbluestone Engineering can provide an AutoCAD version of the bid documents for the contractor to use for generating shop drawings and fabrication drawings. This will include plan drawings with the architectural background. The contractor is responsible for incorporating any modifications that occur during bidding by all disciplines. Details and schedules will not be included.
c. A document release form (see attached) will be required to be completed by the contractor to determine the version of AutoCad and drawings required.
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 4
d. Submittal of the document release form fee will be required prior to the AutoCAD files being transmitted.
1.6 SUBSTITUTIONS
A. All manufacturers listed as Acceptable Manufacturers in each specification section are considered equal to the basis of design. The basis of design is preferred and will take precedence. Any products from an alternate approved manufacturer need to meet the requirements and performance specified and shall be equal to the basis of design.
B. The Contractor may request permission for a substitution of any item (equipment or material), subject to the following conditions:
1. Submit substitution requests in writing to the Engineer, on a form supplied by the Engineer. A sample copy of this form is included at the end of this section. An electronic copy can also be provided to the Contractor by the Engineer.
2. Where equipment or accessories are used which differ in arrangement, configuration, dimensions, ratings, or engineering parameters from those indicated on the contractor documents, the Contractor is responsible for all costs involved in integrating the equipment or accessories into the system and the assigned space and for obtaining the performance from the system into which these items are placed as well as any re-design costs incurred by the Architect or Engineer. The Contractor is also responsible for coordinating changes required by other trades.
3. Any requests for alternate manufacturers must be submitted to the Architect/Engineer at least ten
(10) days prior to bid day. Incomplete substitution requests will not be considered.
C. Approval
1. No work involving requests for substitution shall commence without written approval on the provided form by the Engineer.
2. Any work started or material ordered/installed by the Contractor without written approval shall be removed/repaired at the sole expense of the contractor. The Contractor will also be responsible for any costs incurred by the Owner for such rework.
1.7 QUALITY ASSURANCE
A. Warranty
1. Equipment warranty shall be a minimum of one (1) year from date of factory supervised startup or from the date of substantial completion, whichever is later.
2. Contractor shall warranty all of their work for one (1) year from the date of substantial completion
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 5
B. These documents are diagrammatical in nature and intended to convey scope and general arrangement of the electrical and technology systems. Not all conduits, junction boxes, accessories, etc. are shown on Plan. If items are required to make a system fully operational but not shown on Plan or in these Specifications, they shall be included by the Contractor.
C. The intent of the Drawings is to establish the types of systems and functions; not to set forth each item essential to the functioning of the system. Install the Work complete, including minor details necessary to perform the function indicated. Review pertinent Drawings and adjust the Work to conditions shown. Where discrepancies occur between Drawings, Specifications, and actual field conditions, immediately notify the Architect and Engineer for interpretations.
D. It is the contractor’s responsibility to determine all utility routing prior to purchase and installation of material.
E. For remodel or addition projects, the contractor shall visit and survey the site prior to submitting a bid.
The contractor shall visit the site to understand the complexity of utility routing, phasing, staging, and all general installation. Submitting a bid means the contractor acknowledges the complexities of the project and has made provisions for overcoming these complexities in their bid.
F. The Contractor shall report any discrepancies between these documents and site conditions immediately to the Engineer prior to submitting a bid or starting work. Submittal of a bid indicates that the contractor and the contractor’s subcontractors have carefully and thoroughly reviewed the Drawings, Specifications, and other construction documents and have found them complete and free from ambiguities and sufficient for the purposes intended.
G. Install all equipment per the manufacturer’s requirements / recommendations.
H. No equipment or material provided or installed shall contain mercury.
I. All equipment shall be UL listed where applicable.
1.8 REGULATORY AND UTILITY REQUIREMENTS
A. Contractor is responsible for coordinating all required site inspections by authorities having jurisdiction.
Contractor shall notify Construction Manager of all scheduled inspections seven (7) working days prior to site visit.
B. Contractor is responsible for paying for all fees, permits, and inspections that are required to complete their work.
C. Contractor shall include all work required to install new utility pathways as shown on drawings.
1.9 PROVISIONS FOR FUTURE WORK
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 6
A. Coordinate final location of equipment, equipment pads, building footings, and connection points for ease of extension. All pathways to be marked with coordinate or dimension to the nearest foot for future locating for extension.
1.10 OMISSIONS
A. No later than ten (10) days before bid opening, the Contractor shall call the attention of the Architect and Engineer to any materials or apparatus the Contractor believes to be inadequate and to any necessary items of work omitted.
1.11 DELIVERY, STORAGE, AND HANDLING
A. All equipment and materials shall be protected during shipment and storage against physical damage, vermin, dirt, corrosive substances, fumes, moisture, cold and rain.
B. Take such precautions as are necessary to protect materials from damage. Damaged material shall be, as determined by the Owner and/or Engineer, placed in first class operating condition or be repaired or replaced.
1.12 DIVISION OF WORK AND COORDINATION
A. Any installed work that is not coordinated and that interferes with other contractor's work shall be removed or relocated at the installing contractor's expense.
B. Arrange for conduit to align with future openings in building structure to allow for electrical installations.
C. Coordinate installation of required supporting devices and set sleeves in poured-in-place concrete and other structural components as they are constructed.
1.13 SALVAGE MATERIALS
A. All materials removed shall become the property of, and shall be disposed of by, the Contractor except for items the Owner has designated they will keep.
1. qualifications.
1.14 RECORD DRAWINGS
A. The Contractor shall maintain at least one (1) copy of the Specifications and Drawings on the job site at all times.
B. The Architect will provide the Contractor with a suitable set of Contract Drawings on which daily records of changes and deviations from contract shall be recorded. Dimensions and elevations on the record drawings shall locate all buried or concealed piping, conduit, or similar items.
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 7
C. The daily record of changes shall be the responsibility of Contractor's field superintendent. No arbitrary mark-ups will be permitted.
D. At completion of the project, the Contractor shall submit the marked-up record drawings to the General Contractor/Construction Manager prior to final payment.
PART 2 - PRODUCTS
2.1 IDENTIFICATION
A. See Electrical Section 260553 – Identification.
PART 3 - EXECUTION
3.1 EXCAVATION AND BACKFILL
A. Perform all excavation and backfill work to accomplish indicated electrical systems installation in accordance with Division 31
3.2 CONCRETE WORK
A. The Division 3 Contractor will perform all cast-in-place concrete unless noted otherwise elsewhere.
Provide all layout drawings, anchor bolts, metal shapes, and/or templates required to be cast into concrete or used to form concrete for the support of electrical equipment.
3.3 COORDINATION
A. The Contractor shall cooperate with other trades in locating work in a proper manner. Should it be necessary to raise or lower or move longitudinally any part of the electrical work to better fit the general installation, such work shall be done at no extra cost provided such decision is reached prior to actual installation.
B. Coordinate all work with other contractors prior to installation. Any installed work that is not coordinated and that interferes with other contractor's work shall be removed or relocated at the installing Contractor's expense.
3.4 HOUSEKEEPING AND CLEAN UP
A. The Contractor shall clean up and remove from the premises, daily, all debris and rubbish resulting from its work and shall repair all damage to equipment resulting from its work. When job is complete, this Contractor shall remove all tools, excess material and equipment, etc., from the site.
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 8
3.5 PROJECT CLOSEOUT REQUIREMENTS
A. Final project closeout tasks
1. All conduits labeled per specifications.
2. All conduits cleaned and ready for use. Install new fuses in all equipment with fuses; do not use Owner’s spare fuses.
B. Contractor requirements
1. Marked up drawings and specifications provided to Engineer for incorporation of as-built drawings or to serve as the as-built drawings depending on the project requirements. As-built drawings shall be clean and legible.
END OF SECTION 260500
(ELECTRONIC DOCUMENT RELEASE FORM & SUBSTITUTION REQUEST FORMS ATTACHED)
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 9
Document Release Form
Information Requested:
Project Name:
Drawings Requested:
Media Type: (Check all that are applicable)
AutoCAD DWG Files (Version _____) Adobe PDF Files
REVIT Files (Version _____) Other
Requesting Party:
Name: Address 1:
Company: Address 2:
Signature: Email Address:
Date: Phone #:
KEDbluestone Use:
Form Sent By: Date:
KEDbluestone Project #:
Data contained on these electronic files are part of our instruments of service and shall not be used by you or anyone else receiving these data through or from you for any purpose other than as a convenience in the preparation of shop drawings for the referenced project. Any other use or reuse by you or by others will be at your sole risk and without liability or legal exposure to us. You agree to make no claim and hereby waive, to the fullest extent permitted by law, any claim or cause of action of any nature against us, our officers, directors, employees, agents or sub consultants that may arise out of or in connection with your use of the electronic files. Furthermore, you shall, to the fullest extent permitted by law, indemnify and hold us harmless against all damages, liabilities or costs, including reasonable attorneys’ fees and defense costs, arising out of or resulting from your use of these electronic files. These electronic files are not construction documents. Differences may exist between these electronic files and corresponding hard-copy construction documents. We make no representation regarding the accuracy or completeness of the electronic files you receive. In the event that a conflict arises between the signed or sealed hard-copy construction documents prepared by us and the electronic files, the signed or sealed hard-copy construction documents shall govern. You are responsible for determining if any conflict exists. By your use of these electronic files, you are not relieved of your duty to fully comply with the contract documents, including, and without limitation, the need to check, confirm and coordinate all dimensions and details, take field measurements, verify field conditions and coordinate your work with that of other contractors for the project. Because information presented on the electronic files can be modified, unintentionally or otherwise, we reserve the right to remove all indicia of ownership and/or involvement from each electronic display.
5518 NW 88th Street | Johnston, IA 50131 | P 515.727.0700 | F 515.727.0777 | www.KEDbluestone.com http://www.kedbluestone.com/
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 10
SUBSTITUTION REQUEST FORM (DURING BIDDING)
We submit for your consideration the following product instead of the specified item for the following project:
PROJECT:
SPEC. SECTION SPEC. TITLE PARAGRAPH SPECIFIED ITEM
Proposed Substitution:
MANUFACTURER TRADE NAME MODEL NO.
Attached data includes product description, specifications, drawings, photographs, and performance and test data adequate for evaluation of the request; applicable portions of the data are clearly identified.
Attached data also includes a description of changes to the Contract Documents that the proposed substitution will require for its proper installation.
The Undersigned certifies:
• Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.
• Same warranty will be furnished for proposed substitution as for specified product.
• Same maintenance service and source of replacement parts, as applicable, is available.
• Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.
• Proposed substitution does not affect dimensions and functional clearances.
• Payment will be made for changes to building design, including Architectural and Engineering design, detailing, and construction costs caused by the substitution.
Submitted by:
Signature
Firm
Telephone Email Date
Engineer’s Review and Action
Substitution Approved Substitution Approved As Noted
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 11
Substitution Rejected Substitution Request Received Too Late
Signed by:
Date
Supporting Data Attached:
Drawings Product Data Samples Tests Reports Other _______
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 12
SUBSTITUTION REQUEST FORM (AFTER BIDDING)
We submit for your consideration the following product instead of the specified item for the following project:
PROJECT:
SPEC. SECTION SPEC. TITLE PARAGRAPH SPECIFIED ITEM
Proposed Substitution:
MANUFACTURER TRADE NAME MODEL NO.
INSTALLER PHONE NO.
History: New Product 2-5 years old 5-10 years old More than 10 years old
Differences between proposed substitution and specified product:
Proposed substitution affects other parts of Work: No Yes; explain
Proposed substitution changes Contract Time: No Yes [Add] [Deduct] days
Savings to Owner for accepting substitution: $
The Undersigned certifies:
• Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.
• Same warranty will be furnished for proposed substitution as for specified product.
• Same maintenance service and source of replacement parts, as applicable, is available.
• Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.
• Cost data as stated above is complete. Claims for additional costs related to accepted substitution which may subsequently become apparent are to be waived.
• Proposed substitution does not affect dimensions and functional clearances.
• Payment will be made for changes to building design, including Architectural and Engineering design, detailing, and construction costs caused by the substitution.
• Coordination, installation, and changes in the Work as necessary for accepted substitution will be complete in all respects.
Submitted by:
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
COMMON WORK RESULTS 260500 - 13
Signature Firm Telephone Email Date
Engineer’s Review and Action
Substitution Approved Substitution Approved As Noted Substitution Rejected Substitution Request Received Too Late
Signed by:
Date
Supporting Data Attached:
Drawings Product Data Samples Tests Reports Other ________
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
RACEWAYS AND BOXES 260533 - 1
SECTION 260533 – RACEWAYS AND BOXES
PART 1 - GENERAL
1.1 SCOPE
A. Perform all Work required to provide and install the following conduits, surface raceways, multi-outlet assemblies, auxiliary gutters, wall duct, and boxes for electrical systems including wall and ceiling outlet boxes, floor boxes, and junction boxes.
1.2 SUBMITTALS
A. Conduits: Submit product data and catalog sheets for all components.
B. Handholes: Submit product data and catalog sheets for all components.
PART 2 - PRODUCTS
2.1 RIGID NONMETALLIC CONDUIT AND FITTINGS
A. Conduit: Schedule 40 PVC minimum, Listed, sunlight resistant, rated for 90° C conductors.
B. Fittings and Conduit Bodies: NEMA TC 2, Listed.
2.2 PULL AND JUNCTION BOXES
A. Fiberglass or Concrete Handholes:
1. With weatherproof cover of non-skid finish shall be used for underground installations.
2. Size, type, weight rating, and labeling shall be as noted on the drawings.
3. All handholes and junction/pull boxes shall be Tier 22 load rated.
2.3 GENERAL
A. All boxes shall be of sufficient size to provide free space for all conductors enclosed in the box and shall comply with NEC requirements.
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
RACEWAYS AND BOXES 260533 - 2
PART 3 - EXECUTION
3.1 CONDUIT SIZING, ARRANGEMENT, AND SUPPORT
A. Arrange conduit to maintain headroom and present a neat appearance.
B. Arrange conduit supports to prevent distortion of alignment by wire pulling operations.
C. Do not fasten conduit with wire or perforated pipe straps. Before conductors are pulled, remove all wire used for temporary conduit support during construction.
D. Changes in direction shall be made with symmetrical bends.
3.2 CONDUIT INSTALLATION
A. Cut conduit square; de-burr cut ends.
B. Bring conduit to the shoulder of fittings and couplings and fasten securely.
C. Use conduit hubs for fastening conduit to boxes.
D. Install no more than the equivalent of four (4) 90 degree bends between boxes.
E. Conduit shall be bent according to manufacturers’ recommendations. Torches or open flame shall not be used to aid in bend of PVC conduit.
F. Use suitable conduit caps or other approved seals to protect installed conduit against entrance of dirt and moisture.
G. Provide 1/8 inch nylon pull string in all conduits, except sleeves and nipples.
H. Install expansion-deflection joints where conduit crosses building expansion joints. Note: expansion-deflection joints are not required where conduit crosses building control joints if the control joint does not act as an expansion joint. Install expansion fitting in PVC conduit runs as recommended by the manufacturer.
I. Avoid moisture traps where possible. Where moisture traps are unavoidable, provide junction boxes with drain fittings at conduit low points.
J. Identify conduit under provisions of Section 260553.
K. All conduit installed underground (exterior to building) shall be buried a minimum of 24” below finished grade, whether or not the conduit is concrete encased.
1. All underground conduits shall be installed with “DANGER – BURIED ELECTRICAL CONDUIT” red flagging tape 6-inches above conduit. Tape shall be continuous along the conduit run.
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
RACEWAYS AND BOXES 260533 - 3
2. Tracer wire shall be installed on all exterior electrical utilities. Trace wire to be fourteen (14) gauge minimum solid copper with thermoplastic insulation recommended for direct burial. Wire connectors to be 3M DBR, or approved equal, and shall be watertight to provide electrical continuity. Install trace wire in the same trench with the conduit during installation and secure to conduit as required to ensure that the wire remains adjacent to the conduit. Trace wire access points shall in general be no more than 500’ apart.
L. PVC conduit shall be cleaned with solvent, and dried before application of glue. The temperature rating of glue/cement shall match weather condition. Apply full even coat of cement/glue to entire area that will be inserted into fitting. The entire installation shall meet manufacturers’ recommendations.
3.3 CONDUIT INSTALLATION SCHEDULE
A. Conduit other than that specified below for specific applications shall not be used.
B. Underground Installations Within Five Feet of Foundation Wall: Rigid steel conduit.
C. Underground Installations: Schedule 40 PVC conduit.
D. Directional Boring: HDPE conduit.
3.4 PULL AND JUNCTION BOX INSTALLATION
A. Locate pull boxes and junction boxes above accessible ceilings, in unfinished areas or furnish and install access panels in non-accessible ceilings where boxes are installed. All boxes are to be readily-accessible.
B. Support pull and junction boxes independent of conduit.
C. All handholes and junction/pull boxes shall have the top of the box installed at finished grade. Electrical contractor is responsible for verifying final grade height with civil engineer.
END OF SECTION 260533
Escambia County Project No. 2613
100 Clarinda Lane Pensacola, Florida 32505
Architectural Design Group, Inc.
IDENTIFICATION 260553 - 1
SECTION 260553 - IDENTIFICATION
PART 1 - GENERAL
1.1 SCOPE
A. Perform all Work required to provide and install the labeling of conduits.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Labels: All labels shall be permanent, and machine generated. NO HANDWRITTEN OR NON-PERMANENT LABELS ARE ALLOWED. Exception: Back side of device plates and junction boxes may use handwritten, legible labeling on box covers, unless specifically prohibited by other specification sections.
B. Cable label size shall be appropriate for the conductor or cable size(s), outlet faceplate layout and patch panel design. All labels shall be self-laminating, white/transparent vinyl and be
PART 3 - EXECUTION
3.1 GENERAL
A. Label both end of conduits with permanent marker with intended system and destination. Refer to conduit schedule on drawings for additional information.
3.2 HANDHOLE AND PULLBOX IDENTIFICATION
A. Conduits entering all handholes, junction, and pull boxes shall be label for system served, and destination.
B. Handhole covers shall be labeled with “ELECTRICAL”, or “TECHNOLOGY” as applicable for system served.
END OF SECTION 260553