Add 1 2b Addendum 1 Spec Section 07 84 00 FA441820R0010 B.419.pdf
PDF 26 KB Posted
- Attached to
- Repair Munitions Facility B419 Federal contract opportunity
- Solicitation number
- FA441820R0010
About this file
This document provides details for a firm-fixed price solicitation to repair Munitions Facility B419 at Joint Base Charleston - Weapons Station in Goose Creek, South Carolina. The contractor shall provide all personnel, equipment, materials, tools and supervision necessary to complete the repair project within a 450 calendar day performance period. A mandatory site visit is scheduled for 7 May 2020 at the base's Red Bank Visitor Control Center parking lot. The solicitation was issued by the Department of the Air Force Air Mobility Command for repair of the specified munitions facility located at Joint Base Charleston - Weapons Station. Interested offerors must attend the site visit and provide attendee information by email no later than 5 May 2020 to obtain full project details.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Renovation of Munitions WS Building 419 JBC Project No. DKGV 14-2080 March 3, 2020 Addendum No. 1
SECTION 07 84 00
FIRESTOPPING
05/10
PART 1 GENERAL
1.1 SUMMARY
Furnish and install tested and listed firestopping systems, combination of materials, or devices to form an effective barrier against the spread of flame, smoke and gases, and maintain the integrity of fire resistance rated walls, partitions, floors, and ceiling-floor assemblies, including through-penetrations and construction joints and gaps.
a. Through-penetrations include the annular space around pipes, tubes, conduit, wires, cables and vents.
b. Construction joints include those used to accommodate expansion, contraction, wind, or seismic movement; firestopping material shall not interfere with the required movement of the joint.
Gaps requiring firestopping include gaps between the curtain wall and the floor slab and between the top of the fire-rated walls and the roof or floor deck above and at the intersection of shaft assemblies and adjoining fire resistance rated assemblies.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E84 (2018a) Standard Test Method for Surface Burning Characteristics of Building Materials
ASTM E119 (2018c; E 2018) Standard Test Methods for Fire Tests of Building Construction and Materials
ASTM E814 (2013a; R 2017) Standard Test Method for Fire Tests of Penetration Firestop Systems
ASTM E1399/E1399M (1997; R 2017) Standard Test Method for Cyclic Movement and Measuring the Minimum and Maximum Joint Widths of Architectural Joint Systems
ASTM E1966 (2015; R 2019) Standard Test Method for Fire-Resistive Joint Systems
ASTM E2174 (2014b) Standard Practice for On-Site Inspection of Installed Fire Stops
SECTION 07 84 00 Page 1
ASTM E2307 (2015a) Standard Test Method for Determining Fire Resistance of Perimeter Fire Barrier Systems Using Intermediate-Scale, Multi-story Test Apparatus
ASTM E2393 (2010a) Standard Practice for On-Site Inspection of Installed Fire Resistive Joint Systems and Perimeter Fire Barriers
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
INTERNATIONAL CODE COUNCIL (ICC)
ICC IBC (2018) International Building Code
UNDERWRITERS LABORATORIES (UL)
UL 723 (2018) UL Standard for Safety Test for Surface Burning Characteristics of Building Materials
UL 1479 (2015) Fire Tests of Through-Penetration Firestops
UL 2079 (2004; Reprint Dec 2014) Tests for Fire Resistance of Building Joint Systems
UL Fire Resistance (2014) Fire Resistance Directory
1.3 SEQUENCING
Coordinate the specified work with other trades. Apply firestopping materials, at penetrations of pipes and ducts, prior to insulating, unless insulation meets requirements specified for firestopping. Apply firestopping materials. at building joints and construction gaps, prior to completion of enclosing walls or assemblies. Cast-in-place firestop devices shall be located and installed in place before concrete placement. Pipe, conduit or cable bundles shall be installed through cast-in-place device after concrete placement but before area is concealed or made inaccessible. Firestop material shall be inspected and approved prior to final completion and enclosing of any assemblies that may conceal installed firestop.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Firestopping System ; G
SECTION 07 84 00 Page 2
SD-03 Product Data
Firestopping Materials ; G
SD-06 Test Reports
Inspection ; G
SD-07 Certificates
Firestopping Materials
1.5 QUALITY ASSURANCE
1.6 DELIVERY, STORAGE, AND HANDLING
Deliver materials in the original unopened packages or containers showing name of the manufacturer and the brand name. Store materials off the ground, protected from damage and exposure to elements and temperatures in accordance with manufacturer requirements. Remove damaged or deteriorated materials from the site. Use materials within their indicated shelf life.
PART 2 PRODUCTS
2.1 FIRESTOPPING SYSTEM
Submit detail drawings including manufacturer's descriptive data, typical details conforming to UL Fire Resistance or other details certified by another nationally recognized testing laboratory, installation instructions or UL listing details for a firestopping assembly in lieu of fire-test data or report. For those firestop applications for which no UL tested system is available through a manufacturer, a manufacturer's engineering judgment, derived from similar UL system designs or other tests, shall be submitted for review and approval prior to installation.
Submittal must indicate the firestopping material to be provided for each type of application. When more than a total of 5 penetrations and/or construction joints are to receive firestopping, provide drawings that indicate location, "F" "T" and "L" ratings, and type of application.
Also, submit a written report indicating locations of and types of penetrations and types of firestopping used at each location; record type by UL list printed numbers.
2.2 FIRESTOPPING MATERIALS
Provide firestopping materials, supplied from a single domestic manufacturer, consisting of commercially manufactured, asbestos-free, nontoxic products FM APP GUIDE approved, or UL listed, for use with applicable construction and penetrating items, complying with the following minimum requirements:
2.2.1 Fire Hazard Classification
Material shall have a flame spread of 25 or less, and a smoke developed rating of 50 or less, when tested in accordance with ASTM E84 or UL 723 .
Material shall be an approved firestopping material as listed in UL Fire Resistance or by a nationally recognized testing laboratory.
SECTION 07 84 00 Page 3
2.2.2 Toxicity
Material shall be nontoxic and carcinogen free to humans at all stages of application or during fire conditions and shall not contain hazardous chemicals or require harmful chemicals to clean material or equipment.
2.2.3 Fire Resistance Rating
Firestop systems shall be UL Fire Resistance listed or FM APP GUIDE approved with "F" rating at least equal to fire-rating of fire wall or floor in which penetrated openings are to be protected. Where required, firestop systems shall also have "T" rating at least equal to the fire-rated floor in which the openings are to be protected.
2.2.3.1 Through-Penetrations
Firestopping materials for through-penetrations, as described in paragraph SUMMARY, shall provide "F", "T" and "L" fire resistance ratings in accordance with ASTM E814 or UL 1479 . Fire resistance ratings shall be as follows:
2.2.3.1.1 Penetrations of Fire Resistance Rated Walls and Partitions
F Rating = Rating of wall or partition being penetrated.
2.2.3.1.2 Penetrations of Fire Resistance Rated Floors, Floor-Ceiling Assemblies and the Ceiling Membrane of Roof-Ceiling Assemblies
F Rating = 1 hour, T Rating = 1 hour. Where the penetrating item is outside of a wall cavity the F rating must be equal to the fire resistance rating of the floor penetrated, and the T rating shall be in accordance with the requirements of ICC IBC .
2.2.3.1.3 Penetrations of Fire and Smoke Resistance Rated Walls, Floors, Floor-Ceiling Assemblies, and the ceiling membrane of Roof-Ceiling Assemblies
F Rating = 1 hour, T Rating = 1 hour and L Rating = Where L rating is required.
2.2.3.2 Construction Joints and Gaps
Fire resistance ratings of construction joints, as described in paragraph SUMMARY, and gaps such as those between floor slabs and curtain walls shall be the same as the construction in which they occur. Construction joints and gaps shall be provided with firestopping materials and systems that have been tested in accordance with ASTM E119, ASTM E1966 or UL 2079 to meet the required fire resistance rating. Curtain wall joints shall be provided with firestopping materials and systems that have been tested in accordance with ASTM E2307 to meet the required fire resistance rating.
Systems installed at construction joints shall meet the cycling requirements of ASTM E1399/E1399M or UL 2079 . All joints at the intersection of the top of a fire resistance rated wall and the underside of a fire-rated floor, floor ceiling, or roof ceiling assembly shall provide a minimum class II movement capability.
2.2.4 Material Certification
Submit certificates attesting that firestopping material complies with the
SECTION 07 84 00 Page 4 specified requirements. For all intumescent firestop materials used in through penetration systems, manufacturer shall provide certification of compliance with UL 1479 .
PART 3 EXECUTION
3.1 PREPARATION
Areas to receive firestopping must be free of dirt, grease, oil, or loose materials which may affect the fitting or fire resistance of the firestopping system. For cast-in-place firestop devices, formwork or metal deck to receive device prior to concrete placement must be sound and capable of supporting device. Prepare surfaces as recommended by the manufacturer.
3.2 INSTALLATION
Completely fill void spaces with firestopping material regardless of geometric configuration, subject to tolerance established by the manufacturer. Firestopping systems for filling floor voids 4 inches or more in any direction must be capable of supporting the same load as the floor is designed to support or be protected by a permanent barrier to prevent loading or traffic in the firestopped area. Install firestopping in accordance with manufacturer's written instructions. Provide tested and listed firestop systems in the following locations, except in floor slabs on grade:
a. Penetrations of duct, conduit, tubing, cable and pipe through floors and through fire-resistance rated walls, partitions, and ceiling-floor assemblies.
b. Penetrations of vertical shafts such as pipe chases, elevator shafts, and utility chutes.
c. Gaps at the intersection of floor slabs and curtain walls, including inside of hollow curtain walls at the floor slab.
d. Gaps at perimeter of fire-resistance rated walls and partitions, such as between the top of the walls and the bottom of roof decks.
e. Construction joints in floors and fire rated walls and partitions.
f. Other locations where required to maintain fire resistance rating of the construction.
3.2.1 Insulated Pipes and Ducts
Thermal insulation shall be cut and removed where pipes or ducts pass through firestopping, unless insulation meets requirements specified for firestopping. Replace thermal insulation with a material having equal thermal insulating and firestopping characteristics.
3.2.2 Fire Dampers
Install and firestop fire dampers in accordance with Section 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEM. Firestop installed with fire damper must be tested and approved for use in fire damper system. Firestop installed with fire damper must be tested and approved for use in fire damper system.
SECTION 07 84 00 Page 5
3.2.3 Data and Communication Cabling
Cabling for data and communication applications shall be sealed with re-enterable firestopping products .
3.2.3.1 Re-Enterable Devices
Firestopping devices shall be pre-manufactured modular devices, containing built-in self-sealing intumescent inserts. Firestopping devices shall allow for cable moves, additions or changes without the need to remove or replace any firestop materials. Devices must be capable of maintaining the fire resistance rating of the penetrated membrane at 0 percent to 100 percent visual fill of penetrants; while maintaining "L" rating of <10 cfm/sf at 0 percent to 100 percent visual fill.
3.2.3.2 Re-Sealable Products
Provide firestopping pre-manufactured modular products, containing self-sealing intumescent inserts. Firestopping products shall allow for cable moves, additions or changes. Devices shall be capable of maintaining the fire resistance rating of the penetrated membrane at 0 percent to 100 percent visual fill of penetrants.
3.3 INSPECTION
For all projects, the firestopped areas shall not be covered or enclosed until inspection is complete and approved by the Contracting Officer.
Inspect the applications initially to ensure adequate preparations (clean surfaces suitable for application, etc.) and periodically during the work to assure that the completed work has been accomplished according to the manufacturer's written instructions and the specified requirements.
Submit written reports indicating locations of and types of penetrations and types of firestopping used at each location; type shall be recorded by UL listed printed numbers.
3.3.1 Inspection Standards
Inspect all firestopping in accordance with ASTM E2393 and ASTM E2174 for firestop inspection, and document inspection results to be submitted.
3.3.2 Inspection Reports
Submit inspection report stating that firestopping work has been inspected and found to be applied according to the manufacturer's recommendations and the specified requirements.
-- End of Section --