A04.03 DI-MGMT-81648 CFR.pdf

PDF 85 KB Posted

Attached to
Snorkel Standpipe Repair Federal contract opportunity
Solicitation number
N4523A23R0815
Issued by
Department of the Navy Naval Supply Systems Command

About this file

This Data Item Description outlines the format and content requirements for Condition Found Reports submitted by contractors in response to unexpected work discovered during contract performance for ship repair and maintenance. Condition Found Reports must be serialized, reference the relevant contract and work item, describe the discovered work requirement including location and recommended corrective action. They must also provide cost and schedule estimates for addressing the condition, identifying the preferred time frame for completion, and any potential impacts on contract milestones or completion dates. Electronic submissions are required per the terms of the contract DD 1423.

The related federal contract opportunity is a solicitation from the Department of the Navy seeking proposals to repair snorkel standpipes, with an anticipated award date of August 2023.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: CONDITION FOUND REPORT

Number: DI-MGMT-81648 Approval Date: 20040809 AMSC Number: N7531 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility: N PEO SHIPS-FL32 Applicable Forms: N/A

Use/Relationship: The Condition Found Report identifies needed repairs and recommends corrective action for work discovered during the contract performance period which are not covered by the work specifications.

This DID contains the format, content, and intended use information for the data product resulting from the work task described in the contract.

Requirements:

1. Reference documents. N/A.

2. Format. The report shall be in contractor’s format.

3. Content. The report shall be serialized by CFR Number, and shall include the following:

a. Contract number, ship and hull number

b. Work Item Number to which the CFR relates

c. Date work requirement was discovered

d. Clear description of the work requirement

e. Specific location of the work requirement

f. Recommendation for corrective action

3.1 Recommendation for appropriate/best time to accomplish (i.e. during current availability with or without schedule change, future CNO or Continuous Maintenance Availability), and supporting rationale for the recommendation (such as cost efficiencies, availability of work force, availability of material, premium expenditures, etc.).

3.2 Cost and time estimates and the time frame for which it is valid, including:

a. Class “C” cost estimates. For work requirements which could be estimated within five working days, a class “F” estimate (+/-40%) identifying any potential impact which may affect the current schedule shall be included. The Class “F” estimate shall also contain the date on which a class “C” estimate will be provided.

b. Estimated Premium/Acceleration Costs, including premium costs for; material, subcontractors, man-hours, rework and any additional costs to on going work resulting from inclusion of the CFR work requirement.

c. Identification of related changes, if any, to the internal milestones and production and contract completion dates shall be included. When no changes were required a statement to that fact shall also be included

4. Media. The electronic media requirements shall be as specified in the contract on the DD 1423 CDRL.

5. End of DI-MGMT-81648

Source: https://assist.dla.mil -- Downloaded: 2018-11-28T13:30Z

Check the source to verify that this is the current version before use.

DATA ITEM DESCRIPTION

File details come from the government source that posted it. Updated .