2-2- BID TERMS.pdf
PDF 573 KB Posted
- Attached to
- IFB - SLICK ROCK SUBSTATION CONSTRUCTION
- Solicitation number
- 26-283
- Issued by
- Washington County, Utah
About this file
This is a Bid Terms document for the Slick Rock Substation Project submitted to the City of St. George, Utah (Reference No: 26-283). The project involves site preparation and construction including concrete foundations, transformer containment pads, a control building, access gates, and a precast perimeter wall. Bidders are required to furnish all labor, materials, equipment, permits, fees, and services necessary to complete the work in accordance with contract documents, drawings, and specifications. All work must be performed within a specified contract time period, subject to the City's approval regarding quality, suitability, and acceptability of materials and work fulfillment.
Liquidated damages are assessed at $250.00 per calendar day for each day the contractor fails to complete work within the contract time or any City-approved extension, and an additional $250.00 per day for failure to repair deficiencies within ten days of notification. A bid bond equal to 5% of the total bid amount, issued by a surety company licensed in Utah, must accompany each proposal. One hundred percent payment and performance bonds are required on this project. The City of St. George reserves the right to reject any or all proposals or waive any formality or technicality in its discretion.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID TERMS
Project Name: SLICK ROCK SUBSTATION PROJECT
Reference No: 26-283
Proposal of (“BIDDER"), organized and exisƟng under the laws of the State of doing business as a corporaƟon, partnership, or an individual (circle applicable status), to the City of St. George ("CITY"). Pursuant to and in compliance with the Public NoƟce, BIDDER hereby proposes to perform all Work for the above named Project in strict accordance with the Contract Documents, BIDDER'S InstrucƟons, Drawings, SpecificaƟons, and other documents related thereto, the undersigned, having familiarized themselves with the exisƟng condiƟons on the site and the condiƟons under which the work on the Drawings and in the SpecificaƟons is to be done, hereby proposes to furnish all labor, materials, equipment, incidental items, permits, fees, and services to perform all specified work on the above named project.
By submission of this BID, each BIDDER cerƟfies, and in the case of a joint BID each party thereto cerƟfies as to his own organizaƟon, that this BID has been arrived at independently, without consultaƟon, communicaƟon, or agreement as to any maƩer relaƟng to this BID with any other BIDDER or with any compeƟtor.
All Work shall be in strict accordance with the Contract Documents and documents issued thereto and shall be installed at the price/prices set forth in the Contract Documents. Bidder acknowledges that all Work shall be done subject to CITY’S approval. Decisions and quesƟons as to the quality, suitability, and acceptability of the materials, interpretaƟon of drawings and specificaƟons, and acceptable fulfillment of the Contract by the BIDDER shall be made by CITY.
Of parƟcular importance to be considered in the BID are the following:
CONTRACT TIME AND LIQUIDATED DAMAGES
The WORK is to be performed within the specified CONTRACT TIME. If the CONTRACTOR shall fail to complete the WORK within the CONTRACT TIME, or extension of Ɵme granted by the CITY, then the CONTRACTOR will pay the CITY LIQUIDATED DAMAGES assessed at the rates established as follows:
a. $250.00 (dollars) per day for each calendar day that the CONTRACTOR shall be in default aŌer the CONTRACT TIME.
b. $250.00 (dollars) per day for failure to make repairs to deficiencies in the work within 10 days of noƟficaƟon to repair.
The rates specified in ‘b.’ above are cumulaƟve and are in addiƟon to LIQUIDATED DAMAGES assessed in associaƟon with the overall Contract Time as listed in ‘a.’ above. AddiƟonal informaƟon on LIQUIDATED DAMAGES is provided in the GENERAL CONDITIONS.