A06_SPECIFICATIONS_LAMB_HOUSE_DEMO.pdf

PDF 695 KB Posted

Attached to
GAOA TRFO LAMB HOUSE DEMOLITION AND STABILIZATION
Solicitation number
140L1725R0014
Issued by

About this file

This is a detailed specification document for the Lamb House Demolition and Stabilization project, issued by the Bureau of Land Management's Tres Rios Field Office in Colorado for a 2025 project. The project involves comprehensive demolition and reconstruction of two historic stone buildings, including removing all building additions, reconstructing roofs, providing electrical service, and creating infrastructure such as a parking lot and access trail.

Key work elements include: demolishing building additions while protecting original stone walls, removing hazardous materials like asbestos, reconstructing roofs with synthetic shake shingles, installing a ductless mini-split air conditioner, providing electrical service to the south building, installing new doors and windows, creating a buck and pole fence, constructing a parking lot and access trail, and performing extensive earthwork. The project requires careful preservation of historic architectural elements, with specific requirements for material selection, installation techniques, and site restoration. The total project duration is set at 180 days from the Notice to Proceed, with work limited to Monday-Friday, excluding federal holidays and specific blackout periods.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior Bureau of Land Management

Tres Rios Field Office Colorado

Lamb House Demolition and Stabilization

SPECIFICATIONS

LAMB HOUSE - DEMOLITION AND STABILIZATION

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 SUMMARY OF WORK

01 20 00 PRICE AND PAYMENT PROCEDURES

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 15 TRAFFIC CONTROL AND PUBLIC SAFETY

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 20 00 SURVEY AND PROJECT STAKEOUT

02 41 10 DEMOLITION

02 82 10 ASBESTOS REMOVAL AND DISPOSAL

02 84 50 HAZARDOUS MATERIAL REMOVAL

DI VI SI ON 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON

07 30 00 ROOF RECONSTRUCTION

07 31 00 SYNTHETIC SHAKE SHINGLES AND SIDING

DI VI SI ON 08 - OPENI NGS

08 50 00 DOORS, WINDOWS, WEATHERPROOFING

DI VI SI ON 09 - FI NI SHES

09 90 10 PAINTING

DI VI SI ON 12 - FURNI SHI NGS

12 93 00 CONCRETE PARKING STOPS

DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)

23 81 10 DUCTLESS MINI SPLIT AIR CONDITIONER

DI VI SI ON 26 - ELECTRI CAL

26 10 00 ELECTRICAL SERVICE

26 20 00 ELECTRICAL DISTRIBUTION

DI VI SI ON 31 - EARTHWORK

31 00 00 EARTHWORK

31 11 00 CLEARING AND GRUBBING

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 31 50 BUCK AND POLE FENCE

DI VI SI ON 33 - UTI LI TI ES

33 40 00 STORM DRAINAGE UTILITIES

PROJECT TABLE OF CONTENTS Page 1

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 2

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 PROJECT DESCRIPTION

The work includes, but is not limited to; Demolish all additions to the two original stone buildings. Reconstruct the roofs over the original stone buildings. Provide electrical service to the south stone building.

Construct a parking lot and an access trail.

1.2 LOCATION

The project is located at:

12761 County Road G Cortez, CO 81321.

Note: Google Maps has the work location address: 12921 County Road G

1.3 WORK SCHEDULE

Work shall occur Monday - Friday. Work shall not occur on Federal Holidays, December 26-31, and the day after Thanksgiving. Work shall be completed within 180 days of the Notice to Proceed.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

SECTION 01 32 01

PROJECT SCHEDULE

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Initial Project Schedule ; G

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, and pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required.

3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.2.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones, work listed in the bid schedule, and to allow for satisfactory project planning and execution.

3.2.2 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of submittals.

b. Long procurement activities.

c. Contractor's pre-final inspection.

d. Government's pre-final inspection.

e. Final inspection.

SECTION 01 32 01 Page 9

3.2.3 Government Activities

Include Government activities that could impact progress. These activities include, but are not limited to: Government inspections of work, Government approval of submittals.

3.3 WEEKLY PROGRESS MEETINGS

Conduct a weekly meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities.

3.4 FAILURE TO ACHIEVE PROGRESS

Should the progress fall behind the approved project schedule, the Contracting Officer may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.

3.4.1 Failure to Perform

Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the Contracting Officer pursuant to FAR 52.236-15 Schedules for Construction Contracts, FAR 52.249-10 Default (Fixed-Price Construction), and other contract provisions.

3.4.2 Recovery Schedule

Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.

SECTION 01 32 01 Page 10

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only.

1.2 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer's Representative is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract.

This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government.

1.3 GOVERNMENT APPROVING AUTHORITY

The Contracting Officer's Representative will:

a. Note the date on which the submittal was received.

b. Review submittals for approval within 10 days of receipt.

c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.

Upon completion of review of submittals requiring Government approval, one copy of the submittal will be retained by the Contracting Officer's Representative and one copy of the submittal will be returned to the Contractor.

1.3.1 Review Notations

Submittals will be returned to the Contractor with the following notations:

a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.

b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided the Contractor takes no exception to the corrections.

c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until

SECTION 01 33 00 Page 11 resubmittal is approved.

d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.

e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.

1.4 DISAPPROVED SUBMITTALS

Make corrections required by the Contracting Officer's Representative. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting Officer.

If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.5 APPROVED SUBMITTALS

The Contracting Officer's approval of submittals is not to be construed as a complete check.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 33 00 Page 12

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 2 PAGES

01 32 01 SD-01 Preconstruction Submittals

GInitial Project Schedule

02 41 10 SD-01 Preconstruction Submittals

1.2Colorado Department Of Public

Health And Environment (Cdphe)

Demolition Permit

3.1 GDemolition Plan

02 82 10 SD-01 Preconstruction Submittals

3.1Asbestos Removal Work Plan

03 30 00 SD-03 Product Data

2.2 GStructural Macro Synthetic

Reinforcing Fibers

3.3 GColor Sample

07 30 00 SD-03 Product Data

2.2 GSnow Guards

07 31 00 SD-03 Product Data

2.2 GRoofing Underlayment

2.4 GSynthetic Shake Siding

2.3 GRoof Synthetic Shake Shingles

2.1 GWaterproof Sheet Membrane

08 50 00 SD-03 Product Data

2.1 GDoors

2.2 GWindows

12 93 00 SD-03 Product Data

2.1 GConcrete Parking Stops

23 81 10 SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 2 PAGES

23 81 10 2.1 GDuctless Mini Split Air

Conditioner

2.2 GCondensate Pump

SD-08 Manufacturer’s Instructions

3.1Installation Instructions

26 20 00 SD-03 Product Data

2.2 GElectric Distribution Panel

31 00 00 SD-03 Product Data

2.2 GTrail Surface Aggregate

2.3 GAggregate Base Course

SD-07 Certificates

3.16Weight Tickets

33 40 00 SD-03 Product Data

2.1 GCorrugated Steel Pipe

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SECTION 01 35 15

TRAFFIC CONTROL AND PUBLIC SAFETY

PART 1 GENERAL

1.1 SECTION SUMMARY

Contractor is responsible for work site safety at all times.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 SAFETY

Contractor shall take precautions, as necessary, to protect the public and employees from construction hazards.

3.2 TRAFFIC CONTROL

Contractor shall provide traffic control measures, as necessary, for traffic, trucks, equipment, dumpsters or other potential hazards entering and leaving the work site.

SECTION 01 35 15 Page 13

SECTION 02 20 00

SURVEY AND PROJECT STAKEOUT

PART 1 GENERAL

1.1 SECTION SUMMARY

Not Used.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 PROJECT STAKEOUT

The BLM will stake out the centerline of the access trail and the parking lot stakeout points, as detailed on the plans, one time. The contractor is responsible for all other surveying. The contractor is responsible for re-staking, if necessary, for any reason.

SECTION 02 20 00 Page 14

SECTION 02 41 10

DEMOLITION

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

Demolish all additions to the (2) two stone buildings. There may be loose items inside the building, those loose items will be part of the demolition. Conditions existing at time of the pre-bid site visit inspection will be maintained by the Government.

1.2 COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT (CDPHE)

DEMOLITION PERMIT

Obtain a Colorado Department of Public Health and Environment (CDPHE) Demolition permit prior to beginning work. Submit a copy the approved permit to the Contracting Officer's Representative before beginning demolition work.

1.3 HAZARDOUS MATERIALS

All hazardous materials must be properly removed prior to demolition.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Colorado Department Of Public Health And Environment (Cdphe) Demolition Permit

Demolition Plan ; G

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 DEMOLITION PLAN

Submit a demolition plan that details the how the work will be accomplished. The plan shall include: Sequence of work, protection measures of structures to remain, removal of hazardous materials.

3.2 PROTECTION OF STRUCTURES TO REMAIN

Demolition shall not damage the buildings, or structures, that shall remain.

SECTION 02 41 10 Page 15

3.3 ROOF FINIALS - SALVAGE

Salvage the roof finials and reinstall in accordance with 07 30 00 ROOF

RECONSTRUCTION.

3.4 ANTIQUE STOVE - SALVAGE

Salvage the antique stove. Relocate the stove inside the south stone building, next to the fireplace.

3.5 UTILITIES - PROPANE

Demolish the propane tank and all distribution lines from the tank to the building. The propane tank contains propane. The propane shall be properly removed prior to demolition. Propane shall not be released from the tank into the air.

3.6 UTILITIES - ELECTRIC

Disconnect the electric service to the building, shed, and well house at the meter located on the electric pole. Remove the service wires (service drop) from the pole to the buildings, shed, and well house.

3.7 SEPTIC TANK

Demolish the septic tank. Demolish the sewer line from the buildings to the septic tank. Remove all waste inside the septic tank prior to demolition. Dispose of waste in accordance with federal, state, and local requirements. Backfill with satisfactory soil materials in accordance with section 31 00 00 .

3.8 BUILDING ADDITIONS

Demolish all additions to the (2) two stone buildings. Including walls, roofs, and foundations. Foundations shall be demolished to a depth of 48 inches below grade.

3.9 BELOW GRADE DEMOLITION

Remove below-grade construction a minimum 48 inches below grade. Below grade construction includes; concrete slabs, foundation walls, footings, sewer lines, gas lines, water lines, electric lines and other additions that were not part of the original stone buildings.

Completely fill below-grade areas and voids resulting from demolition operations with satisfactory soil materials in accordance with section 31 00 00 .

3.10 STONE WALL - CONTEMPORARY ADDITION DEMOLITION AND PROTECTION

Demolish all additions to the interior and exterior original stone walls.

Additions include, but are not limited to; drywall, furring strips, ledger boards, heating, ventilation, and air conditioning (HVAC), gas piping, electric wiring and conduit, lights, cabinets, plumbing, door frames, window sills, caulking, flashing, bolts, screws, and other fastening hardware.

Protect all stone walls from damage during demolition.

SECTION 02 41 10 Page 16

3.11 STONE WALL - PLASTER REMOVAL

Removal of plaster applied directly to stone walls is not required. For each wall where plaster is applied directly to the stone wall, remove a six inch diameter section of the plaster to expose the stone underneath.

Take care not to damage the stone wall when removing plaster. Removal of electrical conduit and outlets that are embedded in the plaster is not required.

3.12 STONE BUILDING CEILINGS, FLOOR AND ROOF STRUCTURAL MEMBERS

Demolish ceilings in the stone buildings. Completely expose the floor joists, roof rafters, roof ridge beam, and other structural members.

3.13 DOORS

Demolish all additions to the stone openings at the doors, including but not limited to; doors, door frames, door sills, door jambs, and thresholds.

3.14 WINDOWS

Demolish all additions to the stone openings at the windows, including but not limited to; windows, window frames, and window sills.

3.15 CISTERN

Protect cistern from damage during demolition. Completely fill the cistern in accordance with section 31 00 00 . Leave the stone block covering the cistern in place, undisturbed.

3.16 DEMOLISHED MATERIALS DISPOSAL

All materials designated to be demolished shall become the property of the Contractor and removed from Government property. Dispose of demolition materials in accordance with all applicable federal, state, and local regulations. The Contractor may salvage any of the demolished materials and items.

SECTION 02 41 10 Page 17

SECTION 02 82 10

ASBESTOS REMOVAL AND DISPOSAL

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

Asbestos is present at the work site. The asbestos shall be removed and disposed in accordance with all Federal, State, and Local requirements.

1.2 CRITERIA FOR BIDDING

The BLM has an asbestos survey and inspection report for the work site, from February 2016. Contractor shall assume that no additional asbestos will be found that was not already identified in the existing asbestos survey and inspection report. If additional asbestos is found in the work, then an equitable adjustment for the removal will be made.

Work that occurred in the project since the 2016 asbestos survey includes;

re-roofing over the east building addition, demolition inside the bathroom located closest to the cistern, electrical panel box installation, and sump pump installation.

1.3 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926.1101 Asbestos

40 CFR 61-SUBPART M National Emission Standard for Asbestos

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Asbestos Removal Work Plan

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 ASBESTOS REMOVAL AND DISPOSAL

Perform all work in accordance 40 CFR 61-SUBPART M and 29 CFR 1926.1101 .

Asbestos must be removed by an asbestos removal contractor, certified by the State of Colorado. Submit an asbestos removal work plan that details

SECTION 02 82 10 Page 18 the removal and required safety precautions. Include in the work plan the certification(s) of the person(s) creating the work plan and of the person(s) performing the removal.

SECTION 02 82 10 Page 19

SECTION 02 84 50

HAZARDOUS MATERIAL REMOVAL

PART 1 GENERAL

1.1 DESCRIPTION OF WORK

All hazardous materials must be properly removed prior to demolition.

Hazardous materials include, but are not limited to: asbestos, ozone depleting controlled substances (refrigerants), Polychlorinated Biphenyls (fluorescent light ballasts).

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 ASBESTOS

See section 02 82 10 for asbestos removal requirements.

3.2 LEAD PAINT

Lead paint is present in the work site. The BLM has a lead paint survey from 2016. This project does not require lead paint to be remediated.

However, the Contractor shall follow any Federal, State, or Local requirements for handling and proper disposal of the materials covered with lead paint.

3.3 OTHER HAZARDOUS MATERIALS

The BLM is not aware of any other hazardous materials. The Contractor shall notify the BLM if any other hazardous materials, requiring special disposal are encountered prior to demolition.

SECTION 02 84 50 Page 20

SECTION 03 30 00

CAST-IN-PLACE CONCRETE

PART 1 GENERAL

1.1 SECTION SUMMARY

Patch concrete slab, as necessary for providing electrical service.

1.2 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN CONCRETE INSTITUTE (ACI)

ACI 305.1 (2014) Specification for Hot Weather Concreting

ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting

ASTM INTERNATIONAL (ASTM)

ASTM C387/C387M (2017) Standard Specification for Packaged, Dry, Combined Materials for Concrete and High Strength Mortar

NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA)

NRMCA QC 3 (2015) Quality Control Manual: Section 3, Plant Certifications Checklist:

Certification of Ready Mixed Concrete Production Facilities

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Structural Macro Synthetic Reinforcing Fibers ; G

Color Sample ; G

PART 2 PRODUCTS

2.1 CONCRETE

Provide concrete composed of portland cement, aggregates, water, and admixtures as specified.

SECTION 03 30 00 Page 21

2.1.1 STRENGTH

Compressive strength (f'c) shall be 3500 psi at 28 days.

2.1.2 Air Entrainment

Attain air content at point of placement between 4 and 6 percent.

2.1.3 SLUMP

Slump of the concrete, at the point of placement, shall be 4 inches or less.

2.1.4 PORTLAND CEMENT

ASTM C150/C150M, Type II.

2.2 STRUCTURAL MACRO SYNTHETIC REINFORCING FIBERS

Structural macro synthetic reinforcing fibers shall be Sika Fibermesh 650, or approved equal. Structural macro synthetic reinforcing fibers shall have a diameter greater than 0.3 mm and a length between 1 inch and 3 inches.

2.3 PREPACKAGED CONCRETE MIXTURE

Prepackaged concrete mix shall be identified as conforming to

ASTM C387/C387M

2.4 READY MIXTURE

Ready-mix plant equipment and facilities must be certified in accordance with NRMCA QC 3.

2.5 COLOR

Match existing slab color.

PART 3 EXECUTION

3.1 CONCRETE PATCH

Concrete patch dimensions (thickness and footings) shall match existing dimensions.

3.2 STRUCTURAL MACRO SYNTHETIC REINFORCING FIBERS

Provide 4 pounds of reinforcing fibers per cubic yard of concrete.

Incorporate into concrete mix as recommended by the manufacturer.

3.3 COLOR SAMPLE

Provide a sample of cured, colored concrete prior to placing concrete.

3.4 PREPACKAGED CONCRETE MIXTURE

Use the minimum amount of water to make the mixture. Adding too much water to the mixture will greatly reduce the overall compressive strength. Average slump shall be between 2" to 4".

SECTION 03 30 00 Page 22

3.5 CONCRETE CONSOLIDATION

Concrete shall be adequately vibrated, rodded, or spaded into place to fill voids.

3.6 COLD WEATHER REQUIREMENTS

Perform cold weather concreting in accordance with ACI 306.1 . Use special protection measures if freezing temperatures are anticipated before the expiration of the specified curing period. The ambient temperature of the air where concrete is to be placed and the temperature of surfaces to receive concrete must be not less than 40 degrees F. The temperature of the concrete when placed must be not less than 50 degrees F nor more than 75 degrees F. Heat the mixing water or aggregates to regulate the concrete placing temperature. Materials entering the mixer must be free from ice, snow, or frozen lumps. Do not incorporate salt, chemicals or other materials in the concrete to prevent freezing.

3.7 HOT WEATHER REQUIREMENTS

When job-site conditions are present or anticipated that accelerate the rate of moisture loss or rate of cement hydration of freshly mixed concrete, including an ambient temperature of 80 degrees F or higher, and an evaporation rate that exceeds 0.2 lb/ft2/h, conform concrete work to all requirements of ACI 305.1 .

SECTION 03 30 00 Page 23

SECTION 07 30 00

ROOF RECONSTRUCTION

PART 1 GENERAL

1.1 SECTION SUMMARY

Reconstruct the roofs over the two stone buildings.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Snow Guards ; G

1.3 CRITERIA FOR BIDDING

The condition of the portions of the roof to remain is unknown. The contractor shall assume that up to 10% of the roofs structural members and up to 10% of the roofs non-structural members that are designated to remain shall be replaced or repaired. More than 10% replacement or repair will be a contract modification or equitable adjustment.

Structural members include the roof rafters, ridge beam, sheathing or wood planks or boards on top of the rafters, dormer framing.

Non-structural members include soffit, fascia, trim, and dormer cladding.

PART 2 PRODUCTS

2.1 FLASHING

26 gage galvanized steel.

2.2 SNOW GUARDS

Rocky Guard RG10, as manufactured by rocky mountain snow guards inc.

https://www.rockymountainsnowguards.com/

PART 3 EXECUTION

3.1 DEMOLITION

Demolish roofing as required by section 02 41 10 DEMOLITION and as shown on the drawings. Protect roofing structural members to remain from damage during demolition. Demolish shingles and roofing underlayment of the portion of the roofs to remain.

3.2 WEATHER PROTECTION

Protect buildings from weather and rain at all times. Do not allow rain or precipitation to enter the buildings.

SECTION 07 30 00 Page 24

3.3 ROOF INSPECTION PREPARATION

Completely expose the roof rafters, ridge beam, and other structural members prior to roof inspection.

3.4 ROOF INSPECTION

The BLM will inspect the roof's structural and non- structural members.

The inspection will be completed by a separate BLM contractor. The inspection is not a requirement of this contract, however, coordination with the BLM's contract inspector is a contract requirement.

Provide 30 days notice of when the roof's structural and non- structural members will be ready for inspection. Allow 14 days in the schedule for the coordination of the inspection.

The roof will be inspected for structural deficiencies, such as cracks, splits, deformation, or weathering. And inspected for Wood Destroying Organisms (insects, fungi, bacteria, algae).

Provide access and fall protection for the BLM's roof inspection contractor.

Work on the roof shall not continue until after the inspection.

3.5 REPLACEMENT AND REPAIR

After completing the roof's structural and non-structural inspection, the Contracting Officer's Representative, will designate portions of the roof to be repaired or replaced.

3.6 ROOF RECONSTRUCTION

Reconstruct the roofs, as necessary, to match the plan and elevation views shown on the drawings. Reconstruct any portions of the roof that were damaged during demolition. Provide flashing, underlayment, and synthetic shake shingles for the roofs.

3.7 SURFACE PREPARATION

Ensure that roof deck is smooth, clean, dry, and without loose knots.

Roof surfaces must be firm and free from loose boards, large cracks, and projecting ends that might damage the roofing. Cover knotholes and cracks with sheet metal nailed securely to sheathing. Chimneys, and other projections through roofs, shall be properly flashed. Projecting nails shall be driven flush with the deck.

3.8 METAL FLASHING

Form in longest possible lengths, 8 feet minimum.

Counterflashings: Extend minimum 4 inches up vertical surfaces and minimum 4 inches under shingles.

Valley flashings: Minimum 24 inches wide, extending minimum 10 inches from valley center line.

Eave flashings: Fabricate with bottom edge formed outward 1/4 inch and hemmed to form drip.

SECTION 07 30 00 Page 25

3.9 METAL DRIP EDGE

Provide a metal drip edge, designed to allow water run-off to drip free of underlying construction, at eaves and gable ends prior to the application of roofing shingles.

3.10 SYNTHETIC SHAKE SHINGLE

Provide in accordance with section 07 31 00 SYNTHETIC SHAKE SHINGLES AND

SIDING.

3.11 ROOF FINIALS

Reinstall salvaged roof finials.

3.12 PAINT

Paint soffit, fascia, trim, and cladding in accordance with section

09 90 10 PAINTING.

SECTION 07 30 00 Page 26

SECTION 07 31 00

SYNTHETIC SHAKE SHINGLES AND SIDING

PART 1 GENERAL

1.1 SECTION SUMMARY

Provide synthetic shake roof shingles and synthetic shake siding.

1.2 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D226/D226M (2017) Standard Specification for Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing

ASTM D1970/D1970M (2019) Standard Specification for Self-Adhering Polymer Modified Bituminous Sheet Materials Used as Steep Roofing Underlayment for Ice Dam Protection

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Roofing Underlayment ; G

Synthetic Shake Siding ; G

Roof Synthetic Shake Shingles ; G

Waterproof Sheet Membrane ; G

PART 2 PRODUCTS

2.1 WATERPROOF SHEET MEMBRANE

Self-adhered, leak barrier underlayment, conforming to ASTM D1970/D1970M .

2.2 ROOFING UNDERLAYMENT

Asphalt-saturated organic felt. Type II (No. 30 felt), in accordance with

ASTM D226/D226M

2.3 ROOF SYNTHETIC SHAKE SHINGLES

Multi-width Shake, as manufactured by:

SECTION 07 31 00 Page 27

DaVinci Roofscapes, LLC, 800-DAVINCI, www.davinciroofscapes.com.

10 inch exposure Color: Aged Cedar

Submit the product and the manufacturer's written installation instructions.

2.4 SYNTHETIC SHAKE SIDING

Multi-width Shake, as manufactured by:

DaVinci Roofscapes, LLC, 800-DAVINCI, www.davinciroofscapes.com.

10 inch exposure Color: Aged Cedar

Submit the product and the manufacturer's written installation instructions.

2.5 OR EQUAL PRODUCTS

The synthetic shake shingles and siding products were chosen specifically for their durability, constructability, and aesthetics. In addition, the product specified has been successfully used by the BLM on previous historic restoration projects. "Or equal" products shall equal the properties listed in part 2 of the manufacturer's specifications.

2.6 FASTENERS

Stainless steel, 3/8 inch flat head nails, 1-1/2 inches (38 mm) long.

PART 3 EXECUTION

3.1 WATERPROOF SHEET MEMBRANE

Provide self-adhered waterproof sheet membrane on eaves, rakes, valleys, and around projections or penetrations. Install and fasten in accordance with the manufacturer's written installation instructions. Waterproof sheet membrane is required in addition to roofing underlayment.

3.2 ROOFING UNDERLAYMENT

In addition to the waterproof sheet membrane, provide asphalt roofing underlayment over full roof area. Install and fasten underlayment as specified or recommended by the manufacturer's written instructions. Lay underlayment parallel to roof eaves, starting at eaves. Provide minimum 4 inch laps. Nail in place with roofing nails spaced in accordance with manufacturer's recommendations.

3.3 SYNTHETIC SHAKE SHINGLE INSTALLATION

Install synthetic shake shingles in accordance with the manufacturer's written installation instructions.

3.4 SYNTHETIC SHAKE SIDING INSTALLATION

Install synthetic shake siding in accordance with the manufacturer's written installation instructions.

Install synthetic shake siding on vertical surfaces of roof dormers.

Remove dormer battens as necessary for installation.

SECTION 07 31 00 Page 28

3.5 METAL FLASHING AND DRIP EDGE

Provide in accordance with section 07 30 00 ROOF RECONSTRUCTION.

3.6 SNOW GUARDS

Provide in accordance with section 07 30 00 ROOF RECONSTRUCTION.

SECTION 07 31 00 Page 29

SECTION 08 50 00

DOORS, WINDOWS, WEATHERPROOFING

PART 1 GENERAL

1.1 SECTION SUMMARY

Replace doors and windows. Make the buildings weather tight.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Doors ; G

Windows ; G

PART 2 PRODUCTS

2.1 DOORS

Solid wood. Six panel.

2.2 WINDOWS

Windows shall be wood, single hung, with grilles. Windows shall consist of complete units including but not limited to; sash, glass, frame, weatherstripping, insect screen, and hardware.

PART 3 EXECUTION

3.1 DEMOLITION

Demolish existing doors and windows as required by section 02 41 10

DEMOLITION.

3.2 WEATHERPROOFING

The buildings shall be maintained weatherproof at all times during the work. After demolition is complete, carefully inspect the building for openings. Permanently cover over all openings to provide a weather tight building envelope.

3.3 STONE OPENINGS

Exterior openings in the stone shall be permanently covered in a manor that is weather tight, blends well with the existing stonework, and that can be removed for stone restoration in the future.

SECTION 08 50 00 Page 30

3.4 DOORS

Stone openings are irregular sizes. Provide structural framing, as necessary, for the installation of the largest standard size door that will fit the opening. Provide door frames, door sills, door jambs, and thresholds. Provide door hardware and hinges. All doors locksets shall operate with the same key. Hang doors. Provide weatherstripping for a weathertight installation.

3.5 WINDOWS

Stone openings are irregular sizes. Provide framing, sills, and jambs, as necessary for proper installation of the window. Install windows.

Provide a weather tight installation.

3.6 PAINT

Paint door framing and window framing, interior and exterior, in accordance with section 09 90 10 .

3.7 FINISH

Finish the wood doors in accordance with section 09 90 10 PAINTING.

SECTION 08 50 00 Page 31

SECTION 09 90 10

PAINTING

PART 1 GENERAL

1.1 SECTION SUMMARY

Paint soffit, fascia, trim, and cladding. Paint framing around doors and windows. Paint windowsills. Finish doors.

1.2 COLOR SELECTION

Paint color will be provided after award.

PART 2 PRODUCTS

2.1 PRIMER

Sherwin-Williams; Exterior latex wood primer.

2.2 PAINT

Sherwin-Williams; Emerald urethane trim enamel.

Paint sheen; Satin.

2.3 FINISH

Spar Urethane.

PART 3 EXECUTION

3.1 PROTECTION OF AREAS NOT TO BE PAINTED

Mask, or otherwise protect stone and other items not to be coated.

Restore surfaces contaminated by coating materials to original condition.

3.2 SURFACE PREPARATION

Remove blistering, cracking, flaking, peeling or otherwise deteriorated coatings. Repair damaged areas such as, but not limited to, nail holes, cracks, chips, and spalls with suitable material to match adjacent undamaged areas. Feather and sand smooth edges of chipped paint. Remove dirt, loose particles, and other foreign matter and substances deleterious to coating performance of paint.

3.3 APPLICATION

Thoroughly work coating materials into joints, crevices, and open spaces.

Allow time between coats, as recommended by the coating manufacturer, to permit thorough drying. Each coat shall cover surface of preceding coat or surface completely, and there shall be a visually perceptible difference in shades of successive coats. Provide finished surfaces free from runs, drops, ridges, waves, laps, brush marks, and variations in colors.

SECTION 09 90 10 Page 32

3.4 COATS REQUIRED - PAINTED SURFACES

(1) Primer.

(2) Finish coat.

(3) Second finish coat.

3.5 COATS REQUIRED - FINISHED SURFACES (DOORS)

Three coats are required. Sand the door between coats.

SECTION 09 90 10 Page 33

SECTION 12 93 00

CONCRETE PARKING STOPS

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Concrete Parking Stops ; G

PART 2 PRODUCTS

2.1 CONCRETE PARKING STOPS

Parking stops shall be reinforced concrete. With minimum dimensions of;

six foot length, eight inch width, and 5 inch height.

PART 3 EXECUTION

3.1 CONCRETE PARKING STOPS

Each parking stop shall be held in place with two (2) #4 rebars, 24 inches long.

SECTION 12 93 00 Page 34

SECTION 23 81 10

DUCTLESS MINI SPLIT AIR CONDITIONER

PART 1 GENERAL

1.1 SECTION SUMMARY

Provide a ductless mini split air conditioner.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Ductless Mini Split Air Conditioner ; G

Condensate Pump ; G

SD-08 Manufacturer's Instructions

Installation Instructions

PART 2 PRODUCTS

2.1 DUCTLESS MINI SPLIT AIR CONDITIONER

Mitsubishi Electric, 12,000 BTU/H unit.

Floor mount indoor unit model number: MFZ-KJ12NA Outdoor unit model number: MUFZ-KJ12NAHZ

2.2 CONDENSATE PUMP

REFCO, Combi, item number: 3004146.

PART 3 EXECUTION

3.1 INSTALLATION

Install ductless mini split air conditioner and condensate pump in accordance with the manufacturer's written installation instructions .

Provide electrical service as required.

3.2 WALL PENETRATIONS

All wall penetrations shall go through the windowsill. Wall penetrations shall not go through the stone.

3.3 TRAINING

Train BLM personnel on the proper operation and maintenance of the unit.

SECTION 23 81 10 Page 35

SECTION 26 10 00

ELECTRICAL SERVICE

PART 1 GENERAL

1.1 SECTION SUMMARY

Provide electrical service to the south building, first floor.

1.2 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 2023 National Electrical Code

PART 2 PRODUCTS

2.1 CONDUIT ABOVE GRADE

Galvanized rigid steel conduit. Threaded fittings.

2.2 CONDUIT BELOW GRADE

HDPE, Schedule 40.

2.3 SERVICE WIRE

Copper, 4 AWG.

2.4 GROUND ROD

5/8 inch by 8 foot. Copper-bonded steel.

PART 3 EXECUTION

3.1 GENERAL INSTALLATION REQUIREMENTS

Perform all work in accordance with NFPA 70 .

3.2 UTILITY COORDINATION

Contractor shall coordinate all work with the utility company, as required by the utility company.

3.3 EXISTING DISTRIBUTION PANEL (POLE MOUNTED)

Run service through the existing distribution panel, located on the power pole.

3.4 UNDERGROUND CONDUCTORS

Run conductors underground from the existing distribution panel (power

SECTION 26 10 00 Page 36 pole) to the building. Bury conductors a minimum of 18 inches.

3.5 CONDUIT

Underground conduit run shall have as few bends as practical. Underground conduit shall have less than the equivalent of three (3) ninety degree bends.

3.6 WALL PENETRATIONS

All wall penetrations shall go through the windowsill. Wall penetrations shall not go through the stone.

3.7 CONCRETE SLAB

Saw cut existing concrete slab as required for underground installation of electric service. Cut in neat lines. Patch in accordance with section

03 30 00 CAST-IN-PLACE CONCRETE.

3.8 GROUND RODS

Install (2) ground rods, separated 6 feet apart at new service entrance and bonded to new distribution panel ground bar. Ground rods shall be installed to a depth of 8 feet. If rock is encountered, then the contractor may install the ground rods in a trench at least 30 inches deep, and in accordance with NFPA 70 .

SECTION 26 10 00 Page 37

SECTION 26 10 00

ELECTRICAL DISTRIBUTION

PART 1 GENERAL

1.1 SECTION SUMMARY

Provide electricity inside the south building, first floor.

1.2 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020; TIA

20-1; TIA 20-2; TIA 20-3; TIA 20-4)

National Electrical Code

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Electric Distribution Panel ; G

PART 2 PRODUCTS

2.1 ELECTRICAL METALLIC TUBING (EMT)

Zinc coated steel.

2.2 ELECTRIC DISTRIBUTION PANEL

100 amp, 240 Volt, 12- Space, 24 Circuit, Square D distribution panel.

Home Depot Product:

Internet # 204836339 Model # HOM1224M100PC Store SKU # 1000040029

Panel shall have the following circuits:

Circuit Quantity Ampere Location

1 30 Ductless Mini Split

1 15 Overhead lights

SECTION 26 20 00 Page 38

Circuit Quantity Ampere Location

1 20 Receptacles

2.3 CEILING LIGHTS

Ceiling light similar to "Maxim Lighting's Essentials Collection" Flush mount, 3 bulb, oil rubbed bronze finish. Home Depot product number:

5842MROI

2.4 LIGHT SWITCH

Light switch shall be a timer.

Home Depot Product:

20 Amp 12-Hour Spring Wound In-Wall Timer, White Internet # 205478810 Model # SW12HWK Store SKU # 1000632791

PART 3 EXECUTION

3.1 GENERAL INSTALLATION REQUIREMENTS

Perform all work in accordance with NFPA 70 .

3.2 ELECTRIC DISTRIBUTION PANEL

Securely mount distribution panel to the wall in accordance with manufacturer's recommendations.

3.3 WALL PENETRATIONS

All wall penetrations shall go through the windowsill. Wall penetrations shall not go through the stone.

3.4 GROUNDING

Ground distribution panel, EMT, and ductless mini splt, in accordance with

NFPA 70 .

3.5 CONDUIT

Run conduit horizontal along the existing base board to outlets. Secure conduit to the base board where possible. Minimize the conduit run along the stone (plaster) wall. Run conduit exposed on the ceiling to the ceiling lights.

3.6 RECEPTACLE LOCATION

Mount receptacles on the existing base boards.

3.7 CEILING LIGHTS

Remove existing ceiling lights. Provide two (2) ceiling lights and a wall mounted timer switch.

SECTION 26 20 00 Page 39

SECTION 26 20 00 Page 40

SECTION 31 00 00

EARTHWORK

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Trail Surface Aggregate ; G

Aggregate Base Course ; G

SD-07 Certificates

Weight Tickets

PART 2 PRODUCTS

2.1 IMPORTED FILL MATERIAL

Imported fill material shall be any material classified by ASTM D2487 as

GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, SP, SM, SC, ML, CL, MH.

And comprise stones less than 3 inches in any dimension. Organic soils, and highly plastic, fat clay soils are not acceptable.

2.2 TRAIL SURFACE AGGREGATE

Trail surface aggregate shall be crushed rock or stone and meet the following gradation:

Sieve Size % passing

1/2" 100%

#4 60% - 80%

SECTION 31 00 00 Page 41

Sieve Size % passing

#8 40% - 60%

#200 10%-20%

2.3 AGGREGATE BASE COURSE

Aggregate base course shall meet the requirements of Colorado Department of Transportation Standard Specifications for Road and Bridge Construction 2023, section 703 AGGREGATES. Aggregate base course gradation shall meet the gradation shown in Table 703-2, Class 6.

2.4 GEOTEXTILE LANDSCAPE FABRIC

Geotextile landscape fabric specifically designed to prevent vegetation from growing through the fabric, while allowing water to pass through.

PART 3 EXECUTION

3.1 UNDERGROUND UTILITIES

The Contractor is responsible for locating underground utilities prior to demolition. Contractor shall relocate, or re-bury, the underground communications line, as required, for the roadside rock excavation.

3.2 GENERAL EXCAVATION

Perform excavation of every type of material encountered to the lines, grades, and elevations indicated and as specified. Perform excavation and fill in a manner and sequence that will provide proper drainage at all times, including during construction.

3.3 ROCK EXCAVATION

Solid rock is present and shall be excavated as required.

Rock Excavation - Location Quantity (Cubic Yards)

East Trail Section 90

West Trail Section 65

Middle Trail Section 8

Parking Lot 3

SECTION 31 00 00 Page 42

3.4 ACCESS TRAIL MATERIAL QUANTITIES - STATION 0+00 TO 2+20

Cubic Yards

Cut 90

Fill 80

3.5 IMPORTED FILL MATERIAL QUANTITIES

Imported Fill Location Quantity (Cubic Yards)

Demolished Building Footprint and Foundation 20

Septic Tank 5

Cistern 10

Culvert 15

3.6 GROUND SURFACE PREPARATION

Clear and grub in accordance with section 31 11 00 . Do not perform construction when surfaces are frozen or muddy. Prepare the subgrade to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Shape subgrade to drain.

3.7 AGGREGATE PLACEMENT LOCATIONS (PARKING LOT, ACCESS TRAIL, AROUND

BUILDING)

Subparagraphs apply to the parking lot, access trail, and aggregate placement locations around the buildings.

3.7.1 SUBGRADE

Prepare the subgrade to the lines and grades shown on the plans.

3.7.2 SUBGRADE - COMPACTION

Moisten material as necessary to achieve compaction. Compact the subgrade by operating vibratory compaction equipment over the full width. Continue compaction until a firm surface is achieved, without any soft areas, and a minimum of 3 passes over the entire width.

3.7.3 AGGREGATE PLACEMENT

Contractor shall receive approval of the subgrade prior to placing aggregate base course. Place base course aggregate to the lines and grades shown on the plans.

3.7.4 AGGREGATE BASE COURSE - COMPACTION

Moisten material as necessary to achieve compaction. Compact the base course aggregate by operating vibratory compaction equipment over the full width. Continue compaction until a firm surface is achieved, without any soft areas, and a minimum of 3 passes over the entire width.

SECTION 31 00 00 Page 43

3.8 ACCESS TRAIL CONSTRUCTION

Provide vibratory plate compactor, or other approved methods, to compact the trail subgrade and aggregate in accordance with paragraph 3.7 AGGREGATE PLACEMENT LOCATIONS and subparagraphs.

3.9 ACCESS TRAIL STONE EDGING

Provide stone edging along the access trail. Contractor may utilize the rock excavated for the access trail to construct the trail stone edging.

Work, shape, split, and hew rock as necessary to create stone edging.

Stones shall fit together snugly, such that the stones contain the trail surface aggregate.

3.10 DEMOLITION FILL

Completely fill the voids created after demolition of building additions, foundations, and underground utilities. Fill the voids in complete layers not exceeding 18 inches thickness.

3.11 CISTERN FILL

Completely fill the cistern. Fill the cistern in complete layers not exceeding 18 inches thickness. Fill the cistern with imported fill material. The top 12 inches of cistern fill shall be trail surface aggregate. Leave the stone block covering the cistern in place, undisturbed.

3.12 SEPTIC TANK FILL

Completely fill the void created after demolition of septic tank. Fill the void in complete layers not exceeding 18 inches thickness.

3.13 GRADING - DEMOLITION SITES

The Contractor shall grade the area of demolished construction to a smooth surface, free from irregular surface changes. Import fill material, as necessary, to provide a smooth transition between the stone buildings and adjacent existing grades. Provide positive drainage away from stone buildings.

3.14 DEMOLISHED BUILDING LOCATIONS - TRAIL SURFACE AGGREGATE - GEOTEXTILE

Place trail surface aggregate in the location of the demolished building additions, as shown on the drawings. Place geotextile landscape fabric under the trail surface aggregate. Compact aggregate as required by paragraph 3.7 AGGREGATE PLACEMENT LOCATIONS.

3.15 FINISHING

Finish the surfaces to a smooth and compact surface in accordance with the lines, grades, and cross sections or elevations shown. Provide the degree of finish for graded areas within 0.2 foot of the grades and elevations indicated. Finish surfaces in a manner that will result in effective drainage, regardless of tolerance. Finish slopes shall generally match the slopes shown and never exceed the slopes shown.

SECTION 31 00 00 Page 44

3.16 WEIGHT TICKETS

Submit weight tickets for aggregate base couse and trail surface aggregate. Weight tickets are required prior to payment.

SECTION 31 00 00 Page 45

SECTION 31 11 00

CLEARING AND GRUBBING

PART 1 GENERAL

Not Used.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

3.1 CLEARING AND GRUBBING LIMITS

Clearing and grubbing limits shall be within the fence, access trail, and parking lot. Remove the tree next to the south building as shown on the drawings.

3.2 PROTECTION

Protect trees and vegetation from damage incident to clearing, grubbing, and construction operations.

3.3 CLEARING

Clearing shall consist of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared. Trees, stumps, roots, brush, and other vegetation in areas to be cleared shall be cut off flush with or below the original ground surface.

3.4 GRUBBING

Grubbing consists of the removal and disposal of stumps, roots larger than 3 inches in diameter, and matted roots from the designated grubbing areas.

Remove material to be grubbed, together with logs and other organic or metallic debris not suitable for foundation purposes, to a depth of not less than 12 inches below the original surface level of the ground in the area of new road construction. Fill depressions made by grubbing with suitable material and compact to make the surface conform with the original adjacent surface of the ground.

3.5 DISPOSAL OF CLEARING AND GRUBBING VEGETATION

Dispose of clearing and grubbing material in the material disposal location designated on the plans. Logs, stumps, roots, brush, rotten wood, and other organic material resulting from the clearing and grubbing operations, shall be uniformly scattered on site in piles less than 18 inches off the ground. Process, mulch, cut, or limb material as necessary to comply with disposal pile requirements.

The tree next to the Lamb House is demolished material and shall be removed in accordance with section 02 41 10 DEMOLITION.

SECTION 31 11 00 Page 46

SECTION 31 11 00 Page 47

SECTION 32 31 50

BUCK AND POLE FENCE

PART 1 GENERAL

1.1 SECTION SUMMARY

Provide buck and pole fence.

PART 2 PRODUCTS

2.1 WOOD BUCK POSTS

Minimum 5 inch diameter. Clean-peeled wood poles with inner bark removed and with knots and limbs cut flush with the surface. Posts shall be of tamarack, black or honey locust, ponderosa or lodgepole pine, juniper, osage orange or white oak.

2.2 WOOD POLES

Minimum 3 inch diameter. Clean-peeled wood poles with inner bark removed and with knots and limbs cut flush with…

This is the start of the file's text. The full file is on GovTribe.