A00801-616276.pdf

PDF 772 KB Posted

Attached to
616276 FOXBOROUGH-MIDDLEBOROUGH-NORTON FAP No. STP(BR-OFF)-004S(017)X Bridge Preservation along I-
Solicitation number
BD-27-1030-0H100-0H002-133657
Issued by
Norfolk County, Massachusetts

About this file

This document is a Special Provisions specification issued by the Massachusetts Department of Transportation Highway Division for bridge preservation work along Interstate 495 in Foxborough, Middleborough, and Norton. The project, identified as Proposal No. 616276-136791 and Federal Aid Project No. STP(BR-OFF)-004S(017)X, encompasses repair and preservation activities at six bridge locations: F-06-023 (Spruce Street over I-495 in Foxborough), M-18-042 (Vernon Street over I-495 in Middleborough), M-18-043 (Cherry Street over I-495 in Middleborough), N-23-026 (North Washington Street over I-495 in Norton), N-23-027 (Newcomb Street over I-495 in Norton), and N-23-034 (Plain Street over I-495 in Norton). Work includes selective clearing and thinning, bridge pavement milling and overlay, deck repairs, joint replacement and sealing, sidewalk and curb restoration, structural steel repairs, substructure repairs, concrete protective coatings, steel cleaning and painting, and pavement markings. The estimated contract value is $9,271,000, with proposals due October 27, 2026 at 2:00 p.m. via www.bidx.com. Bidders must be pre-qualified by MassDOT in the Bridge-Construction or Painting-Structural category prior to submission. Standard work hours are 7:00 a.m. to 3:30 p.m. Monday through Friday during the off-season, with approved nighttime work between 9:00 p.m. and 5:30 a.m. The contract includes specific holiday work restrictions and ADA compliance requirements for pedestrian access throughout all work zones.

Pricing for the contract is subject to adjustment provisions for hot mix asphalt, Portland cement mixtures, diesel fuel, gasoline, and structural steel based on specified base prices posted on MassDOT's Highway Division website. A proposal guaranty equal to five percent of the bid value is required. Labor participation goals are set at 15.3% for minorities and 6.9% for women for each job category, applicable to both contractor and subcontractor on-site construction workforce. The project is subject to prevailing wage rate schedules as determined by the Massachusetts Department of Labor and Workforce Development and the United States Department of Labor. The contract is federally funded and subject to Build America, Buy America Act requirements mandating that all iron, steel, manufactured products, and construction materials be produced or manufactured in the United States, with limited exceptions. The contractor is responsible for environmental permitting, utility coordination, compliance with the National Defense Authorization Act regarding telecommunications equipment, truck safety device requirements, and adherence to all applicable federal, state, and local regulations including those concerning asbestos, lead paint removal, and protected species. The contract is governed by Massachusetts General Laws Chapter 30 Section 39M and includes federal equal employment opportunity requirements under Executive Order 11246.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Massachusetts Department Of Transportation Highway Division Proposal No. 616276-136791

A00801 - 1

DOCUMENT A00801

SPECIAL PROVISIONS

FOXBOROUGH – MIDDLEBOROUGH – NORTON

Federal Aid Project No. STP (BR-OFF)-004S(017)X Bridge Preservation along I-495, F-06-023, M-18-042, M-18-043, N-23-026, N-23-027 & N-23-034

Labor participation goals for this Project shall be 15.3% for minorities and 6.9% for women for each job category. The goals are applicable to both Contractor’s and Subcontractor’s on-site construction workforce. Refer to Document 00820 for details.

SCOPE OF WORK

All work under this Contract shall be done in conformance with the 2026 Standard Specifications for Highways and Bridges, the Supplemental Specifications contained in this book, the Construction Standard Details in effect as of July 2026, the 1990 Standard Drawings for Signs and Supports, the 2015 Overhead Signal Structure and Foundation Standard Drawings, the 11th Edition of the Manual on Uniform Traffic Control Devices (MUTCD) and the January 2026 Massachusetts Amendments to the MUTCD, the 1968 Standard Drawings for Traffic Signals and Highway Lighting, the latest edition of The American Standard for Nursery Stock, the Plans and these Special Provisions.

The work under this Contract shall consist of furnishing various artisans, materials, supplies, equipment and engineering services to perform bridge substructure, deck repairs, and painting along the I-495 Corridor in District Five for which no other contracts of this nature are in the process of being awarded. The work includes:

BRIDGE LOCATIONS

F-06-023 (3XN)

Spruce St. over I-495SB in Foxborough

1. Selective Clearing and Thinning.

2. Bridge Pavement Milling of the bridge Surface and Approaches of 1½”.

3. Perform Partial Depth Deck Repairs.

4. Replace Milled Wearing Surface with 1 ½” of Superpave Bridge Surface Course – 9.5

Polymer (SSC – B – 9.5-P).

5. Repair Joints and install new Pre-compressed Joint Seal at Abutment B and a sawcut with hot-poured Joint Sealer at Abutment A.

6. Repair Southeast Sidewalk and Restore Curb Alignment by Resetting Settled and Rotated

Curb.

7. Perform Structural Steel Repairs to Beam Ends.

A00801 - 2

SCOPE OF WORK (Continued)

8. Perform Substructure Repairs as needed.

9. Apply Concrete Protective Coating at Parapets, End Posts and Abutments.

10. Install Pavement Markings.

F-06-023 (3XP)

Spruce St. over I-495NB in Foxborough

3. Replace Milled Wearing Surface with 1 ½” of Superpave Bridge Surface Course – 9.5

Polymer (SSC – B – 9.5-P).

4. Repair Joints and install new Pre-compressed Joint Seal at Abutment C and a sawcut with hot-poured Joint Sealer at Abutment D.

5. Repair Northeast Sidewalk and Restore Curb Alignment by Resetting Settled and Rotated

Curb.

6. Perform Structural Steel Repairs to Beam Ends and Utility Beam Support.

7. Perform Substructure Repairs as needed.

8. Apply Concrete Protective Coating at Parapets, End Posts and Abutments.

9. Install deck drain extension.

10. Install Pavement Markings.+-

N-23-026 (3Y2)

N. Washington St. over I-495 in Norton

2. Replace Utility Beam Support.

3. Perform Substructure Repairs as needed.

4. Apply Concrete Protective Coating at Parapets, Pier and Abutments.

5. Clean (Full Removal) and Paint Steel Bridge No. N-23-026 (3Y2).

N-23-027 (3Y3)

Newcomb St. over I-495 in Norton

3. Perform Deck Repairs.

4. Replace Milled Wearing Surface with 1 ½” of Superpave Bridge Surface Course – 9.5

Polymer (SSC – B – 9.5-P).

5. Replace pre-compressed joint seal at both joints

6. R&R sidewalk curbing at both approaches and replace sidewalk.

7. Perform Structural Steel Repairs to Beam Ends.

8. Perform Substructure Repairs as needed.

9. Apply Concrete Protective Coating at Parapets, Pier and Abutments.

A00801 - 3

10. Clean (Full Removal) and Paint Steel Bridge No. N-23-027 (3Y3).

11. Install Pavement Markings.

N-23-034 (3Y4)

Plain St. over I-495 in Norton

3. Replace Milled Wearing Surface with 1 ½” of Superpave Bridge Surface Course – 9.5

Polymer (SSC – B – 9.5-P).

4. Perform Full Joint Replacement.

5. R&R sidewalk curbing at both approaches and replace sidewalk.

6. Perform Substructure Repairs as needed.

7. Apply Concrete Protective Coating at Parapets, Pier and Abutments.

8. Clean (Full Removal) and Paint Steel Bridge No. N-23-034 (3Y4).

9. Install Pavement Markings.

M-18-042 (4AY)

Vernon St. over I-495 in Middleborough

2. Jacking and Shoring for pier pedestal repairs.

3. Bridge Pavement Milling of the bridge Surface and Approaches of 1½”.

4. Reconstruct sidewalk along the wingwalls and remove & reset curbing.

5. Perform Full Depth and Partial Depth Deck Repairs.

6. Mill & Overlay Bridge and approach with 1 ½” of Superpave Bridge Surface Course –

9.5 Polymer (SSC – B – 9.5-P).

7. Perform Full Joint Replacement at pier deck joints.

8. Sawing and sealing abutment joints.

9. Perform Substructure Repairs as needed.

10. Apply Concrete Protective Coating at Parapets, Pier and Abutments.

11. Clean (Full Removal) and Paint Steel Bridge No. M-18-042 (4AY).

12. Clean out scuppers, scupper repair, fix/replace drain pipes disconnected from deck and pier cap.

13. Install Pavement Markings.

M-18-043 (4AA)

Cherry St. over I-495 in Middleborough

2. Bridge Pavement Milling of the bridge Approaches of 1½”.

3. Mill and overlay bridge approach with 1 ½” of Superpave Surface Course – 9.5 Polymer

9.5 Polymer (SSC – B – 9.5-P).

4. Replace Joint Seal at Pier No. 1 & 3

A00801 - 4

5. Sealing the joint between the concrete bridge deck and the base of the existing granite bridge curbing along the sidewalk.

6. Applying penetrating sealer to exposed bridge deck

7. Perform Full Joint Replacement at Pier No. 2.

8. Sawing and sealing abutment joints.

9. Replace specified diaphragm connection plates and clean & Paint Beam No. 13 and new connection plates within the limits of the repair and to address scrapes on bottom flange.

10. Perform Substructure Repairs as needed.

11. Apply Concrete Protective Coating at Parapets, Piers and Abutments.

12. Apply Pavement Markings.

All work shall be performed within, and accessed by, existing State, City or Town roadway layouts. No rights to enter on, or occupy, private property have been acquired for this project.

CONTRACTOR QUESTIONS AND ADDENDUM ACKNOWLEDGEMENTS

Prospective bidders are required to submit all questions to the Construction Contracts Engineer by 3:00 P.M. on the Tuesday of the previous week before the scheduled bid opening date. Any questions received after this time will not be considered for review by the Department.

Contractors should email questions and addendum acknowledgements to the following email address massdotspecifications@dot.state.ma.us The MassDOT proposal number and municipality is to be placed in the subject line.

SCHEDULE OF WORK

All proposed work hours shall conform to Subsection 7.09 and be subject to the written approval of the Engineer.

It is anticipated that all work under this contract will be done between the hours of 7:00 am to 3:30 pm, Monday through Friday in the off season and include “set-up” and “breakdown” time for all materials and equipment. All lanes shall promptly be re-opened to vehicular traffic in adherence to these specified times. The Contractor shall schedule and execute his work in such a manner as to present the least interference and impedance of traffic. In this case, safety devices and sign placement shall conform to the applicable sketches shown in the Standard Traffic Control Plans or an approved TTCP.

Night Time Work All work locations requiring night hours, as approved by the Engineer, are restricted as follows:

Sunday: 9:00 PM to 5:30 AM Monday Monday: 9:00 PM to 5:30 AM Tuesday Tuesday: 9:00 PM to 5:30 AM Wednesday Wednesday: 9:00 PM to 5:30 AM Thursday Thursday: 9:00 PM to 5:30 AM Friday mailto:MassDOTSpecifications@dot.state.ma.us

A00801 - 5

SCHEDULE OF WORK (Continued)

The work may not proceed beyond the normal 8-hour day unless prior approval is obtained from the Engineer for that day. Approval to work beyond the scheduled work will only be given when special conditions exist that warrant working beyond the scheduled work, as determined by the Engineer.

The Contractor may schedule night shifts longer than 8-hours with prior approval by the Engineer.

No additional compensation will be made for work scheduled during nighttime or longer working hours.

These time periods include the "set-up" and "breakdown" of the traffic pattern employed. No operations, personnel, or equipment will be allowed on the roadways except during working hours.

The Contractor shall schedule work to ensure the final coat of paint is not damaged by other operations. Any damage to coatings due to other Contractor’s operations shall be repaired at the Contractor’s expense.

The Contractor shall schedule operations such that any beam requiring temporary support or jacking shall be performed efficiently and will be paid once per location. This may require concurrent substructure and superstructure repairs.

Any jacking or shoring reused at the same bridge crossing as required by the Engineer shall be considered a remove and reset. Jacking and shoring transported to a new location will be considered a new payment of jacking and shoring item.

The Contractor shall schedule the work with consideration that zinc primer alone left exposed may deteriorate over a season. If the zinc primer is left exposed the contractor will be responsible for any surface preparation or rework needed prior to the application of the intermediate and final coats. Consideration should be given to applying the full three-coat system in a single season in all areas that do not require steel repairs, to limit rework as much as practical.

No work shall be scheduled in the vicinity of Gillette Stadium or the Xfinity Center during events.

PEDESTRIAN ACCESS

ADA compliant access must be maintained at all times, including pedestrian guidance systems at work zones. Any pedestrian detours or bypasses shall include ADA compliant route with proper barricades, railing, ramps and signage, etc.

EQUIVALENT SINGLE AXLE LOADS (ESALS)

The estimated traffic level to be used for SUPERPAVE HMA mixture designs for this contract, expressed in Equivalent Single Axle Loads (ESALs) for the design travel lane over a 20-year period, is 1.0 Million 18-kip (80-kn) ESALs.

A00801 - 6

HOLIDAY WORK RESTRICTIONS

(Supplementing Subsection 7.09)

The District Highway Director (DHD) may authorize work to continue during these specified time periods if it is determined by the District that the work will not negatively impact the traveling public. DHD may allow work in those areas on a case by case basis and where work is behind barrier and will not impact traffic

Below are the holiday work restrictions:

New Years Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.

Martin Luther King's Birthday (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.

President's Day (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.

Evacuation Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.

Patriot's Day (State Holiday) Work restrictions will be in place for Districts 3 and 6 along the entire Boston Marathon route and any other locations that the DHD in those districts determine are warranted so as not to impact the marathon. All other districts work restrictions will be as per DHD.

Memorial Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.

Bunker Hill Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.

Juneteenth No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.

Independence Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.

A00801 - 7

HOLIDAY WORK RESTRICTIONS (Continued)

Labor Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.

Columbus Day (Federal Holiday) No work on major arterials from 5:00 AM on the Friday before, until the normal start of business on the following day

Veterans' Day (Federal Holiday) No work restrictions due to traffic concerns.

Thanksgiving Day (Federal Holiday) No work on major arterials from 5:00 AM two days before until the normal start of business on the following Monday.

Christmas Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day.

BIDDERS LIST

Pursuant to the provisions of 49 CFR Part 26.11 all official bidders will be required to report the names, addresses and telephone numbers of all firms that submitted bids or quotes in connection with this project. Failure to comply with a written request for this information within 15 business days may result in a recommendation to the Prequalification Committee that prequalification status be suspended until the information is received.

The Department will survey all firms that have submitted bids or quotes during the previous year prior to setting the annual goal and shall request that each firm report its age and gross receipts for the year.

ASBESTOS

Asbestos may be present in forms including but not limited to asbestos cement utility conduit, pipe insulation, pipe wrap, and/or gunite/shotcrete. The contractor shall identify potential asbestos-containing material (ACM) that may be impacted as part of the contract work. If ACM or potential ACM will be physically impacted, the contractor shall communicate this information to the Engineer, District Environmental Engineer (DEE), receive approval prior to beginning work, and conduct all work in accordance with applicable federal, state, and local regulations. When ACM is impacted, Asbestos Liability Insurance shall be obtained. The Contractor and the Massachusetts Department of Transportation shall be named as additional insureds. No Assignment of work will be allowed without the approval of the Engineer. The contractor will be reimbursed for this work.

A00801 - 8

BUILD AMERICA BUY AMERICA PREFERENCE

On Federally-aid projects the Buy America (23.CFR § 635.410) and Build America, Buy America Act. requires the following,

(1) all iron and steel used in the project are produced in the United States--this means all manufacturing processes, from the initial melting stage through the application of coatings, must occur in the United States. Foreign steel and iron can be used if the cost of the materials does not exceed 0.1% of the total Contract cost or $2,500, whichever is greater.

The action of applying a coating to a covered material (i.e., steel and iron) is deemed a manufacturing process subject to Buy America. Coating includes epoxy coating, galvanizing, painting and any other coating that protects or enhances the value of a material subject to requirements of Build America, Buy America. Steel used for temporary support of excavation, including H piles, soldier piles, and sheeting when the steel is required to be left in place is subject to requirements of Build America, Buy America. Temporary steel, shall remain in place when it falls within the influence zone of the soil supporting any structure or railroad tracks.

(2) all manufactured products used in the project are produced in the United States—this means the manufactured product was manufactured in the United States and

(3) all construction materials are manufactured in the United States—this means that all manufacturing processes for the construction material occurred in the United States.

“Construction materials” includes an article, material, or supply—other than an item of primarily iron or steel; a manufactured product; cement and cementitious materials;

aggregates such as stone, sand, or gravel; or aggregate binding agents or additives—that is or consists primarily of:

• non-ferrous metals,

• plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables),

• glass (including optic glass),

• lumber; or

• drywall.

The Buy America preference only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a Buy America preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished infrastructure project but are not an integral part of the structure or permanently affixed to the infrastructure project.

All articles, materials, and supplies should be classified as an iron or steel product, a manufactured product, or another product as specified by law or in 2 CFR part 184 (such other products specified by law or in 2 CFR part 184 include “excluded materials” and “construction materials”); an article, material, or supply must not be considered to fall into multiple categories.

A00801 - 9

DISPOSAL OF EXCAVATED MATERIALS AND SITE CLEANING

The Contractor is required to broom clean all work site areas after the removal of excavated debris regardless of preexisting conditions. This includes areas under excavated bridge joints such as pier caps, revetment areas, and bridge shielding areas. Removal of debris, site cleaning, and disposal of debris is incidental to the Contract and no additional payment will be made unless otherwise noted or specified on this Contract.

CONTAMINATED SOIL

Soil to be removed from the project area shall not be assumed to be uncontaminated and must be evaluated prior to off-site management for potential contamination with hazardous materials. No soil may be disposed of off-site without proper assessment by the contractor and approval from the Resident Engineer (RE), District Environmental Engineer (DEE), or the project designee.

SOIL STOCKPILING DIRECTIVE P-22-001

Any stockpiling of soil must be performed in compliance with Policy Directive P-22-001, Off- Site Stockpiling of Soil from MassDOT Construction Projects. This directive limits the allowable locations for off-site stockpiling of soil generated during MassDOT projects and includes various requirements that must be satisfied by the contractor prior to off-site stockpiling. The Contractor is responsible for identifying a suitable stockpile location.

ENVIRONMENTAL PERMITTING

The proposed work does not occur in jurisdictional wetland resources subject to section 401 or section 404 of the Clean Water Act; therefore, the project does not require a Water Quality Certification from the Massachusetts Department of Environmental Protection or authorization from the US Army Corps of Engineers. The proposed work qualifies for the bridge exemption authorized in the Transportation Bond Bill and is therefore not subject to the Massachusetts Wetlands Protection Act, the Massachusetts Public Waterfront Act (Chapter 91), or the Massachusetts Environmental Policy Act.

If field conditions and/or Contractor-proposed erection, demolition, staging, or other procedures require work to occur in or otherwise impact water or wetland resource areas, the Contractor is advised that no associated work can occur until all required environmental permits have been obtained allowing such work. The Contractor must notify the District 5 Highway Director and Resident Engineer in writing at least 60 days prior to desire commencement of the proposed activity.

All environmental submittals, including any Contract with Local, State, or Federal environmental agencies, must be coordinated with the District 5 Environmental Engineer. The Contractor is expected to fully cooperate with requests for information and provide same in a timely manner. The Contractor is further advised that the Department will not entertain a delay claim due to the time required to obtain the environmental permits.

A00801 - 10

CONTRACTOR ACTIVITY ADJACENT TO WETLANDS

The Contractor shall not stockpile material or equipment, perform maintenance or refuel equipment in a wetland area, within 100 feet of a wetland, or within 200 feet of a river, stream, pond, or other similar open body of water.

NORTHERN LONG-EARED BAT AND TRICOLORED BAT PROTECTION

The northern long-eared bat (Myotis septentrionalis; NLEB) and tricolored bat (Perimyotis subflavus; TCB) are listed as federally endangered or proposed endangered, respectfully, under the Endangered Species Act (ESA). The U.S. Fish and Wildlife Service (USFWS) developed this guidance to address ESA compliance and promote conservation of NLEB and TCB. MassDOT, on behalf of FHWA, completed the Section 7 consultation process by utilizing the USFWS Information for Planning and Consultation (IPaC) system. The IPaC review concluded that proposed activities result in a May Affect, Not Likely to Adversely Affect (NLAA) determination, thereby fulfilling federal Section 7 informal consultation compliance. (see Document USFWS NLAA).

In advance of the uplisting of the TCB to endangered under the ESA, the following Avoidance and Minimization Measures (AMMs) must be strictly adhered to in order to protect NLEB and TCB and to be in compliance with the ESA. Contact MassDOT Environmental Services - Wildlife Unit Supervisor for questions about project limits, restrictions, or conservation measures.

General AMM

• The Contractor shall ensure all personnel working in on the project site are aware of all environmental commitments related to NLEB and TCB, including all applicable AMMs. NLEB and TCB information (https://www.fws.gov/midwest/endangered/mammals/nleb/ and https://www.fws.gov/species/tricolored-bat-perimyotis-subflavus) shall be made available to all personnel.

Lighting AMMs

• Direct temporary lighting away from suitable habitat during the active season: April 15 to

October 31.

• When installing new or replacing existing permanent lights, use downward-facing, full cut-off lens lights (with same intensity or less for replacement lighting); or for those transportation agencies using the BUG system developed by the Illuminating Engineering Society, be as close to 0 for all three ratings with a priority of “uplight” of 0 and “backlight” as low as practicable.

Tree Removal AMMs

• If additional cutting is proposed by the Contractor that is outside the scope of this contract, additional review is required by the MassDOT Highway Division’s Environmental Services Section, and additional review and restrictions may be required by the USFWS.

• Ensure tree removal is limited to that specified in project plans and ensure that contractors understand clearing limits and how they are marked in the field (e.g., install bright colored flagging/fencing prior to any tree clearing to ensure contractors stay within clearing limits).

• No tree cutting, trimming, or removal of trees and/or woody vegetation >3-inch in diameter shall be conducted between: April 15 to October 31

• The Contractor shall ensure all personnel working in on the project site are aware of all environmental commitments related to NLEB and/or TCB, including the TOY restriction.

https://www.fws.gov/midwest/endangered/mammals/nleb/

A00801 - 11

NORTHERN LONG-EARED BAT AND TRICOLORED BAT PROTECTION (Continued)

Bridge AMM

• Following the March 9th, 2026, guidance from the USFWS regarding roadway transportation structures in New England, an inspection of the bridge for the presence of, or evidence of use by, bats was not conducted. The MassDOT Wildlife Unit conducted a desktop review that determined the bridge/culvert is not (1) a covered bridge, (2) a bridge with wood/timber as a component of construction, (3) a bridge with stone/masonry construction, (4) a “cave-like” culvert, typically greater than 200 feet long, and/or (5) located on Nantucket County. The bridge/culvert did not meet any of these exceptions, and therefore no survey was required.

CONCRETE FINISHING

Bridge decks patches that are to be left exposed without bituminous or cement concrete overlays or that are receiving a waterproofing mix without waterproofing membrane shall receive a textured steel raked finish. The deck shall be transversely tined with a metal rake while the concrete is still plastic perpendicular to the centerline of the bridge from. Rake tines shall be spaced less than two (2) inches on center. No un-textured deck surface greater than 6 in. in width shall remain. A minimum clearance of 1 in. shall exist between the texturing and the end of deck or edge of metal bridge deck expansion joint. No overlapping or repeating of texturing in the same location shall be permitted.

NONCONFORMING COMPRESSIVE STRENGTH OF CEMENT CONCRETE

Concrete with compressive strength test results failing to attain the limits specified in Table 901.64-3 of 901.64.B: Acceptance Testing shall be evaluated for structural adequacy and serviceability at the Contractors’ expense. The Department will review all production records, the concrete test records, petrographic analysis report, field notes, and the placement records for the concrete in question. If the Engineer determines the material is found to be adequate to remain in place, payment shall be adjusted in accordance with the following formula:

𝑃𝑃 =

2(𝑓𝑓𝑓𝑓 − 𝑓𝑓′𝑐𝑐)(𝑈𝑈𝑈𝑈)(𝑄𝑄)

𝑓𝑓′𝑐𝑐

Where:

𝑃𝑃 = 𝑝𝑝𝑝𝑝𝑝𝑝 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑓𝑓𝑓𝑓𝑓𝑓 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐

𝑓𝑓′𝑐𝑐 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 28 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑓𝑓𝑓𝑓 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 56 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑄𝑄 = 𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝑏𝑏𝑏𝑏 𝑡𝑡ℎ𝑒𝑒 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝑈𝑈𝑈𝑈 = 𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑜𝑜𝑜𝑜 𝑡𝑡ℎ𝑒𝑒 𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑠𝑠𝑠𝑠𝑠𝑠 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑝𝑝𝑝𝑝𝑝𝑝 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦 𝑓𝑓𝑓𝑓𝑓𝑓 𝑡𝑡ℎ𝑒𝑒 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝

A00801 - 12

GENERAL REQUIREMENTS FOR DEMOLITION AND WORK INVOLVING

PAINTED STEEL

(02/06/2020)

Demolition and work involving painted steel shall conform to the requirements of Subsection 961 of the Standard Specifications.

Work Involving Painted Steel

Hazardous materials shall be removed in the immediate area of any intended welding, heating, saw cutting or burning of steel. Hazardous material removal is required to allow the demolition of structural steel, railings, drainage systems, utility supports, steel lamp posts, etc.

The contractor shall assume that the coatings on the steel contain lead (Pb), unless otherwise determined by testing. The contractor shall certify in writing to the Engineer the results of all testing, and shall also certify that any lead (Pb) coated steel removed from the project was not reused or buried, but was sent to a scrap metal recycling facility.

Implement and maintain programs and procedures, which comply with the requirements of this specification and all applicable standards and regulations. Comply with all applicable regulations even if the regulation is not specifically referenced herein. If a state or local regulation is more restrictive than the regulation of this specification, follow the more restrictive requirements.

This requirement is intended only for the demolition and preparation prior to repair and does not include provisions for recoating of steel.

Environmental

All applicable portions of Subsections 961.65 “Worker Protection” and 961.66 “Environmental Protection and Monitoring” shall be followed when performing this work.

During chemical stripping a hand washing facility may be used in lieu of a decontamination/changing facility.

Hazardous material shall be collected during the disassembly and disposed of as outlined in Subsection 961.68 “Handling of Hazardous Waste and Reporting Release Programs”.

The applicable submittals shall be according to Subsection 961.69 “Submittals”.

Cleaning/Removal

Cutting Or Burning Of Steel

All surfaces to be welded, heated, saw cut or burned shall be cleaned so as to remove all contaminants and/or hazardous materials, which could be discharged to the environment as a function of the subsequent operations.

A00801 - 13

GENERAL REQUIREMENTS FOR DEMOLITION AND WORK INVOLVING

PAINTED STEEL (Continued)

Lead paint shall be removed in its entirety in an area prescribed by a 6 inch (15 cm) minimum offset from the required work. The paint removal operation may be dry abrasive blasting, wet abrasive blasting or chemical stripping.

Proper level of containment shall be used when performing this work in accordance with Subsection 961.67 “Containment”. Full containment is not required during chemical stripping operation however; the Contractor shall install proper shielding and/or tarpaulins under the chemical stripping operations in order to catch all debris generated during this procedure. A cleaned area must be inspected and approved before the demolition operations are started.

During cleaning operations the Contractor shall be required to furnish and erect temporary floodlights illuminating the steel surface at a minimum of 30-foot candles. This lighting shall be used in areas where there is insufficient lighting for proper cleaning operations and inspection.

The Contractor shall supply electrical power.

The Contractor shall provide support for interim and final inspection of the bridge during cleaning operations. This support shall include the necessary traffic controls and safe access to the work.

Mechanical Disassembly Of Steel

All surfaces to be mechanically disassembled by shear cutting or removing bolts or rivets shall not require deleading. When shear cutting or removing bolts or rivets, the Contractor shall not use any method that will cause dust and/or particles to be emitted and/or dispersed into the environment to an extent that would expose the workers above the Action Levels of 30µg/m3.

For purposes of limiting the lead (Pb) dust, the Contractor will be required to dampen the lead paint work areas.

The contractor shall install a proper shielding and/or tarpaulins under all lead-paint-coated surfaces to be shear cut or bolts or rivets ordered removed in order to catch any loose lead paint chips, dust or particles.

PREPARATION OF CONCRETE SURFACES:

All concrete surfaces to be patched shall be roughened, cleaned of all laitance, dirt, grease, oil, other contaminants, and all standing water. All reinforcing steel encountered in the excavation shall be thoroughly cleaned by abrasive blasting before being covered with new concrete.

In bonding new concrete to already set concrete, the surface of the concrete shall be thoroughly cleaned, roughened, and ponded with clean water to achieve Saturated Surface Dry (SSD) condition then it shall then be blown off with oil free compressed air.

A00801 - 14

PROTECTION OF UTILITIES AND PROPERTY

(Supplementing Subsection 7.13)

The bridge plans may indicate the location of existing known utilities in the vicinity of the work.

Bidders are cautioned to verify this information, as its accuracy and completeness are not guaranteed in any manner.

The Contractor’s attention is directed to the necessity of making his own investigation in order to assure that no damage to existing structures, drainage lines, traffic signal conduits, etcetera, will occur.

The Contractor is responsible for the protection of vehicular and pedestrian areas on and under the bridges being worked on. The Contractor at no additional compensation (unless otherwise, noted in this Contract) shall take all necessary precautions.

PIGEON WASTE

The Contractor shall remove and dispose of the pigeon waste and any other debris accumulated on the steel members and bridge seats in areas where work is being performed. Pigeon waste and debris material contaminants will require special handling and disposal in accordance with all Federal, state, and local requirements. No separate payment will be made for removal and disposal of pigeon waste. Cost shall be incidental to the contract pay items.

SUBSECTION 8.02 SCHEDULE OF OPERATIONS

Replace this subsection with the following:

An integrated cost and schedule controls program shall be implemented by the Contractor to track and document the progress of the Work from Notice to Proceed (NTP) through the Contractor Field Completion (CFC) Milestone. The Contractor’s schedules will be used by the Engineer to monitor project progress, plan the level-of-effort required by the Department’s work force and consultants and as a critical decision-making tool. Accordingly, the Contractor shall ensure that it complies fully with the requirements specified herein and that its schedules are both accurate and updated as required by the specification throughout the life of the project. Detailed requirements are provided in Division II, Section 722 Construction Scheduling.

NOTICE TO OWNERS OF UTILITIES

(Supplementing Subsection 7.13)

District 5 Acting Utility/Constructability Engineer Diane Hayes (617) 429-0431 diane.e.hayes@dot.state.ma.us

Written notice shall be given by the Contractor to all public service corporations or officials owning or having charge of publicly or privately owned utilities of the Contractor’s intention to commence operations affecting such utilities at least one week in advance of the commencement of such operations and the Contractor shall at that time file a copy of such notice with the Engineer.

mailto:diane.e.hayes@dot.state.ma.us

A00801 - 15

NOTICE TO OWNERS OF UTILITIES (Continued)

A list of public and private utilities can be found on the MassDOT website at:

https://www.mass.gov/info-details/utility-contacts-by-district-and-municipality

Select District 5

Select Town, and then locate the utility. The utility contact list is for guidance only and is not guaranteed to be complete or up to date.

NOTIFICATION OF PUBLIC OFFICALS

Town officials are shown at website https://www.mass.gov/lists/massachusetts-city-and-town-websites and select the required City/Town website.

State Police are shown at website https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries. Select the area of jurisdiction to find the local station.

The Contractor shall be responsible for informing the following officials in each area that he is assigned to work in: Superintendent, Department of Public Works or Town Engineer.

Superintendent, Water Department, Superintendent, Sewer Departments. Police Department, Fire Department, Electric Company, Railroads.

NATIONAL GRID EMERGENCY TELEPHONE NUMBERS

ELECTRIC:

Outage/ Emergency: 1-800-465-1212 New Service: 1-800-375-7405 Customer Support: 1-800-322-3223

EVERSOURCE EMERGENCY TELEPHONE NUMBERS

GAS:

Outage/ Emergency: 800-592-2000 New Service: 866-678-2744 Customer Support: 800-592-2000

ELECTRIC:

Outage/ Emergency: 1-800-592-2000 or 1-844-726-7562 New Service: 1-888-633-3797 (1-888-need pwr) Customer Support: 1-800-340-9822 https://www.mass.gov/info-details/utility-contacts-by-district-and-municipality https://www.mass.gov/lists/massachusetts-city-and-town-websites https://www.mass.gov/lists/massachusetts-city-and-town-websites https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries

A00801 - 16

SUBSECTION 8.14 UTILITY COORDINATION, DOCUMENTATION, AND

MONITORING RESPONSIBILITIES

A. GENERAL

In accordance with the provisions of Section 8.00 Prosecution and Progress, utility coordination is a critical aspect to this Contract. This section defines the responsibility of the Contractor and MassDOT, with regard to the initial utility relocation plan and changes that occur as the prosecution of the Work progresses. The Engineer, with assistance from the Contractor shall coordinate with Utility companies that are impacted by the Contractor’s operations. To support this effort, the Contractor shall provide routine and accurate schedule updates, provide notification of delays, and provide documentation of the steps taken to resolve any conflicts for the temporary and/or permanent relocations of the impacted utilities. The Contractor shall provide copies to the Engineer of the Contractor communication with the Utility companies, including but not limited to:

• Providing advanced notice, for all utility-related meetings initiated by the Contractor.

• Providing meeting minutes for all utility-related meetings that the Contractor attends.

• Providing all test pit records.

• Request for Early Utility work requirements of this section (see below).

• Notification letters for any proposed changes to Utility start dates and/or sequencing.

• Written notification to the Engineer of all apparent utility delays within seven (7) Calendar

Days after a recognized delay to actual work in the field – either caused by a Utility or the Contractor.

• Any communication, initiated by the Contractor, associated with additional Right-of-Way needs in support of utility work.

• Submission of completed Utility Completion Forms.

B. PROJECT UTILITY COORDINATION (PUC) FORM

The utility schedule and sequence information provided in the Project Utility Coordination Form (if applicable) is the best available information at the time of the bid and has been considered in setting the contract duration. The Contractor shall use all of this information in developing the bid price and the Baseline Schedule Submission, inclusive of the individual utility durations sequencing requirements, and any work that has been noted as potentially concurrent utility installations.

C. INITIATION OF UTILITY WORK

The Engineer will issue all initial notice-to-proceed dates to each Utility company based on either the:

1) Contractor’s accepted Baseline Schedule

2) An approved Early Utility Request in the form of an Early Utility sub-net schedule (in accordance with the requirements of this Subsection)

3) An approved Proposal Schedule

C.1 - BASELINE SCHEDULE – UTILITY BASIS

The Contractor shall provide a Baseline Schedule submission in accordance with the requirements of Subsection 8.02 and inclusive of all of the information provided in the PUC Form that has been issued in the Contract documents. This is to include the utility durations, sequencing of work, allowable concurrent work, and all applicable considerations that have been depicted on the PUC Form.

A00801 - 17

SUBSECTION 8.14 (Continued)

C.2 – EARLY UTILITY REQUEST – (aka SUBNET SCHEDULE) PRIOR TO THE BASELINE All early utility work is defined as any anticipated/required utility relocations that need to occur prior to the Baseline Schedule acceptance. In all cases of proposed early utility relocation, the Contractor shall present all known information at the pre-construction conference in the form of a ‘sub-net’ schedule showing when each early utility activity needs to be issued a notice-to-proceed. The Contractor shall provide advance notification of this intent to request early utility work in writing at or prior to the Pre-Construction meeting. Prior to officially requesting approval for early utility work, the Contractor shall also coordinate with MassDOT and all utility companies (private, state or municipal) which may be impacted by the Contract. If this request is acceptable to the Utilities and to MassDOT, the Engineer will issue a notice-to-proceed to the affected Utilities, based on these accepted dates.

C.3 – PROPOSAL SCHEDULE - CHANGES TO THE PUC FORM

If the Contractor intends to submit a schedule (in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02) that contains durations or sequencing that vary from those provided in the Project Utility Coordination (PUC) Form, the Contactor must submit this as an intended change, in the form of a Proposal Schedule and in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02. These proposed changes are subject to the approval of the Engineer and the impacted utilities, in the form of this Proposal Schedule and a proposed revision to the PUC form. The Contractor shall not proceed with any changes of this type without written authorization from the Engineer, that references the approved Proposal Schedule and PUC form changes. The submission of the Baseline Schedule should not include any of these types of proposed utility changes and should not delay the submission of the Baseline Schedule. As a prerequisite to the Proposal Schedule submission, and in advance of the utility notification(s) period, the Contractor shall coordinate the proposed utility changes with the Engineer and the utility companies, to develop a mutually agreed upon schedule, prior to the start of construction.

D. UTILITY DELAYS

The Contractor shall notify the Engineer upon becoming aware that a Utility owner is not advancing the work in accordance with the approved utility schedule. Such notice shall be provided to the Engineer no later than seven (7) calendar days after the occurrence of the event that the Contractor believes to be a utility delay. After such notice, the Engineer and the Contractor shall continue to diligently seek the Utility Owner’s cooperation in performing their scope of Work.

E. UTILITY DELAYS

The Contractor shall notify the Engineer upon becoming aware that a Utility owner is not advancing the work in accordance with the approved utility schedule. Such notice shall be provided to the Engineer no later than seven (7) calendar days after the occurrence of the event that the Contractor believes to be a utility delay.

After such notice, the Engineer and the Contractor shall continue to diligently seek the Utility Owner’s cooperation in performing their scope of Work.

In order to demonstrate that a critical path delay has been caused by a third-party Utility, the Contractor must demonstrate, through the requirements of the monthly Progress Schedule submissions and the supporting contract records associated with Subsection 8.02, 8.10 and 8.14, that the delays were beyond the control of the Contractor.

A00801 - 18

SUBSECTION 8.14 (Continued)

All documentation provided in this section is subject to the review and verification of the Engineer and, if required, the Utility Owner. In accordance with MassDOT Specifications, Division I, Subsection 8.10, a Time Extension will be granted for a delay caused by a Utility, only if the actual duration of the utility work is in excess of that shown on the Project Utility Coordination Form, and only if;

1) proper Notification of Delay was provided to MassDOT in accordance with the time requirements that are specified in this Section

2) the utility delay is a critical path impact to the Baseline Schedule (or most recently approved Progress Schedule)

F. LOCATION OF UTILITIES

The locations of existing utilities are shown on the Contract drawings as an approximation only.

The Contractor shall perform a pre-construction utility survey, including any required test pits, to determine the location of all known utilities no later than thirty (30) calendar days before commencing physical site work in the affected area.

G. POST UTILITY SURVEY – NOTIFICATION

Following completion of a utility survey of existing locations, the Contractor will be responsible to notify the Engineer of any known conflicts associated with the actual location of utilities prior to the start of the work. The Engineer and the Contractor will coordinate with any utility whose assets are to be affected by the Work of this Contract. A partial list of utility contact information is provided in the Project Utility Coordination Form.

H. MEETINGS AND COOPERATION WITH UTILITY OWNERS

The Contractor shall notify the Engineer in advance of any meeting they initiate with a Utility Owner’s representative to allow MassDOT to participate in the meeting if needed.

Prior to the Pre-Construction Meeting, the Contractor should meet with all Utility Owners who will be required to perform utility relocations within the first 6 months of the project, to update the affected utilities of the Project Utility Coordination Form and all other applicable Contract requirements that impact the Utilities. The Contractor shall copy the Engineer on any correspondence between the Utility Owner and the Contractor.

I. FORCE ACCOUNT / UTILITY MONITORING REQUIREMENTS

The Engineer will be responsible for recording daily Utility work force reports. The start, suspension, re-start, and completion dates of each of the Utilities, within each phase of the utility relocation work, will be monitored and agreed to by the Engineer and the Contractor as the work progresses.

J. ACCESS AND INSPECTION

The Contractor shall be responsible for allowing Utility owners access to their own utilities to perform the relocations and/or inspections. The Contractor shall schedule their work accordingly so as not to delay or prevent each utility from maintaining their relocation schedule.

A00801 - 19

COMPLIANCE WITH THE NATIONAL DEFENSE AUTHORIZATION ACT

(Supplementing Subsection 7.01)

On all projects, the “Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment” Regulation (2 CFR 200.216) prohibits the Contractor from using or furnishing the following telecommunications equipment or services:

• Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities).

• For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities).

• Telecommunications or video surveillance services provided by such entities or using such equipment.

• Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.

This prohibition applies to all products manufactured by the aforementioned companies, including any individual components or parts.

By submitting a bid on a project, the Contractor certifies that all work will be in compliance with the terms of 2 CFR 200.216. The Contractor shall submit a COC indicating compliance with the above provisions for all telecommunications equipment or services included in the Contract.

Payment for the item in which the materials are incorporated may be withheld until these COCs are received. Any cost involved in furnishing the certificate(s) shall be borne by the Contractor.

TRUCK SAFETY DEVICES

(Supplementing Subsection 7.04: Motor Vehicles)

All motor vehicles subject to Section 7 of Chapter 90 to be operated under this Contract shall be equipped with safety devices as provided therein and in 540 CMR 4.00.

The Contractor shall certify to the Registry of Motor Vehicles, in a manner prescribed by the Registrar, that all applicable vehicles are equipped with Lateral Protective Devices, Convex Mirrors, Cross Over Mirror(s) and Back Up Cameras in accordance with the requirements of 540

CMR 4.00.

The Contractor shall provide evidence satisfactory to the Department to demonstrate compliance with the above certification requirement for all applicable vehicles operated under this Contract by the Contractor and its subcontractors and vendors in a manner set forth by the Department.

A00801 - 20

TRUCK SAFETY DEVICES (Continued)

Thereafter, the Contractor shall have an affirmative obligation to continue to provide such evidence of compliance on an ongoing basis and no later than 7 days after certification with the Registry of Motor Vehicles of any additional vehicles operated under this Contract by the Contractor and its subcontractors and vendors.

Non-compliance with respect to a vehicle that is subject to 540 CMR 4.00 may subject the Contractor to statutory fines as established in M.G.L. c. 90, § 7 and/or contractual remedies up to and including termination of the Contract.

NON-BID-ITEM

The following specs included under Non-bid Item will be required only as directed by the Engineer to cover such a work that has not been included in any contract bid Items. the Contractor will not bid on the specialty services; however, the Contractor will be reimbursed for the cost as required by the engineer:

PAYMENT FOR SPECIALTY SERVICES

The Contractor will be paid for any specialty services (Regardless of whether hired by the Contractor as a specialty sub-contractor crew, or as an individual artisan) required for work that has not been included as incidental to any Contract Bid Item plus ten (10) percent. However, no specialty services shall be hired until approved by the Engineer and competitive prices may be required if the Engineer so directs. The specialty services will be used only as required by the Engineer.

SUPPLEMENTAL REQUIREMENTS FOR NON-BID ITEMS

(Supplementing Subsection 3.04)

The Contractor will be paid for additional artisans, equipment rental, materials, engineering services and specialty services required to perform the work plus (10%) percent, plus actual increased bond premium.

The Contractor shall be required to furnish certified paid receipts for additional artisans, equipment rental, materials, engineering services and specialty services that are required to perform the work prior to payment by the…