A06_Hanalei_Valley_Viewpoint_Final_Specifications_0618_2021.pdf
PDF 4 MB Posted
- Solicitation number
- 140P2021R0114
About this file
This document outlines specifications for a federal construction contract opportunity with the National Park Service to develop a viewpoint site for the U.S. Fish and Wildlife Service Hanalei National Wildlife Refuge in Hanalei, Hawaii. The project involves roadway improvements within the state highway right-of-way, including acceleration and deceleration lanes as well as a site access driveway. Additional site work includes developing two viewpoints, a parking area, concrete and stone walls, fencing, sidewalks, an interpretive kiosk, vault toilet, landscaping, and an entrance sign. Construction must follow state and federal requirements and obtain necessary permits from the Hawaii Department of Transportation and other agencies. The contractor will be responsible for safety plans and procedures, waste management, erosion control, and maintaining access during the project duration, which is estimated to be completed within 150 days of the notice to proceed.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Fish and Wildlife Service
Hanalei Valley Viewpoint June 2021
Specifications
Task Order Number 140P2021F0069 NPS IDIQ Contract Number 140P2021D0006 Design Services for Design Development and Construction Documents
USFWS Hanalei Valley Viewpoint TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 35 23 Safety Requirements 01 40 00 Quality Requirements and CQC Form 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 56 39 Temporary Tree and Plant Protection 01 57 19.12 Noise & Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data
DIVISION 02 – EXISTING CONDITIONS
02 41 19 Selective Demolition
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete
DIVISION 05 – METALS
05 50 00 Metal Fabrications
DIVISION 09 – FINISHES
09 91 13 Exterior Painting
DIVISION 10 – SPECIALTIES
10 14 23 Signage
DIVISION 12 – FURNISHINGS
12 93 00 Site Furnishings
USFWS Hanalei Valley Viewpoint TOC-2
DIVISION 13 – SPECIAL CONSTRUCTION
13 34 23 Pre-engineered Restroom Building
DIVISION 31 – EARTHWORK
31 10 00 Site Clearing 31 20 00 Earth Moving
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 33 Landscape Establishment 32 12 16 Asphalt Paving 32 13 13 Concrete Paving 32 17 23 Pavement Markings 32 31 00 Architectural and Field Fencing 32 93 00 Exterior Plants
DIVISION 33 – UTILITIES
33 05 00 Common Work Results for Utilities 33 41 00 Storm Utility Drainage Piping
USFWS Hanalei Valley Viewpoint 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Contractor Use of Site
3. Public Use of Site
4. Conduct of Operations
5. Work Restrictions
6. Special Construction Requirements
7. Soils Investigation Report
8. Additional Reports
B. Related Requirements:
1. Section 015639 "Temporary Tree and Plant Protection" for preservation of natural features and tree protection.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: U.S. Fish and Wildlife Service (USFWS) Hanalei Valley Viewpoint, Kauai Highway, Kauai County, Hawaii.
B. The Work consists of:
1. Highway adding acceleration/deceleration lanes and site access driveway within the right of way of Kuhio Highway, Hawaii Department of Transportation (HDOT) including but not limited to grading, drainage, pavement, signage and pavement markings.
2. Viewpoints, parking and site amenities within the site property boundary including but not limited to grading, drainage, parking lot pavement, concrete and stone veneer retaining walls, privacy walls, fences, sidewalks, interpretive signage, vault toilet, planting, automated gate, and entrance sign.
C. Project will be constructed under a single prime contract.
D. USFWS is the project owner. The National Parks Service will provide project management and development services on behalf of USFWS.
1.3 ORDER OF OPERATIONS
A. Order of Operations: The Contractor will prioritize the construction of site security improvements, including the installation of perimeter fencing, gated access, and the privacy
USFWS Hanalei Valley Viewpoint 01 11 00 - 2 wall, berm, and associated adjacent work. See Section 01 32 16 for construction milestones.
These improvements must be completed first in order to comply with the purchase agreement for the project site.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Site Access: Construction access is only permitted from the Hawaii Department of Transportation (HDOT). The Government has secured authorization for a new highway access from the department of transportation. No construction access is permitted from adjacent private property without written approval from the Contracting Officer and landowner.
C. Storage of Materials: Confine storage of materials to area shown on plans. Storage of materials within the highway right of way is not allowed without approval from the Contracting Officer and the highway Kauai District Engineer.
D. Parking: Confine parking to area shown on plans. Site access is allowed from Kuhio Highway only, do not trespass on adjacent private property to access site.
E. Stockpiling: Confine stockpiling to area shown on drawing.
F. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
G. Hauling Restrictions: Comply with legal load restrictions in hauling of materials.
1.5 PUBLIC USE OF SITE
A. The highway will be open to the public during construction. The area within the site property boundary will be closed to the public during construction.
1.6 CONDUCT OF OPERATIONS
A. Contractor shall conduct operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable rules and regulations prescribed by the US Fish and Wildlife Service.
USFWS Hanalei Valley Viewpoint 01 11 00 - 3
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 2 business days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.7 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except as approved by the Contracting Officer.
B. To avoid disturbing the ʿōpeʿapeʿa (hoary bat), woody plants greater than 15-feet tall would not be disturbed, removed, or trimmed during the pupping season June 1 through September 15.
C. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility in coordination with the utility cooperator at no expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruption without the utility cooperator and the Contracting Officers written permission.
1.8 REQUIREMENTS
A. Project Website: A project website administered by NPS will be used for purposes of managing communication and documents during construction stage.
1. See Section 01 31 00 "Project Management and Coordination" for requirements on using Project Website.
1.9 SOILS INVESTIGATION REPORT
A. The report Geotechnical Engineering Report dated January 2017, prepared by Masa Fujioka & Associates, is available in with this package.
USFWS Hanalei Valley Viewpoint 01 11 00 - 4
B. In case of conflict between report and drawings or specifications, the drawings and specifications govern. Notify the Government immediately of any conflicts.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
USFWS Hanalei Valley Viewpoint 01 26 01 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
USFWS Hanalei Valley Viewpoint 01 26 01 - 2
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
USFWS Hanalei Valley Viewpoint 01 26 01 - 3
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm
USFWS Hanalei Valley Viewpoint 01 26 01 - 4
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
USFWS Hanalei Valley Viewpoint 01 26 01 - 5
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit…………… …10%
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
USFWS Hanalei Valley Viewpoint 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
USFWS Hanalei Valley Viewpoint 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cutoff points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 01 – Roadway Improvements
1. This item consists of furnishing and installing all roadway systems including, but not limited to contractor mobilization, general conditions, required materials testing, traffic control plan and traffic control measures, erosion and sediment control, construction access, clearing and grubbing, demolition, excavation and embankment, haul off, new and relocated utilities, hydroseeding, striping and signs, and all other work within the right-of-way as shown on the contract documents.
2. Measurement for payment will be per the State of Hawaii Department of Transportation
Standard Specifications and Special Provisions, on percentage of work performed per the schedule of values, with approval of Contracting Officer.
3. Payment will be made at the contract bid price for work completed up to the contract line item lump sum price.
B. Contract Line Item Number 02 – Site Security
1. This item consists of furnishing and installing the permanent site security improvements including, but not limited to berm, planting, privacy wall with cultured stone veneer, perimeter fencing, vehicle gates, and gate control systems within the site.
2. Measurement for payment will be based on the percentage of work performed per the schedule of values, with approval of Contracting Officer.
3. Payment will be made at the contract bid price for work completed up to the contract line item lump sum price.
C. Contract Line Item Number 03 – Site Interpretive and Entry Signs
1. This item consists of furnishing and installing the interpretive and entry signs including, but not limited to, the interpretive kiosk frame and foundation, interpretive sign panels, metal fasteners and mounting hardware, and entry sign and posts within the site.
USFWS Hanalei Valley Viewpoint 01 27 00 - 2
2. Measurement for payment will be based on the percentage of work performed per the schedule of values, with approval of Contracting Officer.
3. Payment will be made based upon the percentage of work completed up to the contract line item lump sum price.
D. Contract Line Item Number 04 – Site Pre-engineered Restroom Building
1. This item consists of furnishing and installing the restroom building including, but not limited to, excavation for the restroom, required materials testing, pre-engineered restroom building delivered to the site, necessary storage tanks, fixtures, furnishings, and equipment, installation and commissioning of the restroom.
2. Measurement for payment will be based on the percentage of work performed per the schedule of values, with approval of Contracting Officer.
3. Payment will be made based upon the percentage of work completed up to the contract line item lump sum price.
E. Contract Line Item Number 05 – Site Improvements
1. This item consists of furnishing and installing site improvements including, but not limited to, contractor mobilization, general conditions, required materials testing, erosion and sediment control, temporary fencing and gates, clearing and grubbing, demolition, excavation and embankment, haul off, utilities, site landscaping, hydroseeding, striping and regulatory signs, pavements, curbs, site furnishings, and all other work within the site as shown on the contract documents.
2. Measurement for payment will be based on the percentage of work performed per the schedule of values, with approval of Contracting Officer.
3. Payment will be made based upon the percentage of work completed up to the contract line item lump sum price.
F. Option A – Seat Wall at Kiosk
1. Contract Line Item Number 06
2. This option consists of furnishing and installing the stone veneered seat wall at the kiosk as shown on the plans and includes all additional work necessary to install Option A.
3. Measurement for payment will be based on the percentage of work performed per the schedule of values, with approval of Contracting Officer.
4. Payment will be made based upon the percentage of work completed up to the contract line item lump sum price.
G. Option B – Stone Veneer at Viewpoints
1. Contract Line Item Number 07
2. This option consists of installing cultured stone veneer at the two viewpoints as shown on the plans and includes all additional work necessary to install Option B
3. Measurement for payment will be based on the percentage of work performed per the schedule of values, with approval of Contracting Officer.
4. Payment will be made based upon the percentage of work completed up to the contract line item lump sum price.
H. Option C – Stone Veneer at Restroom
USFWS Hanalei Valley Viewpoint 01 27 00 - 3
1. Contract Line Item Number 08
2. This option consists of deleting lap siding detail on lower half of restroom and installing site-installed cultured stone veneer cladding stone on the restroom building as shown on the plans. Includes all additional work and manufacturer coordination necessary to install
Option C
3. Measurement for payment will be based on the percentage of work performed per the schedule of values, with approval of Contracting Officer.
4. Payment will be made based upon the percentage of work completed up to the contract line item lump sum price.
END OF SECTION 01 27 00
USFWS Hanalei Valley Viewpoint 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS/DSC Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction
B. Construction Permits – Contractor Provided
C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
USFWS Hanalei Valley Viewpoint 01 31 00 - 2
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Layout and Staking: Contractor to layout and stake proposed viewpoint locations, fencing, walls, trails, and panel signs in the field for review and approval by the Contracting Officer.
C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.4 SUBMITTALS
A. Division 1 documents: The following items shall be submitted a minimum of one week prior to
Preconstruction Conference. Contracting Officer will schedule the Pre-Construction Conference date in coordination with the Contractor.
1. Letter designating Project Superintendent
2. Construction Schedule, draft baseline for project
3. A Comprehensive Schedule of Values for work within state highway right of way
4. A Comprehensive Schedule of Values for work within the project property boundary.
5. Accident Prevention Plan
6. A List of Subcontractors for this project
7. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
8. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
9. Waste Management Plan
10. Quality Control Plan
11. Temporary Storm Water Pollution Prevention Plan (SWPP)
12. Traffic control plan and permit application
13. List of Required Construction Permits. Include the following information for each permit:
USFWS Hanalei Valley Viewpoint 01 31 00 - 3
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
B. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of
Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on
NPS/DSC management software website.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by
Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete RFI Form on NPS/DSC Project Website as follows:
1. Enter general information at the top of the form.
2. Under the "Action" section at the bottom of the form, select "Question" then select
"Contracting Officer/COR" in drop-down of "Send to" box.
3. Enter details of question and attach related documents.
4. Select "Submit Form" at bottom of page.
USFWS Hanalei Valley Viewpoint 01 31 00 - 4
D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Contracting Officer's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or
Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT WEB SITE
A. Use Contracting Officer-designated project management website hosted by others for communication during contract period for the following:
1. Project directory
2. Project correspondence
3. Meeting agendas and minutes
4. Contract modifications forms and logs
5. RFI form and processing
6. Task and issue management
7. Photo documentation
8. Baseline schedule, schedule updates and calendar management
9. Submittal form and processing
10. Payment coordination documentation
11. Drawing and specification document hosting, viewing, and updating
12. Online document collaboration
13. Reminder and tracking functions
14. Archiving functions
15. Notification of submittal and RFI statuses and current responsible party
16. Permits and addendums
B. Some documents are not suitable to be shared using the NPS/DSC management software website.
Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using NPS/DSC management software website and shall be coordinated with Project team as appropriate.
C. Submit to Contracting Officer a list of employees who will need access to the website. Users will receive an invitation to register from Department of Interior (DOI). Once registered on DOI website, user will be given access to NPS/DSC management software website.
USFWS Hanalei Valley Viewpoint 01 31 00 - 5
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later.
1.7 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, the Contracting Officer will schedule the Pre-Construction Conference date in coordination with the Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Jobsite Safety
3. Resolution of comments on required Division 1 documents
4. Coordination of Subcontractors
5. Labor law application
6. Modifications
7. Payments to Contractor
8. Payroll reports
9. Contract time
10. Liquidated damages
11. Contractor Performance Evaluation
12. Display of Hotline posters
13. Notice to proceed
14. Correspondence procedures
15. NPS/DSC Project website
16. Acceptance/rejection of work
17. Progress meetings
18. Submittal procedures
19. NPS Final Accessibility Inspection
20. Environmental requirements and permits
21. Permit requirements
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials
25. Value engineering
26. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor. Meetings will be held at the Contractor’s job office or at the USFWS refuge office. The Contracting Officer will confirm the progress meeting location at the pre-construction meeting.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the
Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
USFWS Hanalei Valley Viewpoint 01 31 00 - 6
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of offsite fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update with three-week look ahead (provide updated Critical
Path Method (CPM)).
i. Impacts to highway traffic, lane closures, and coordination with HDOT.
j. Status of Project Record Drawings and O&M manuals.
k. Other business relating to work.
l. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting
Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
USFWS Hanalei Valley Viewpoint 01 31 00 - 7
x. Protection of adjacent work
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.8 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing
Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Storm Water Pollution Prevention Plan (SWPPP).
d. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
e. Training for Contractor personnel in accordance with position requirements.
f. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Noise and Acoustics Management
4. Temporary Storm Water Pollution Prevention Environmental Management
5. Construction Waste Management
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Noise and Acoustics Management
c. Temporary Storm Water Pollution Prevention
USFWS Hanalei Valley Viewpoint 01 31 00 - 8
4. Pollution Prevention (P2) practices: Submit evidence of P2 training, participation in
P2 programs and familiarity with P2 practices.
5. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution
Prevention Plan.
1.9 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the
Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the
Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. NEPA Environmental Assessment and FONSI
2. Hawaii Conservation District Use Application, subdivision and development permit KA-
3. Hawaii Coastal Zone Management Application, federal consistency review
4. National Historic Preservation Act, Section 106 review
5. Kauai County Class 1 Zoning Permit
6. National Pollutant Discharge Elimination System, Hawaii General Permit
C. Contractor Furnished Permits: The contractor will be responsible for the following construction-related permits.
1. Permit to Perform Work Upon State Highways: Permits listed below were identified as likely to be required based on typical means and methods of construction. The list is provided to assist Contractor in determining which permits will be required from the
Hawaii Department of Transportation for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. The Contractor shall obtain all permits required to legally conduct work.
a. Highway Construction Permit
b. Traffic Control Plan
c. Streetlight Relocation Request
d. Highway Lane Closure Request, USFWS Hanalei Valley Viewpoint 01 31 00 - 9
e. Weekly Lane Closure Form
f. Overweight/Oversize Vehicle Transport Permit (for restroom structure)
2. Electrical Utilities: If required, the Contractor will obtain a Utility Relocation Request permit from the Kauai Island Utility Cooperative for relocation or demolition of electrical utilities.
3. Noise Permit: If required, the Contractor will obtain a Community Noise Permit per Hawaii
Administrative Rules, Title 11, Chapter 46. See specification section 01 57 19.21 Noise and Acoustics Management.
4. Solid Waste Disclosure Form: If required, the Contractor shall prepare and submit Solid
Waste Disclosure Form from Construction Sites. See specification section 01 74 19
Construction Solid Waste and Disposal.
D. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
E. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
3. Upload permits to NPS/DSC management software website when permits are obtained.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
USFWS Hanalei Valley Viewpoint 01 32 16 - 1
CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of Construction Schedule requirements including:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.
C. The Contractor must obtain construction access prior to mobilization, see Contractor Furnished Permits. Coordinate site access with Contracting Officer.
1.2 DEFINITIONS
A. Activity: A discrete part of a project identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: Allocation of the Schedule of Values for completion of an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. Critical Path Method (CPM): Method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: Longest connected chain of interdependent activities through the network schedule that establishes minimum overall Project duration and contains no float.
E. Float: Measure of leeway in starting and completing an activity.
USFWS Hanalei Valley Viewpoint 01 32 16 - 2
1. Float: Not for the exclusive use or benefit of the Government or Contractor but is jointly owned.
2. Free Float: Amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total Float: Measure of leeway in starting or completing an activity without adversely affecting planned Project completion date.
F. Resource Loading: Allocation of manpower and equipment necessary for completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Electronic Copies: Schedules and reports submitted shall be posted on the NPS/DSC management software website in native electronic file formats. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.
B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show…