This document is a Sources Sought Notice (SSN) from the National Park Service (NPS) for three separate projects to extend public boat launch ramps at Calville Bay, Echo Bay, and Hemenway Harbor within the Lake Mead National Recreation Area in Nevada.
The projects have a construction magnitude over $10 million each and involve constructing gravel roadways, new launch ramps, parking areas, and supporting infrastructure such as utilities. The NPS anticipates issuing a competitive Request for Proposals in Fall 2024 and requires bid, performance, and payment bonds. The NPS is seeking responses from both large and small businesses to gather market information and determine if a small business set-aside is feasible. Interested parties should provide their company details, bonding capacity, relevant project experience, and indicate interest in one or more of the three projects. Responses are due by June 17, 2024 at 10:00 AM.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
12795 W. ALAMEDA PKWY
P.O. BOX 25287
DENVER, COLORADO 80225-0287
In Reply Refer to:
D5215 (DSC-CS)
LAKE 318673, 324894, 332529
| Date: | 06/03/2024 |
| To: | General Public (Via the Government’s Point Entry) |
| From: | Dayna Omiya, Contracting Officer, National Park Service, Denver Service Center |
| Subject: | Sources Sought Notice |
| Reference: | LAKE 318673 EXTEND PUBLIC LAUNCH RAMP AT CALVILLE BAY; LAKE 324894 EXTEND PUBLIC LAUNCH RAMP AT ECHO BAY; LAKE 332529 EXTEND PUBLIC LAUNCH RAMP AT HEMENWAY HARBOR, LAKE MEAD NATIONAL RECREATION AREA, BOULDER CITY, NEVADA |
This is a Sources Sought Notice (SSN) for the purpose of conducting market research. Proposals are NOT being requested, nor accepted at this time. Responses are being requested from both large and small businesses. This is one (1) SSN for a potential of three (3) separate contracts.
Purpose: The purpose of this notice is to gain knowledge regarding the type of interested businesses and their qualifications. The National Park Service (NPS) will use information obtained through this notice to develop an acquisition strategy.
The Government anticipates conducting a competitive acquisition for this requirement. The amount of interest or lack thereof will determine the possibility of a small business or other socio-economical small business set-aside for the solicitation. Analysis of the quality of responses to this source sought announcement will be considered in the market research being conducted, and in the making of any small business set-aside determination for this requirement.
Additional Information: No proposal package, solicitation, specification or drawings are available with this notice.
Cost Reimbursement: Response to this announcement is strictly voluntary; no reimbursement will be made for any costs associated with providing information in response to this sources sought announcement or any follow-up information requests.
North American Industry Classification System (NAICS) code: 237990 Other Heavy and Civil Engineering Construction
Small Business Size Standard: $45,000,000
Solicitation: The NPS anticipates issuing a request for proposals in the fall of 2024.
Bonding: The NPS anticipates bid, performance and payment bonds will be required. Please provide your maximum bonding capacity.
Project Description:
LAKE 318673 EXTEND PUBLIC LAUNCH RAMP AT CALVILLE BAY:
· The project is located at Lake Mead National Recreation Area, Boulder City, Nevada
· The construction magnitude is more than $10,000,000.
· The surrounding area is rural with limited staging located at each Calville Bay.
· No unique material delivery requirements.
· The construction site is 32 miles to Boulder City, NV and 26 miles to Las Vegas, NV from nearest suppliers and lodging facilities.
· The Park will remain open during construction, thus contract activities and logistics must be structured and scheduled to minimize visitor impact. Construction of boat ramps will require phasing to allow for approximately half of the width of the ramp (min 30 ft) to remain open to the public during construction.
· The site requires protective measures to ensure the surrounding area remains undisturbed. Typical best management practices (BMP) will be required to contain the limits of disturbance.
· The structure is a not a historic/natural/cultural resource.
· The anticipated period of performance of 730 calendar days including any potential weather shutdown.
· There are seasonal/other shutdowns mandated through the construction season. Only if Razorback Sucker spawning is discovered, then Dec 1st to May 1st restriction for water based construction. Not currently anticipated for these locations. Contractor may want to schedule work based on anticipated seasonal lake level fluctuations with lake levels lowest June to Nov every year.
· Winter construction may be required. If it makes sense for the contractor based on lake levels. More likely in first season with shallow ramp installation depths. Not likely to significantly impact construction operations as location has mild winters.
Project Scope:
1. Construction of gravel roadway, a new cast-in-place and precast panel launch ramp, a gravel parking area and a cast-in-place helipad including but not limited to site clearing, excavation, fill, trenching.
| 2. | Construction of four (4) mobile toilets and solar lights at the CB launch ramp including but not limited to manufacturing, delivering and installing four (4) mobile toilets, providing and installing solar lights, layout, testing and other incidental items. |
| 3. | Construction of a buried power system generally along and within the new gravel road to provide power to the relocated Marinas, including but not limited to trenching, conduit, wire, bedding, backfill, electrical equipment, layout, testing and other incidental items. |
| 4. | Construction of a buried water system generally along and within the new gravel road to provide water to the relocated Marinas, including but not limited to trenching, piping, bedding, backfill, locator tape, tracing wire, gate valves, Reduced Pressure Principal Assembly (RPPA) backflow prevention device, flow meter, air/vac valves, Pressure Reducing Valve (PRV), layout, testing and other incidental items. |
| 5. | Construction of a buried sewer system generally along and within the new gravel road to provide sewer for the relocated Marinas, including but not limited to trenching, piping, bedding, backfill, locator tape, tracing wire, gate valves, intermediate lift station(s), air/vac valves, layout, testing and other incidental items. |
| 6. | Construction of a marina fueling station for Marina #2, including but not limited to concrete pad, fuel fill station, trenching, piping, bedding, backfill, connection/containment pod, layout, testing and other incidental items. Marina #2 has a floating fuel tank that is filled from land by gravity. |
| 7. | Construction of the parking lots for the Marinas, including but not limited to site clearing, excavation, fill. |
| 8. | Construction of the maintenance yard for the Marinas, including but not limited to site clearing, excavation, fill, trenching, stormwater culverts, aggregate base course, signage, layout, testing and other incidental items. |
LAKE 324894 EXTEND PUBLIC LAUNCH RAMP AT ECHO BAY:
· The project is located at Lake Mead National Recreation Area, Boulder City, Nevada
· The construction magnitude is more than $10,000,000.
· The surrounding area is rural with limited staging located at Echo Bay.
· No unique material delivery requirements.
· The construction site is 56 miles to Boulder City, NV and 50 miles to Las Vegas, NV from nearest suppliers and lodging facilities.
· The Park will remain open during construction, thus contract activities and logistics must be structured and scheduled to minimize visitor impact. Construction of boat ramps will require phasing to allow for approximately half of the width of the ramp (min 30 ft) to remain open to the public during construction.
· The site requires protective measures to ensure the surrounding area remains undisturbed. Typical best management practices (BMP) will be required to contain the limits of disturbance.
· The structure is a not a historic/natural/cultural resource.
· The anticipated period of performance of 730 calendar days including any potential weather shutdown.
· There are seasonal/other shutdowns mandated through the construction season. Only if Razorback Sucker spawning is discovered, then Dec 1st to May 1st restriction for water based construction. Not currently anticipated for these locations. Contractor may want to schedule work based on anticipated seasonal lake level fluctuations with lake levels lowest June to Nov every year.
· Winter construction may be required. If it makes sense for the contractor based on lake levels. More likely in first season with shallow ramp installation depths. Not likely to significantly impact construction operations as location has mild winters.
Project Scope:
The Lake Mead, Echo Bay Boat Launch Ramp Extension project includes construction of a gravel roadway as well as in-water construction of a launch ramp. The ramp will extend to a depth of 1000' AMSL. The ramp will be constructed of precast concrete panels in 7' vertical sections. The ramp will be constructed in water and to depths of up to 40-feet to finish grade. Construction will require excavation and disposal of approximately 2-feet of soft lakebed sediment. Note that the use of coffer dams and blasting are not allowed methods of construction.
LAKE 332529 EXTEND PUBLIC LAUNCH RAMP AT HEMENWAY HARBOR:
· The project is located at Lake Mead National Recreation Area, Boulder City, Nevada
· The construction magnitude is $10,000,000.
· The surrounding area is rural with limited staging located at Hemenway Harbor.
· No unique material delivery requirements.
· The construction site is 6 miles to Boulder City, NV and 16 miles to Las Vegas, NV of miles from nearest suppliers and lodging facilities.
· The Park will remain open during construction, thus contract activities and logistics must be structured and scheduled to minimize visitor impact. Construction of boat ramps will require phasing to allow for approximately half of the width of the ramp (min 30 ft) to remain open to the public during construction.
· The site requires protective measures to ensure the surrounding area remains undisturbed. Typical best management practices (BMP) will be required to contain the limits of disturbance.
· The structure is a not a historic/natural/cultural resource.
· The anticipated period of performance of 730 calendar days including any potential weather shutdown.
· There are seasonal/other shutdowns mandated through the construction season. Only if Razorback Sucker spawning is discovered, then Dec 1st to May 1st restriction for water based construction. Not currently anticipated for these locations. Contractor may want to schedule work based on anticipated seasonal lake level fluctuations with lake levels lowest June to Nov every year.
· Winter construction may be required. If it makes sense for the contractor based on lake levels. More likely in first season with shallow ramp installation depths. Not likely to significantly impact construction operations as location has mild winters.
Project Scope:
The Lake Mead, Hemenway Harbor Boat Launch Ramp Extension project includes in-water construction of approximately 1,100-LF of launch ramp. The ramp will be 100-ft wide and constructed at a 5% slope utilizing a series of mechanically connected 20-ft x 3-ft precast reinforced concrete panels. The ramp will be constructed in water and to depths of up to 40-feet to finish grade. Construction will require excavation and disposal of approximately 2-feet of soft lakebed sediment. The ramp will be required to remain partially active for public use during construction.
Submittal Contents: Interested (small and large) businesses should submit the following information:
| (1) | Company name, DUNS number, address, point of contact, telephone number, and email address. |
| (2) | Business type: Classification as a Large or Small Business under the above listed NAICS, Small Business Administration (SBA) certified Historically Underutilized Business Zone (HUBZone), Veteran-Owned Small Businesses (VOSB), Service-Disabled Veteran-Owned Small Businesses (SDVOSB), SBA certified Woman Owned Small Business (WOSB), Economically Disadvantaged Woman Owned Small Business (EDWOSB). The size of a small business firm includes all parents, subsidiaries, affiliates, etc.—see 13 CFR 121.108.) Misrepresentation of size status can result in penalties. |
| (3) | Statement regarding your company’s bonding capacity. Letters from bonding companies are not required at this time. |
(4) Information demonstrating experience and capability on projects of same or similar size, scope and magnitude, and constructed under similar conditions. Please provide your experience with similar in-water construction?
(5) In addition businesses may submit existing marketing materials such as capability statements and brochures.
(6) Would you be interested in all three (3) projects? If not, which one(s)?
Submittal Due Date/Time:10:00 AM, Monday, June 17, 2024