This document is an Exhibit C.1 Project Description for the University Medical Center of El Paso (UMC) 2025 Bond Implementation Program, detailing seven distinct expansion and renovation projects across the UMC Main Campus. The proposed projects include expanding surgical services for both UMC and El Paso Children's Hospital, adding two new cardiac catheterization procedure rooms, upgrading interior finishes in the Thomason Tower, renovating dietary facilities, creating a new 23-bed ICU and Burn Center, relocating endoscopy services, and renovating the 8th floor of Thomason Tower to accommodate 25 observation bedrooms. The projects are part of a comprehensive campus improvement initiative, with construction documents for some projects scheduled to be issued for bid in Summer 2025.
The related state and local contract opportunity is a Request for Qualifications (RFQ) seeking an Activation and Occupancy Planner to support the UMC 2025 Bond Implementation Projects. The selected firm will work under the direction of the Assistant Administrator of Planning Design and Construction, with the ultimate goal of providing comprehensive planning services for the campus improvements. The selection will be made at UMC's sole discretion, evaluating proposals based on best value to the organization. The project is located in Texas and is being pursued by the El Paso County Hospital District, demonstrating a strategic approach to modernizing and expanding medical infrastructure in the region.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 7-Exhibit A Owner and Consultant Agreement 1.docx | DOCX document | |
| 1-EXHIBIT E Reimbursable Expense Maximum Values.docx | DOCX document | |
| 6-Exhibit C.2 Project Descriptions Off Campus.docx | DOCX document | |
| 2-EXHIBIT F Insurance Requirements.docx | DOCX document | |
| 8-Exhibit D.1 Preliminary Bond Project Schedules Main Campus.xlsx | XLSX spreadsheet | |
| 3-Exhibit B Scope of Services.docx | DOCX document | |
| 5-Exhibit D.2 Preliminary Bond Project Schedules Off Campus.xlsx | XLSX spreadsheet | |
| 4-950-09-25-021 Activation Occupancy Planner.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit C.1 – Project Descriptions UMC Main Campus University Medical Center of El Paso UMC 2025 Bond Implementation Program
1. Expand UMC Surgical Services Project Description: Expand UMC Surgery to include three Operating Rooms (including Hybrid, Burn, General OR) north of the existing Surgical Department; Renovate portions of existing Surgery to expand Pre-Op and PACU units.
Preliminary Concept:
2. Expand El Paso Children’s Hospital Surgical Services Project Description: Expand EPCH Surgery to include a two-story addition including first floor shell space and a Hybrid OR on the second floor.
Preliminary Concept:
3. Expansion of Cardiac Catheterization Services Project Description: Provide two new Cardiac Cath procedure rooms and relocate smaller modalities (e.g. EKG, Echo and office spaces) to adjacent areas.
Preliminary Concept:
Assumed Scope:
- Move outpatient imaging across the hall into vacant western Texas Tech offices (red rectangle)
- Reconfigure Imaging & Nuc. Med (upper red area) to add 2 Cath Labs
- Move Imaging Admin spaces across the hall to vacant blue area; include Medical Staff Lounge from 8
- Expand Recovery to accommodate additional Cath Lab patients
4. Expand Facility Lifespan
1. Thomason Tower 3rd & 4th Floor Interior Finish Upgrades Current finishes including wall, floor, millwork are outdated and will be upgraded to reflect the UMC Interior Standards that were incorporated in the recent renovations of Thomason Tower floors 5, 6 & 7.
1. Dietary Renovations Replacement of the obsolete dishwasher including physical separation between “clean” and “dirty” operations. Additional opportunities include finish upgrades of the dining areas and line-service areas.
5. New 23 Bed ICU & Burn Center Project Description: Renovate 3rd Floor North Tower for 23 Intensive Care Bedrooms.
Design Concept
6. Relocate Endoscopy Project Description: Relocate Endoscopy from North Tower Third Floor to First Floor.
Design Concept
7. Renovate Thomason Tower 8th Floor to accommodate 25 Observation Bedrooms Project Description: Leo A Daly is the Architect of Record and Construction Documents are scheduled to be issued for Bid in Summer 2025.
Design Concept:
image3.png image4.jpeg image5.png image6.png image1.png image2.png