This is a Statement of Work (SOW) for repair and upgrades to fire alarm systems at seven Missile Alert Facilities (MAFs D-01, E-01, F-01, I-01, L-01, N-01, and O-01) located at Malmstrom Air Force Base, Montana. The project is identified as NZAS 25-0008 and is managed by 341 CES/CEM (Civil Engineer Squadron/Civil Engineer Management).

The contractor must deliver comprehensive design and installation services including new fire alarm control panels, detectors, alarm/notification devices, pull stations, conductor and raceways, HVAC modifications with automatic shutdown and duct dampers, and integration with existing standpipe suppression systems. Design must be completed by a NICET Level III Fire Alarm System certified professional and stamped by a registered professional engineer with minimum three years of experience; submittals require review by a Qualified Fire Protection Engineer. Installation must be performed by NICET Level 2 FAS technicians for fire alarm devices and NICET Level 1 FAS or licensed electricians for conduit work. The contractor must conduct independent third-party asbestos and lead-based paint testing with full laboratory analysis and provide 50% and 100% design submittals with all drawings and product data. The design phase has a total performance period of 73 days from delivery order signature, with specific milestones: kickoff meeting (10 days), 50% design draft (14 days), government review (7 days), 100% final submittal (14 days), government acceptance (7 days), and installation/testing/training per location (21 days). All work must comply with Air Force Design Guide, UFC criteria, National Electric Code, NFPA guidance, OSHA, EPA, ASHRAE regulations, Life Safety Code, and applicable Montana state and local codes. Drawings must be in AutoCAD 2024 or older, with documents in current Microsoft Office formats. The government will provide existing site and building plans if available, standard USAF title blocks, submittal schedule templates, and General Requirements sections on Microsoft Word.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Fire Alarm, MAF D-01, E-01, F-01, I-01, L-01, N-01, and O-01

All Services

Project Number NZAS 25-0008

341 CES/CEM

Malmstrom AFB, MT

GENERAL REQUIREMENTS

1.00 General Scope

The Contractor shall perform all design, submittals, materials, installation services, and system programming and testing, required to deliver to the United States Air Force all services necessary for the accomplishment of the project entitled Repair Fire Alarm, Missile Alert Facility MAF D-01, E-01, F-01, I-01, L-01, N-01, and O-01, Project Number NZAS 25-0008, in accordance with all requirements specified within this Statement of Work.

1.01 Project Description

The purpose of this effort is to provide design/report documents and installation to repair the fire protection system at MAF D-01, E-01, F-01, I-01, L-01, N-01, and O-01 to comply with current Air Force Design Guide, Global Strike/Materials Command Design Directives, Base Standards, and referenced publications. The intent is to provide an upgraded fire protection system that fully complies with current USAF design standards, Unified Facilities Criteria (UFC). See the latest Unified Facilities Criteria (UFC) Design Procedures at www.wbdg.org where applicable to this design. This project design shall include the following items:

a) The design shall provide for a new fire alarm control panel, installation of new detectors and alarm/notification devices, relocation of new detectors and alarm/notification devices where applicable, installation/re-location of pull stations, and new conductor and raceways if required to meet code requirements.

b) Design shall be completed by a National Institute for Certification in Engineering Technologies, Fire Alarm System, Level III certification, at a minimum. Design submittals must bear the review stamp of a Qualified Fire Protection Engineer.

c) The design shall include all alarming and sensors for existing standpipe suppression systems.

d) The design shall provide for HVAC modifications in regard to automatic shutdown and necessary duct dampers.

e) A 50% and a 100% design submittal to include all drawings and product data for all devices to be provided for MAFB review.

f) Contractor shall provide an independent third party to perform asbestos and lead-based paint testing and surveys and the results shall be included in a report. Any previous asbestos and lead-based paint surveys shall be provided to the contractor and shall be included in the report, if available.

1.02 Construction

A. Electrical work must be performed by qualified personnel with credentials who are familiar with applicable code requirements and shall provide credential documents upon request. A NICET Level 2 FAS or higher Fire Alarm Technician shall install and terminate fire alarm devices, cabinets and panels.

An electrician or NICET Level 1 FAS shall install conduit and conductors for the fire alarm system.

Verifiable credentials consist of State, National and Local Certifications or Licenses that a Master or Journeyman Electrician may hold, depending on work being performed, and shall conform to all requirements of the project specifications. Provide Manufacturer's certificate of acceptance of the qualifications of the installing contractor to install, test, owner training, and maintain the manufacturer's equipment shall be submitted.

1.03 1.03 Period of Performance

Upon receipt of the approved delivery order the contractor complete all work up to and including solicitation document submittal according to the schedule below, with “Day 1” corresponding to the date of the signed delivery order. Submittals will be delivered to the government within each scheduled period shown, in accordance with the submittal schedule shown later in this SOW. Should an resubmittal be required, the government will provide a date for which the resubmittal is due, and the remaining milestone completion dates will be extended the same number of days. If any Government review period is completed in fewer days than shown below, no change to the next due dates will be made. If any Government review period takes longer than the indicated maximum number of days shown below, the contract will be extended by the number of days that were exceeded.

Activity Maximum # of Days Allowed

Kick off Meeting 10 days

Design 50% Investigative Report Draft 14 days

Gov’t Review of 50% Design 7 days

Design 100% Final Submittal 14 days

Gov’t Acceptance of Final Design 7 days

Installation/Testing/Training per Location 21 days

TOTAL DESIGN PERIOD OF PERFORMANCE 73 days

1.04 Government Furnished Information and Materials

The following information and materials will be made available to the Contractor:

Existing site and building plans and details, if they exist. It is the responsibility of the contractor to request these items if required, and to verify their completeness and accuracy at the project location

Standard USAF title blocks and other drawing features to be used for final contract drawings on CD

Submittal schedule format for use with MS Excel

General Requirements Section 01-00-00, Security Section 01-10-00, and Environmental Protection Section 01-36-00 on Microsoft Word

Unique fire protection or other design requirements, if applicable.

1.05 Codes, Criteria, and Regulations

The project will comply with all applicable laws, National Codes and Regulations for building construction and safety, as well as with all applicable DoD, AF, state, and local codes. Any fire protection system must be fully designed and stamped by a registered professional engineer with a minimum of three years of experience and responsibility for design of such systems. Performance specifications are not acceptable. None of these references mentioned above will be provided by the Government.

1.06 Government Criteria and Standards include (but are not limited to):

Contract User/Customer Requirements Uniform Facility Criteria (https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc) AF Design Standards and Engineering Technical Letters (https://www.wbdg.org/ffc/af-afcec) AF Regulations, Manuals, Instructions, and Mil Handbooks (https://www.e-publishing.af.mil/) Malmstrom AFB Installation Development Plan Malmstrom AFB General Plan Malmstrom AFB District Plans / Area Development Plans Malmstrom AFB Installation Facility Standards / Facilities Excellence Plan

1.07 National Codes and Regulations (latest editions) include (but are not limited to):

National Electric Code National Fire Protection Association guidance OSHA Regulations EPA Regulations ASHRAE Regulations Life Safety Code

1.08 State and Local Codes and Regulations include (but are not limited to):

Administrative Rules of the State of Montana Montana Department of Environmental Quality (DEQ) Circulars/Policies Montana Public Works Standard Specifications

1.09 Design Policy

Modern construction techniques and architectural treatment should be incorporated in the project designs to obtain both quality and economy, and to provide a functional, complete, and usable facility. Emphasis must be placed on investigative and preliminary design efforts to insure all ancillary and related work items are included in the design to eliminate any near future requirements for upgrade or repair. The project description must be used as a preliminary, basic, and abbreviated outline of work to be performed. It is the contractors responsibility to add to or modify the project content as necessary using sound professional observations, experience, and judgement. Plans and specifications must be of sufficient detail and quality to allow accurate bidding and minimize the potential for claims without the need for a site visit by potential bidders. Wherever products are specified by brand name, the contractor will provide the Government with copies of descriptive literature.

Provide dates for all documents referenced in specifications or drawings.

1.10 Energy and Environmentally Conscious Design

The contractor shall design a sustainable facility/system which improves employee productivity, enhances employee health and safety, reduces operating costs, reduces some first costs, and reduces environmental impact. The project shall strive to meet UFC 1-200-02, High Performance and Sustainable Building Design, to the maximum extent technically feasible. The project shall be designed to minimize facility/system maintenance and maximize quality of life and quality of work.

The contractor shall meet the requirements and consider the alternatives that have been identified in the National Environmental Policy Act (NEPA) process (Environmental Assessments, Environmental Impact Statements).

For all building renovation projects that require a lead-based paint and asbestos survey (according to 1.02), the survey shall determine the presence, actual location, and quantity of materials likely to be encountered during the project. Any part of the existing building that this project may impact shall be included in this survey requirement. The contractor shall be responsible for procuring an independent third party to conduct these surveys by ladder access to the building areas as required, locating, and quantifying the work requirements, repairing sample cutout areas on floors, walls, roofs, etc., and obtaining complete and accurate results. The survey reports shall be based on actual laboratory test results and not on visual observations. If lead paint or asbestos is found, the contractor is responsible for providing specifications for abatement. The Government will provide, as an attachment to this Statement of Work, the results of all lead and asbestos testing previously accomplished. The results of the surveys and all test reports are to be included in the contractor Investigative Report. The Project Specifications shall cover all abatement requirements and shall also include copies of the surveys and test reports as an appendix to the applicable specification sections. Full size drawings showing all quantities/locations of asbestos and lead based paint in the facility project work areas shall be included in the Project Drawings. The bidding requirements are to provide for bidding action for known quantities, along with unit prices for various categories of work and materials in the event of hidden quantities.

1.11 Meetings and Site Visits

Before the contractor provides a proposal bid for this project and subsequent negotiations, there will be a design pre-bid scope validation meeting between contractor and Government representatives involved with the project to ascertain that the contractor clearly comprehends and understands the various scopes of work to be performed under each type of service. During the meeting, the contractor may present their views as to how they propose to accomplish the project and to review and discuss the requirements. A site visit to the project site may be conducted following this meeting.

Once this project has been awarded to the contractor, a design kickoff meeting with the same parties as above will be held, to further discuss project requirements, the anticipated schedule, base access arrangements, etc.

After each design milestone submittal, the contractor and Government representatives will meet to discuss and resolve design review comments, before moving on to the next stage of design.

During the course of the design effort, the contractor may be called upon to attend other meetings pertaining to the project. The contractor or the Government may request coordination conferences when it is deemed necessary by both parties to clarify the work or discuss potential changes to the schedule.

The contractor shall prepare written minutes of all meetings to include attendee list and summary of meeting results / agreements. Copies of minutes shall be transmitted to the attendees within 5 business days.

All meetings and presentations will be held at Malmstrom AFB unless otherwise indicated. It is preferable that contractors representatives attend in person; however, virtual presence will be considered upon request. The contractor will schedule and arrange the virtual meeting in a platform compatible with government use (WebEx, MS Teams, etc.), while the Government will arrange for the physical meeting space and computer/projector setup for in-person meetings which also have virtual participants.

The contractor or their duly authorized representative will be required to perform an investigation of the project site and will be required to make periodic visits to the project site as part of their contract as necessary to ensure design accuracy and timely completion of the project. The contractor must provide ample advance notice of personnel needing base access, so that arrangements can be made in a timely manner.

1.12 Submittals

Data submittals shall be delivered no later than the contractually required date and will include a dated cover letter. All documents will be on recycled paper copied both sides unless specified otherwise.

The contractor will not be responsible for the time used by the Government in reviewing submittals.

1.13 Software

All drawings will be AutoCAD Release 2024, or older, generated; word processing, spreadsheets, and all documents to the extent possible will be in the most current version of Microsoft Office (conversion from other software not acceptable).

1.14 Quality Control

The contractor is responsible for the accuracy and content of their work. Government review does not relieve the contractor from the responsibility of conducting thorough in-house reviews prior to submitting to the Government. With each submittal, the names of each reviewer along with the particular areas reviewed will be submitted by separate letter entitled Certification of Quality Control. The letter will also address the total number of hours spent by these individuals in the review process.

1.15 Security Information

The contractor and their duly authorized representatives shall comply with pertinent Air Force security regulations while working on the project. Special security clearances such as CONFIDENTIAL, SECRET, etc., are not required by the contractor for the design of this project. Take all possible precautions and efforts to prevent the disclosure of any information that might provide prospective construction contractors, manufacturers, or suppliers a bidding advantage over others. Do not discuss project information with those off-base who do not have a need to know.

1.16 Anti-Terrorism (AT) Training

In accordance with DoDI O-2000.16v1_AFI 10-245-O, Antiterrorism (AT) Program Implementation, ensure Level I – AT Awareness Training is completed by all personnel within 30 days of requiring access, and annually thereafter. The training will be provided by the Government. The objective of the training is to provide personnel with requisite knowledge necessary to remain vigilant and enable employment of AT tactics, techniques, and procedures. This training will be conducted by Malmstrom AFB 341st Contracting Squadron, by providing a written pamphlet for review.

1.17 Force Protection

While on Malmstrom AFB and any associated properties under its control, including Launch Facilities (LFs), and Missile Alert Facilities (MAFs), all contractor personnel are required to abide by all real-world Force Protection Condition (FPCON) measures, random anti-terrorism measures (RAMs), shelter-in-place orders, evacuations, and lock-down notices as directed. Examples include mandatory badge or ID checks, facility single points-of-entry, and searches of hand-carried items.

END OF PART 1