This document is a detailed Existing Utilities and Demolition Plan (Landside) for the Flagler Executive Airport project, prepared by GAI Consultants. The plan provides a comprehensive schematic of existing infrastructure, utility locations, and demolition requirements for the General Aviation Terminal Building construction. The drawing includes specific instructions for removing and protecting various utility structures such as electric services, fiber optic lines, storm pipes, sanitary sewer lines, water mains, and communication infrastructure. The plan emphasizes the contractor's responsibility to coordinate directly with utility providers like Florida Power and Light (FPL), Brighthouse/Spectrum Communications, and local authorities to ensure proper demolition, protection, and potential relocation of existing utilities.

The plan contains extensive notes detailing the contractor's responsibilities, including submitting termination and service modification requests to applicable utility providers, maintaining service to existing tenants throughout construction, and implementing temporary measures to prevent service interruptions. The document highlights the complexity of the project, requiring careful coordination with multiple utility owners and infrastructure stakeholders. The contractor must take extreme caution when working near existing infrastructure, particularly the sewer line crossing, and is responsible for any damages to existing facilities. The plan also references additional documentation, such as the SJRWMD ERP 76127-04 for stormwater management system details, indicating a comprehensive approach to infrastructure management during the airport terminal construction project.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ev ev et a/ c a/c a

AIRPORT ROAD

AVIATION DR.

TAXIWAY ALPHA

TAXIWAY ALPHA

AVIATION DRIVE

AIRPORT ROAD

RESTAURANT

TAXIWAY A TAXIWAY A

AVIATION DRIVE

EXISTING TERMINAL BUILDING

CB

a/ c a/c

S

S

S

F / O U G

S

S

HANGAR

CORPORATE HANGAR

HANGAR

APRON

ENTERPRISE

RENT A CAR

ENTERPRISE PARKING

CAR WASH

SHELTER

SPECIAL NOTE: CONTRACTOR

TO TAKE EXTREME CAUTION

WHEN WORKING NEAR EXISTING

SEWER LINE CROSSING. SEWER

LINE TO BE PROTECTED.

A1

SCALE: 1"=40'

EXISTING UTILITIES AND DEMOLITION PLAN (LANDSIDE)

A1

SCALE: NOT TO SCALE

SHEET NOTES

SCALE: 1" = 40'

40 8040

1. ALL EXISTING UTILITIES SERVICING EXISTING FACILITIES SHALL BE MAINTAINED BY THE CONTRACTOR

THROUGHOUT CONSTRUCTION BY WHATEVER MEANS NECESSARY. THESE OPTIONS MAY INCLUDE,

BUT ARE NOT LIMITED TO, PROTECTION IN PLACE OF EXISTING UTILITIES, INSTALLATION OF TEMPORARY UTILITIES AT NO ADDITIONAL COST TO THE OWNER OR TENANT, OR ALTERATIONS TO THE PLANS OR PHASING, APPROVED BY THE ENGINEER, TO FACILITATE UNINTERRUPTED UTILITY

SERVICE TO THE OWNER AND/OR TENANT. ALL PLANNED UTILITY INTERRUPTIONS SHALL BE

SCHEDULED WITH A MINIMUM 1 WEEK NOTICE AND SHALL BE APPROVED BY THE ENGINEER, OWNER, AND TENANT. UNPLANNED INTERRUPTIONS TO UTILITY SERVICES SHALL BE SUBJECT TO LIQUIDATED

DAMAGES AS SPECIFIED IN THE CONTRACT DOCUMENTS OR $1,000 PER DAY, WHICHEVER IS

GREATER.

2. THE UTILITIES SHOWN ON THESE PLANS ARE A COMBINATION OF INFORMATION OBTAINED DURING

THE TOPOGRAPHIC SURVEY AND RESEARCH OF AS-BUILTS AND RECORD DRAWINGS PROVIDED BY

THE AIRPORT. THE ACTUAL LOCATIONS OF UTILITIES WITHIN THE PROJECT LIMITS MAY VARY AND IT SHALL BE THE SOLE RESPONSIBILITY OF THE CONTRACTOR TO LOCATE/IDENTIFY/MARK-OUT ALL EXISTING UTILITIES WITHIN THE LIMITS OF THE PROJECT AND IN THE VICINITY OF THE PROJECT

LIMITS AS NECESSARY FOR THE COMPLETION OF THE WORK. FAILURE TO DEMONSTRATE A

SATISFACTORY LEVEL OF DUE DILIGENCE IN UTILITY RESEARCH AND LOCATION SHALL RESULT IN THE CONTRACTOR'S FORFEITURE OF LOST TIME AND FINANCIAL CLAIMS DUE TO UTILITY SERVICE INTERRUPTIONS. A SATISFACTORY LEVEL OF DUE DILIGENCE SHALL INCLUDE, AT A MINIMUM; UTILITY

LOCATES FROM ALL KNOWN SERVICE PROVIDERS (FPL, AT&T, FLAGLER COUNTY, AND

BRIGHTHOUSE/SPECTRUM); SOFT DIGS/HAND DIGS IN CONFLICT AREAS OR “HOT SPOTS”; AND

NON-INVASIVE SUBTERRANEAN EXPLORATION WHEN DEEMED NECESSARY BY THE ENGINEER. IF THE ENGINEER HAS AGREED, IN WRITING, THAT A SATISFACTORY LEVEL OF DUE DILIGENCE HAS BEEN

COMPLETED, AND THE CONTRACTOR PROCEEDS WITH WORK AND EXCAVATION IN ACCORDANCE

WITH THE CONTRACT DOCUMENTS, DISCOVERY AND/OR DAMAGE TO EXISTING UNKNOWN UTILITIES

SHALL BE HANDLED IN ACCORDANCE WITH THE CONTRACT.

A2

SCALE: NOT TO SCALE

KEYED NOTES AND SHEET LEGEND

REMOVE EXISTING OVERHEAD ELECTRIC SERVICE, BURIED FIBER OPTIC

CABLE, WATER SERVICE LINE, STORM PIPE, OR SANITARY SEWER LINE.

REMOVE EXISTING UTILITY STRUCTURE

REMOVE EXISTING STORM STRUCTURE

1. LIMIT OF ELECTRICAL DEMOLITION AND REINSTALLATION SHALL BE

DETERMINED BY FLORIDA POWER AND LIGHT (FPL). IT IS THE

RESPONSIBILITY OF THE CONTRACTOR TO COORDINATE DIRECTLY

WITH FPL REGARDING UTILITY DEMOLITION AND NEW UTILITY

INSTALLATIONS.

2. REMOVE EXISTING UTILITY POLE. COORDINATE DEMOLITION WITH

FLORIDA POWER AND LIGHT (FPL). IT IS THE RESPONSIBILITY OF THE

CONTRACTOR TO COORDINATE DIRECTLY WITH FPL REGARDING

UTILITY DEMOLITION AND NEW UTILITY INSTALLATIONS.

3. REMOVE EXISTING STORM STRUCTURE

4. REMOVE EXISTING SANITARY MANHOLE. EXISTING SANITARY SEWER

PIPE TO REMAIN SHALL BE PROTECTED IN PLACE FOR RECONNECTION

5. REMOVE EXISTING 2" WATER SERVICE CONNECTION. CONNECTION

SHALL REMAIN IN PLACE UNTIL SERVICE CONNECTION TO NEW WATER

MAIN HAS BEEN COMPLETED.

6. REMOVE EXISTING BURIED FIBER OPTIC CABLE. COORDINATE

DEMOLITION WITH BRIGHTHOUSE/SPECTRUM COMMUNICATIONS.

7. REMOVE EXISTING OVERHEAD ELECTRIC SERVICE. COORDINATE

DEMOLITION WITH FLORIDA POWER AND LIGHT (FPL). IT IS THE

RESPONSIBILITY OF THE CONTRACTOR TO COORDINATE DIRECTLY

WITH FPL REGARDING UTILITY DEMOLITION AND NEW UTILITY

INSTALLATION.

8. REMOVE EXISTING 8" SANITARY SEWER.

9. EXISTING UTILITY POLE TO REMAIN SHALL BE PROTECTED IN PLACE.

10. EXISTING 12" WATER MAIN TO REMAIN SHALL BE PROTECTED IN PLACE.

11. EXISTING BRIGHTHOUSE/SPECTRUM BURIED FIBER OPTIC TO REMAIN

SHALL BE PROTECTED IN PLACE.

12. EXISTING SANITARY SEWER MANHOLE TO REMAIN SHALL BE

PROTECTED IN PLACE DURING DEMOLITION OF EXISTING SANITARY

SEWER PIPE. EXISTING STRUCTURE SHALL BE MODIFIED AS NEEDED

FOR INSTALLATION OF NEW SANITARY SEWER PIPE.

13. EXISTING 8" SANITARY SEWER TO REMAIN SHALL BE PROTECTED IN

PLACE.

14. EXISTING SANITARY SEWER MANHOLE TO REMAIN SHALL BE

PROTECTED IN PLACE.

15. EXISTING COMM. HAND HOLE TO BE REMOVED. CONTRACTOR TO FIELD

LOCATE EXISTING CABLES AND PROVIDE LOCATIONS TO THE

ENGINEER. THE CONTRACTOR SHALL BE REQUIRED TO PROVIDE

TEMPORARY INSTALLATION FOR EXISTING TENANTS AND EXISTING

BUILDINGS. THE CONTRACTOR SHALL COORDINATE DIRECTLY WITH

THE UTILITY OWNER PRIOR TO REMOVING, RELOCATING,

DEMOLISHING, OR INSTALLING ANY NEW OR TEMPORARY

INFRASTRUCTURE.

16. REMOVE EXISTING STORM PIPE, (TYP.)

17. LIMIT OF POTABLE WATER MAIN DEMOLITION. CONTRACTOR SHALL BE

RESPONSIBLE FOR PROTECTING EXISTING WATER LINE TO REMAIN IN

PLACE, AND FOR PREPARATIONS AND PRECAUTIONS NECESSARY TO

FACILITATE THE CONNECTION TO NEW POTABLE WATER MAIN.

18. CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO ENSURE

THAT EXISTING FOUNDATIONS, SIDEWALK, PARKING AREAS, ETC. ARE

NOT UNDER-MINED BY THE REMOVAL AND DEMOLITION OF EXISTING

STORM DRAIN PIPE OR STORM DRAIN STRUCTURES. DAMAGE TO

EXISTING FACILITIES TO REMAIN SHALL BE REPAIRED BY THE

CONTRACTOR AT NO ADDITIONAL COST TO THE OWNER.

19. SEE SITE PLAN FOR FENCE DEMOLITION.

20. REMOVE EXISTING 12" WATER MAIN. SERVICE CONNECTIONS TO

EXISTING TERMINAL BUILDING SHALL REMAIN IN PLACE DURING

CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR

PROVIDING TEMPORARY MEASURES OR INSTALLATIONS AS NEEDED

TO PROVIDE WATER SERVICE TO EXISTING TENANTS AND BUILDINGS

THROUGHOUT THE PROJECT.

21. REMOVE EXISTING HYDRANT AND BOLLARDS.

22. SEE CIVIL DEMO PLANS FOR LIMITS OF SIDEWALK AND BUILDING

DEMOLITION.

23. REMOVE EXISTING STORM PIPE AND MITERED END SECTIONS.

24. LOCATION AND EXTENT OF BURIED FIBER OPTIC LINES SHALL BE

COORDINATED BY THE CONTRACTOR DIRECTLY WITH

BRIGHTHOUSE/SPECTRUM.

25. EXISTING 6" SANITARY SEWER, PROTECT IN PLACE. CAP AT END FOR

FUTURE CONNECTION. CONTRACTOR SHALL ENSURE THAT ALL

EXISTING SANITARY SERVICE LATERALS ARE MAINTAINED

THROUGHOUT THE CONSTRUCTION, AND SHALL PROVIDE TEMPORARY

SERVICE LINES IF THE CONSTRUCTION OPERATIONS CAUSE

INTERRUPTIONS TO EXISTING INFRASTRUCTURE.

26. POTABLE WATER SERVICE TO EXISTING TENANTS SHALL BE

MAINTAINED THROUGHOUT THE PROJECT. CONTRACTOR SHALL BE

REQUIRED TO PROVIDE TEMPORARY WATER SERVICE AT NO

ADDITIONAL COST TO THE OWNER OR TENANT IF THE CONTRACTOR'S

WORK PHASING IS ANTICIPATED TO CAUSE AN INTERRUPTION OF

SERVICE.

27. EXISTING 2" WATER LINE TO REMAIN SHALL BE PROTECTED IN PLACE.

28. EXISTING SANITARY SEWER SHALL BE PROTECTED IN PLACE DURING

STORM PIPE AND STORM STRUCTURE REMOVAL. IF CONFLICTS

BETWEEN STORM AND SANITARY UTILITIES ARE ENCOUNTERED, IT

SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO CONSTRUCT

OR IMPLEMENT TEMPORARY MEASURES AS NEEDED.

29. REMOVE EXISTING SANITARY MANHOLE

30. EXISTING STORM CATCH BASIN TO REMAIN SHALL BE PROTECTED IN

PLACE

31. EXISTING STORM PIPE TO REMAIN SHALL BE PROTECTED IN PLACE.

EXISTING DRAINAGE

CANAL TO EAST POND

SYSTEM. SEE SJRWMD ERP

76127-04 FOR MORE INFO

REGARDING OVERALL

AIRPORT STORMWATER

MANAGEMENT SYSTEM

GENERAL UTILITY COORDINATION & RESPONSIBILITY NOTES:

· THE CONTRACTOR SHALL BE REQUIRED TO SUBMIT REQUESTS FOR TERMINATION,

NEW SERVICE REQUESTS, OR SERVICE MODIFICATION REQUESTS TO ALL APPLICABLE

UTILITY ENTITIES IN REGARDS TO THE WORK PROPOSED ON THIS PROJECT.

AFFECTED UTILITY PROVIDERS INCLUDE, BUT ARE NOT LIMITED TO, FPL, AT&T,

BRIGHTHOUSE/SPECTRUM, AND FLAGLER COUNTY.

· EACH UTILITY PROVIDER RESERVES THE RIGHT TO MAKE ADJUSTMENTS TO THE

PLANS AND SPECIFICATIONS SHOWN IN THE CONTRACT AS NEEDED TO BEST

ACCOMMODATE THE SPECIFIC SITE CONDITIONS AND THE SPECIFIC DETAILS OF THEIR

EXISTING AND PROPOSED UTILITY INFRASTRUCTURE.

· CHANGES TO THE OVERALL MEANS AND METHODS NECESSARY TO ACCOMPLISH THE

SCOPE OF WORK ARE EXPECTED, AND SHALL NOT BE GROUNDS FOR CHANGE

ORDERS OR ADDITIONAL COMPENSATION, UNLESS CHANGES BY THE UTILITY

PROVIDERS REPRESENT A SIGNIFICANT CHANGE IN SCOPE OR DESIGN INTENT AS

AGREED UPON BY THE OWNER AND ENGINEER.

· THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING DIRECTLY WITH THE

UTILITY PROVIDERS TO DETERMINE THE DELINEATION OF SCOPE ITEMS RELATED TO

THE INSTALLATIONS AND DEMOLITION, AND THE CONTRACTOR SHALL BE

RESPONSIBLE FOR MAKING PAYMENTS TO UTILITY PROVIDERS FOR DESIGN,

ENGINEERING, AND MATERIALS COSTS ASSOCIATED WITH THE UTILITY IMPACTS.

gaiconsultants iafong Cloud http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ iafong Callout IN THE EVENT THAT ALTERNATE CONNECTOR ROAD OPTION IS SELECTED, THE CLOUDED DRAINAGE PIPES AND DRAINAGE STRUCTURE TO REMAIN.