About this file
This document is a detailed Existing Utilities and Demolition Plan (Landside) for the Flagler Executive Airport project, prepared by GAI Consultants. The plan provides a comprehensive schematic of existing infrastructure, utility locations, and demolition requirements for the General Aviation Terminal Building construction. The drawing includes specific instructions for removing and protecting various utility structures such as electric services, fiber optic lines, storm pipes, sanitary sewer lines, water mains, and communication infrastructure. The plan emphasizes the contractor's responsibility to coordinate directly with utility providers like Florida Power and Light (FPL), Brighthouse/Spectrum Communications, and local authorities to ensure proper demolition, protection, and potential relocation of existing utilities.
The plan contains extensive notes detailing the contractor's responsibilities, including submitting termination and service modification requests to applicable utility providers, maintaining service to existing tenants throughout construction, and implementing temporary measures to prevent service interruptions. The document highlights the complexity of the project, requiring careful coordination with multiple utility owners and infrastructure stakeholders. The contractor must take extreme caution when working near existing infrastructure, particularly the sewer line crossing, and is responsible for any damages to existing facilities. The plan also references additional documentation, such as the SJRWMD ERP 76127-04 for stormwater management system details, indicating a comprehensive approach to infrastructure management during the airport terminal construction project.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ev ev et a/ c a/c a
AIRPORT ROAD
AVIATION DR.
TAXIWAY ALPHA
TAXIWAY ALPHA
AVIATION DRIVE
AIRPORT ROAD
RESTAURANT
TAXIWAY A TAXIWAY A
AVIATION DRIVE
EXISTING TERMINAL BUILDING
CB
a/ c a/c
S
S
S
F / O U G
S
S
HANGAR
CORPORATE HANGAR
HANGAR
APRON
ENTERPRISE
RENT A CAR
ENTERPRISE PARKING
CAR WASH
SHELTER
SPECIAL NOTE: CONTRACTOR
TO TAKE EXTREME CAUTION
WHEN WORKING NEAR EXISTING
SEWER LINE CROSSING. SEWER
LINE TO BE PROTECTED.
A1
SCALE: 1"=40'
EXISTING UTILITIES AND DEMOLITION PLAN (LANDSIDE)
A1
SCALE: NOT TO SCALE
SHEET NOTES
SCALE: 1" = 40'
40 8040
1. ALL EXISTING UTILITIES SERVICING EXISTING FACILITIES SHALL BE MAINTAINED BY THE CONTRACTOR
THROUGHOUT CONSTRUCTION BY WHATEVER MEANS NECESSARY. THESE OPTIONS MAY INCLUDE,
BUT ARE NOT LIMITED TO, PROTECTION IN PLACE OF EXISTING UTILITIES, INSTALLATION OF TEMPORARY UTILITIES AT NO ADDITIONAL COST TO THE OWNER OR TENANT, OR ALTERATIONS TO THE PLANS OR PHASING, APPROVED BY THE ENGINEER, TO FACILITATE UNINTERRUPTED UTILITY
SERVICE TO THE OWNER AND/OR TENANT. ALL PLANNED UTILITY INTERRUPTIONS SHALL BE
SCHEDULED WITH A MINIMUM 1 WEEK NOTICE AND SHALL BE APPROVED BY THE ENGINEER, OWNER, AND TENANT. UNPLANNED INTERRUPTIONS TO UTILITY SERVICES SHALL BE SUBJECT TO LIQUIDATED
DAMAGES AS SPECIFIED IN THE CONTRACT DOCUMENTS OR $1,000 PER DAY, WHICHEVER IS
GREATER.
2. THE UTILITIES SHOWN ON THESE PLANS ARE A COMBINATION OF INFORMATION OBTAINED DURING
THE TOPOGRAPHIC SURVEY AND RESEARCH OF AS-BUILTS AND RECORD DRAWINGS PROVIDED BY
THE AIRPORT. THE ACTUAL LOCATIONS OF UTILITIES WITHIN THE PROJECT LIMITS MAY VARY AND IT SHALL BE THE SOLE RESPONSIBILITY OF THE CONTRACTOR TO LOCATE/IDENTIFY/MARK-OUT ALL EXISTING UTILITIES WITHIN THE LIMITS OF THE PROJECT AND IN THE VICINITY OF THE PROJECT
LIMITS AS NECESSARY FOR THE COMPLETION OF THE WORK. FAILURE TO DEMONSTRATE A
SATISFACTORY LEVEL OF DUE DILIGENCE IN UTILITY RESEARCH AND LOCATION SHALL RESULT IN THE CONTRACTOR'S FORFEITURE OF LOST TIME AND FINANCIAL CLAIMS DUE TO UTILITY SERVICE INTERRUPTIONS. A SATISFACTORY LEVEL OF DUE DILIGENCE SHALL INCLUDE, AT A MINIMUM; UTILITY
LOCATES FROM ALL KNOWN SERVICE PROVIDERS (FPL, AT&T, FLAGLER COUNTY, AND
BRIGHTHOUSE/SPECTRUM); SOFT DIGS/HAND DIGS IN CONFLICT AREAS OR “HOT SPOTS”; AND
NON-INVASIVE SUBTERRANEAN EXPLORATION WHEN DEEMED NECESSARY BY THE ENGINEER. IF THE ENGINEER HAS AGREED, IN WRITING, THAT A SATISFACTORY LEVEL OF DUE DILIGENCE HAS BEEN
COMPLETED, AND THE CONTRACTOR PROCEEDS WITH WORK AND EXCAVATION IN ACCORDANCE
WITH THE CONTRACT DOCUMENTS, DISCOVERY AND/OR DAMAGE TO EXISTING UNKNOWN UTILITIES
SHALL BE HANDLED IN ACCORDANCE WITH THE CONTRACT.
A2
SCALE: NOT TO SCALE
KEYED NOTES AND SHEET LEGEND
REMOVE EXISTING OVERHEAD ELECTRIC SERVICE, BURIED FIBER OPTIC
CABLE, WATER SERVICE LINE, STORM PIPE, OR SANITARY SEWER LINE.
REMOVE EXISTING UTILITY STRUCTURE
REMOVE EXISTING STORM STRUCTURE
1. LIMIT OF ELECTRICAL DEMOLITION AND REINSTALLATION SHALL BE
DETERMINED BY FLORIDA POWER AND LIGHT (FPL). IT IS THE
RESPONSIBILITY OF THE CONTRACTOR TO COORDINATE DIRECTLY
WITH FPL REGARDING UTILITY DEMOLITION AND NEW UTILITY
INSTALLATIONS.
2. REMOVE EXISTING UTILITY POLE. COORDINATE DEMOLITION WITH
FLORIDA POWER AND LIGHT (FPL). IT IS THE RESPONSIBILITY OF THE
CONTRACTOR TO COORDINATE DIRECTLY WITH FPL REGARDING
UTILITY DEMOLITION AND NEW UTILITY INSTALLATIONS.
3. REMOVE EXISTING STORM STRUCTURE
4. REMOVE EXISTING SANITARY MANHOLE. EXISTING SANITARY SEWER
PIPE TO REMAIN SHALL BE PROTECTED IN PLACE FOR RECONNECTION
5. REMOVE EXISTING 2" WATER SERVICE CONNECTION. CONNECTION
SHALL REMAIN IN PLACE UNTIL SERVICE CONNECTION TO NEW WATER
MAIN HAS BEEN COMPLETED.
6. REMOVE EXISTING BURIED FIBER OPTIC CABLE. COORDINATE
DEMOLITION WITH BRIGHTHOUSE/SPECTRUM COMMUNICATIONS.
7. REMOVE EXISTING OVERHEAD ELECTRIC SERVICE. COORDINATE
DEMOLITION WITH FLORIDA POWER AND LIGHT (FPL). IT IS THE
RESPONSIBILITY OF THE CONTRACTOR TO COORDINATE DIRECTLY
WITH FPL REGARDING UTILITY DEMOLITION AND NEW UTILITY
INSTALLATION.
8. REMOVE EXISTING 8" SANITARY SEWER.
9. EXISTING UTILITY POLE TO REMAIN SHALL BE PROTECTED IN PLACE.
10. EXISTING 12" WATER MAIN TO REMAIN SHALL BE PROTECTED IN PLACE.
11. EXISTING BRIGHTHOUSE/SPECTRUM BURIED FIBER OPTIC TO REMAIN
SHALL BE PROTECTED IN PLACE.
12. EXISTING SANITARY SEWER MANHOLE TO REMAIN SHALL BE
PROTECTED IN PLACE DURING DEMOLITION OF EXISTING SANITARY
SEWER PIPE. EXISTING STRUCTURE SHALL BE MODIFIED AS NEEDED
FOR INSTALLATION OF NEW SANITARY SEWER PIPE.
13. EXISTING 8" SANITARY SEWER TO REMAIN SHALL BE PROTECTED IN
PLACE.
14. EXISTING SANITARY SEWER MANHOLE TO REMAIN SHALL BE
PROTECTED IN PLACE.
15. EXISTING COMM. HAND HOLE TO BE REMOVED. CONTRACTOR TO FIELD
LOCATE EXISTING CABLES AND PROVIDE LOCATIONS TO THE
ENGINEER. THE CONTRACTOR SHALL BE REQUIRED TO PROVIDE
TEMPORARY INSTALLATION FOR EXISTING TENANTS AND EXISTING
BUILDINGS. THE CONTRACTOR SHALL COORDINATE DIRECTLY WITH
THE UTILITY OWNER PRIOR TO REMOVING, RELOCATING,
DEMOLISHING, OR INSTALLING ANY NEW OR TEMPORARY
INFRASTRUCTURE.
16. REMOVE EXISTING STORM PIPE, (TYP.)
17. LIMIT OF POTABLE WATER MAIN DEMOLITION. CONTRACTOR SHALL BE
RESPONSIBLE FOR PROTECTING EXISTING WATER LINE TO REMAIN IN
PLACE, AND FOR PREPARATIONS AND PRECAUTIONS NECESSARY TO
FACILITATE THE CONNECTION TO NEW POTABLE WATER MAIN.
18. CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO ENSURE
THAT EXISTING FOUNDATIONS, SIDEWALK, PARKING AREAS, ETC. ARE
NOT UNDER-MINED BY THE REMOVAL AND DEMOLITION OF EXISTING
STORM DRAIN PIPE OR STORM DRAIN STRUCTURES. DAMAGE TO
EXISTING FACILITIES TO REMAIN SHALL BE REPAIRED BY THE
CONTRACTOR AT NO ADDITIONAL COST TO THE OWNER.
19. SEE SITE PLAN FOR FENCE DEMOLITION.
20. REMOVE EXISTING 12" WATER MAIN. SERVICE CONNECTIONS TO
EXISTING TERMINAL BUILDING SHALL REMAIN IN PLACE DURING
CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR
PROVIDING TEMPORARY MEASURES OR INSTALLATIONS AS NEEDED
TO PROVIDE WATER SERVICE TO EXISTING TENANTS AND BUILDINGS
THROUGHOUT THE PROJECT.
21. REMOVE EXISTING HYDRANT AND BOLLARDS.
22. SEE CIVIL DEMO PLANS FOR LIMITS OF SIDEWALK AND BUILDING
DEMOLITION.
23. REMOVE EXISTING STORM PIPE AND MITERED END SECTIONS.
24. LOCATION AND EXTENT OF BURIED FIBER OPTIC LINES SHALL BE
COORDINATED BY THE CONTRACTOR DIRECTLY WITH
BRIGHTHOUSE/SPECTRUM.
25. EXISTING 6" SANITARY SEWER, PROTECT IN PLACE. CAP AT END FOR
FUTURE CONNECTION. CONTRACTOR SHALL ENSURE THAT ALL
EXISTING SANITARY SERVICE LATERALS ARE MAINTAINED
THROUGHOUT THE CONSTRUCTION, AND SHALL PROVIDE TEMPORARY
SERVICE LINES IF THE CONSTRUCTION OPERATIONS CAUSE
INTERRUPTIONS TO EXISTING INFRASTRUCTURE.
26. POTABLE WATER SERVICE TO EXISTING TENANTS SHALL BE
MAINTAINED THROUGHOUT THE PROJECT. CONTRACTOR SHALL BE
REQUIRED TO PROVIDE TEMPORARY WATER SERVICE AT NO
ADDITIONAL COST TO THE OWNER OR TENANT IF THE CONTRACTOR'S
WORK PHASING IS ANTICIPATED TO CAUSE AN INTERRUPTION OF
SERVICE.
27. EXISTING 2" WATER LINE TO REMAIN SHALL BE PROTECTED IN PLACE.
28. EXISTING SANITARY SEWER SHALL BE PROTECTED IN PLACE DURING
STORM PIPE AND STORM STRUCTURE REMOVAL. IF CONFLICTS
BETWEEN STORM AND SANITARY UTILITIES ARE ENCOUNTERED, IT
SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO CONSTRUCT
OR IMPLEMENT TEMPORARY MEASURES AS NEEDED.
29. REMOVE EXISTING SANITARY MANHOLE
30. EXISTING STORM CATCH BASIN TO REMAIN SHALL BE PROTECTED IN
PLACE
31. EXISTING STORM PIPE TO REMAIN SHALL BE PROTECTED IN PLACE.
EXISTING DRAINAGE
CANAL TO EAST POND
SYSTEM. SEE SJRWMD ERP
76127-04 FOR MORE INFO
REGARDING OVERALL
AIRPORT STORMWATER
MANAGEMENT SYSTEM
GENERAL UTILITY COORDINATION & RESPONSIBILITY NOTES:
· THE CONTRACTOR SHALL BE REQUIRED TO SUBMIT REQUESTS FOR TERMINATION,
NEW SERVICE REQUESTS, OR SERVICE MODIFICATION REQUESTS TO ALL APPLICABLE
UTILITY ENTITIES IN REGARDS TO THE WORK PROPOSED ON THIS PROJECT.
AFFECTED UTILITY PROVIDERS INCLUDE, BUT ARE NOT LIMITED TO, FPL, AT&T,
BRIGHTHOUSE/SPECTRUM, AND FLAGLER COUNTY.
· EACH UTILITY PROVIDER RESERVES THE RIGHT TO MAKE ADJUSTMENTS TO THE
PLANS AND SPECIFICATIONS SHOWN IN THE CONTRACT AS NEEDED TO BEST
ACCOMMODATE THE SPECIFIC SITE CONDITIONS AND THE SPECIFIC DETAILS OF THEIR
EXISTING AND PROPOSED UTILITY INFRASTRUCTURE.
· CHANGES TO THE OVERALL MEANS AND METHODS NECESSARY TO ACCOMPLISH THE
SCOPE OF WORK ARE EXPECTED, AND SHALL NOT BE GROUNDS FOR CHANGE
ORDERS OR ADDITIONAL COMPENSATION, UNLESS CHANGES BY THE UTILITY
PROVIDERS REPRESENT A SIGNIFICANT CHANGE IN SCOPE OR DESIGN INTENT AS
AGREED UPON BY THE OWNER AND ENGINEER.
· THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING DIRECTLY WITH THE
UTILITY PROVIDERS TO DETERMINE THE DELINEATION OF SCOPE ITEMS RELATED TO
THE INSTALLATIONS AND DEMOLITION, AND THE CONTRACTOR SHALL BE
RESPONSIBLE FOR MAKING PAYMENTS TO UTILITY PROVIDERS FOR DESIGN,
ENGINEERING, AND MATERIALS COSTS ASSOCIATED WITH THE UTILITY IMPACTS.
gaiconsultants iafong Cloud http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ http://www.gaiconsultants.com/ iafong Callout IN THE EVENT THAT ALTERNATE CONNECTOR ROAD OPTION IS SELECTED, THE CLOUDED DRAINAGE PIPES AND DRAINAGE STRUCTURE TO REMAIN.
File details come from the government source that posted it. Updated .