616276 Bid Items List.txt

TXT text file 5 KB Posted

Attached to
616276 FOXBOROUGH-MIDDLEBOROUGH-NORTON FAP No. STP(BR-OFF)-004S(017)X Bridge Preservation along I-
Solicitation number
BD-27-1030-0H100-0H002-133657
Issued by
Norfolk County, Massachusetts

About this file

This is a bid items list for a bridge preservation project issued by the Massachusetts Department of Transportation (MassDOT) along Interstate 495 in Foxborough, Middleborough, and Norton. The project encompasses bridge preservation work across six locations (F-06-023, M-18-042, M-18-043, N-23-026, N-23-027, and N-23-034) under Federal Aid Project No. STP(BR-OFF)-004S(017)X. The scope includes selective clearing and thinning, bridge deck drainage improvements, structural steel repairs, concrete excavation and placement, pavement milling and resurfacing with superpave materials, joint sealing, curb work, pedestrian ramp construction, traffic management and safety measures, protective coatings and sealers, and temporary protective shielding. Significant line items include 8,888 square yards of bridge pavement milling, 751 tons of superpave bridge surface course, 60,751 square feet of elastomeric protective coating, 8,200 square yards of penetrating epoxy sealer treatment, and 11,681 square feet of existing protective shielding removal and reset. Electronic proposals are due October 27, 2026 at 2:00 p.m. via www.bidx.com. Bidders must be pre-qualified by MassDOT in either the Bridge-Construction or Painting-Structural category prior to submission by submitting a Request Proposal Form (R109) to prequal.r109@dot.state.ma.us.

The estimated contract value is $9,271,000. A proposal guaranty equal to five percent of the bid value is required. The project includes price adjustment provisions for hot mix asphalt, Portland cement mixtures, diesel fuel, gasoline, and structural steel tied to specified base prices posted on MassDOT's Highway Division website. The contract is subject to prevailing wage rate schedules as determined by the Massachusetts Department of Labor and Workforce Development and the United States Department of Labor. Minority and female participation goals are contained in the specifications appendices. The contract is governed by Massachusetts General Laws Chapter 30 Section 39M and includes federal equal employment opportunity requirements under Executive Order 11246 and Architectural Access Board rules and regulations. Proposal documents are available exclusively on www.bidx.com, and paper submissions are not accepted. Interested parties may request informational documents at no charge by contacting MassDOTBidDocuments@dot.state.ma.us.

Text of this file

PRO_FILENO = 616276,DESCPT = Bridge Preservation along I-495, F-06-023, M-18-042, M-18-043, N-23-026, N-23-027 & N-23-034,Location = FOXBOROUGH,DB_CONTRACT = 136791

OFF_QUANT,UNITS,DESCPT1,ITEM_NO

"4035.000","SY","SELECTIVE CLEARING AND THINNING AT BRIDGES","102.02"

"1.000","EA","BLEEDER (BRIDGE DECK) PVC","106.15"

"1.000","EA","BRIDGE DECK DRAIN PVC PIPE EXTENSION","106.16"

"35.000","CF","ELASTOMERIC CONCRETE EXPANSION DAMS","106.491"

"9.000","EA","JACKING AND SHORING","106.88"

"250.000","FT","SEALING BENEATH GRANITE BRIDGE CURBING","107.88"

"795.000","LB","STRUCTURAL STEEL REPAIRS","107.97"

"124.000","CY","UNCLASSIFIED EXCAVATION","120.1"

"29.000","CY","REINFORCED CONCRETE EXCAVATION","127.1"

"30.000","CY","REINFORCED CONCRETE SUBSTRUCTURE EXCAVATION","127.12"

"34.000","SY","REINFORCED CONCRETE DECK EXCAVATION (FULL DEPTH)","127.4"

"9.000","CY","REINFORCED CONCRETE DECK EXCAVATION (PARTIAL DEPTH)","127.41"

"50.000","CY","REINFORCED CONCRETE DECK EXCAVATION AT JOINTS","127.42"

"37.000","SY","BRIDGE PAVEMENT EXCAVATION","129.6"

"80.000","CY","GRAVEL BORROW","151."

"390.000","SY","FINE GRADING AND COMPACTING - SUBGRADE AREA","170."

"1.000","TON","DISPOSAL OF TREATED WOOD PRODUCTS","184.1"

"3.000","EA","DRAINAGE STRUCTURE ADJUSTED","220."

"3.000","FT","DRAINAGE STRUCTURE REBUILT","220.2"

"6.000","CY","REMOVAL OF DRAINAGE STRUCTURE SEDIMENT","227.3"

"6.000","EA","GATE BOX ADJUSTED","358."

"8888.000","SY","BRIDGE PAVEMENT MILLING","415.4"

"751.000","TON","SUPERPAVE BRIDGE SURFACE COURSE - 9.5 POLYMER (SSC-B - 9.5 - P)","450.601"

"33.000","TON","HMA FOR PATCHING","451."

"791.000","GAL","ASPHALT EMULSION FOR TACK COAT","452."

"5980.000","FT","HMA JOINT ADHESIVE","453."

"12.000","TON","TEMPORARY ASPHALT PATCHING","472."

"293.000","FT","SAWING AND SEALING JOINTS IN ASPHALT PAVEMENT AT BRIDGES","482.31" "77.000","FT","GRANITE TRANSITION CURB FOR PEDESTRIAN CURB RAMPS - STRAIGHT","509."

"640.000","FT","CURB REMOVED AND RESET","580."

"3.000","EA","CURB INLET REMOVED AND RESET","581."

"235.000","FT","CURB REMOVED AND DISCARDED","594."

"1.000","EA","TEMPORARY IMPACT ATTENUATOR, REDIRECTIVE, TL-2","628.314"

"300.000","FT","TEMPORARY FENCE","657."

"70.000","SY","CEMENT CONCRETE PEDESTRIAN CURB RAMP","701.2"

"47.000","TON","HOT MIX ASPHALT SIDEWALK OR DRIVEWAY","702."

"1.000","LS","SCHEDULE OF OPERATIONS (TYPE C) - FIXED PRICE $70500","722.3"

"6.000","EA","SIGN REMOVED AND RESET","734."

"24.000","MO","ENGINEER'S FIELD OFFICE AND EQUIPMENT (TYPE A)","740."

"1.000","LS","MOBILIZATION","748."

"210.000","FT","SEDIMENT CONTROL BARRIER","767.121"

"3.000","EA","ELECTRIC MANHOLE ADJUSTED","811.36"

"765.000","HR","ROADWAY FLAGGER","850.41"

"249.000","DAY","TRAFFIC CONES FOR TRAFFIC MANAGEMENT","851.1"

"2000.000","SF","SAFETY SIGNING FOR TRAFFIC MANAGEMENT","852."

"370.000","FT","TEMPORARY PEDESTRIAN BARRICADE","852.11"

"1.000","EA","TEMPORARY PEDESTRIAN CURB RAMP","852.12"

"4.000","EA","PORTABLE BREAKAWAY BARRICADE TYPE III","853.1"

"460.000","FT","TEMPORARY BARRIER (TL-2)","853.2"

"311.000","DAY","TRUCK MOUNTED ATTENUATOR","853.403"

"356.000","DAY","TEMPORARY ILLUMINATION FOR WORK ZONE","853.8"

"1300.000","FT","TEMPORARY PAVING MARKINGS - 6 INCH (PAINTED)","854.016"

"500.000","SF","PAVEMENT MARKING REMOVAL","854.1"

"299.000","DAY","TEMPORARY PORTABLE RUMBLE STRIP","854.6"

"244.000","DAY","ARROW BOARD (TYPE C)","856.096"

"378.000","DAY","PORTABLE CHANGEABLE MESSAGE SIGN","856.12"

"1513.000","DAY","REFLECTORIZED DRUM","859."

"315.000","DAY","REFLECTORIZED DRUMS WITH SEQUENTIAL FLASHING WARNING LIGHTS","859.1"

"5335.000","FT","6 INCH RECESSED WHITE LINE (MC, UFD, WR)","862.406"

"5337.000","FT","6 INCH RECESSED YELLOW LINE (MC, UFD, WR)","863.406"

"36.000","CY","5000 PSI, 3/4 INCH, 685 HP CEMENT CONCRETE","904.3"

"31.000","CY","5000 PSI, 3/8 INCH, 710 HP CEMENT CONCRETE","905.2"

"403.000","SF","CEMENTITIOUS MORTAR FOR PATCHING","909.2"

"57.500","CY","RAPID HARDENING CONCRETE FOR REPAIRS","909.3"

"4865.000","LB","STEEL REINFORCEMENT FOR STRUCTURES - EPOXY COATED","910.1"

"225.000","SF","CLEAN (FULL REMOVAL) AND PAINT STRUCTURAL STEEL","961.2"

"1.000","LS","CLEAN (FULL REMOVAL) AND PAINT STEEL BRIDGE NO. N-23-026 (3Y2)","961.201" "1.000","LS","CLEAN (FULL REMOVAL) AND PAINT STEEL BRIDGE NO. N-23-027 (3Y3)","961.202" "1.000","LS","CLEAN (FULL REMOVAL) AND PAINT STEEL BRIDGE NO. N-23-034 (3Y4)","961.203" "1.000","LS","CLEAN (FULL REMOVAL) AND PAINT STEEL BRIDGE NO. M-18-042 (4AY)","961.204"

"60751.000","SF","ELASTOMERIC PROTECTIVE COATING","964.3"

"8200.000","SY","PENETRATING EPOXY SEALER TREATMENT ON BRIDGE DECKS","964.60"

"901.000","SF","MEMBRANE WATERPROOFING FOR BRIDGE DECK REPAIRS","966."

"9.000","EA","BRIDGE SCUPPER DRAINAGE PIPES","968.21"

"578.000","FT","PRE-COMPRESSED JOINT SEALER SYSTEM","973.2"

"96.000","SY","SPECIAL SLOPE PAVING UNDER BRIDGE REMOVED AND RESET","987.02"

"11681.000","SF","EXISTING PROTECTIVE SHIELDING REMOVED AND RESET","994.05"

"2997.000","SF","TEMPORARY PROTECTIVE SHIELDING","994.1"

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .