9-MAJOR SUBCONTRACTOR LISTING.pdf
PDF 38 KB Posted
- Attached to
- IFB - SLICK ROCK SUBSTATION CONSTRUCTION
- Solicitation number
- 26-283
- Issued by
- Washington County, Utah
About this file
This is a Major Subcontractor Listing form for the City of St. George's Slick Rock Substation Construction project. The document serves as a template for general contractors to identify major subcontractors and self-perform work assignments that will be utilized for the project. The form requires contractors to list subcontractor names, addresses, and contract amounts at the time of proposal submission. Contractors performing work directly must identify the responsible employee or foreman from their firm. The listing will subsequently function as a schedule of values for tracking and processing monthly progress payments throughout the construction period.
The form emphasizes that only subcontractors whose proposals are being utilized and who will perform the actual work should be listed. The document does not specify pricing requirements or set-asides, but rather functions as an administrative schedule. Contractors must include bid bonds equal to 5% of the total bid amount issued by surety companies licensed in Utah, with the City of St. George named as obligee. Additionally, 100% payment and performance bonds are mandatory for project completion. The City of St. George reserves the right to reject any or all proposals or waive any formality or technicality as deemed in the city's interest.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name: ________________________________________________________________
Reference No. ________________________________________________________________
Major Subcontractors Listing Mark amount "NA" if not applicable. Copy and Paste if additional sub-contractors are needed.
Provide only the subcontractor's name whose PROPOSAL was used and who will be doing the work for each area of work at the time proposal is due. Supplement also will become a schedule of values to check each monthly progress payment. General Contractor's listing themselves to self-perform work shall list the employee of their firm who will act as foreman for said work.
GENERAL CONTRACTOR:
Subcontractor Name: ____________________________________________________________ Subcontractor Address: __________________________________________________________ Amount: $________________________
SUB-CONTRACTOR: Choose an item.
Subcontractor Name: ____________________________________________________________ Subcontractor Address: __________________________________________________________ Amount: $
SUB-CONTRACTOR: Choose an item.
Subcontractor Name: ____________________________________________________________ Subcontractor Address: __________________________________________________________ Amount: $________________________
END OF SECTION
File details come from the government source that posted it. Updated .