8-Public Safety Headquarters Addendum 5.pdf

PDF 2 MB Posted

Attached to
2026-85 Standard Boarding Up of Commercial and Residential Properties Rebid
Solicitation number
Not on record
Issued by
Lehigh County, Allentown City, Pennsylvania

About this file

Public Safety Headquarters Addendum 5 – Allentown, Pennsylvania

Addendum No. 5 is a supplementary contract document issued by the City of Allentown's Department of Finance, Purchasing Office, dated May 27, 2026, modifying the bidding requirements for the Public Safety Headquarters renovation project. The addendum extends the questions due date to June 10, 2026, at 4:00 PM (submitted via PennBid) and shifts the bid opening from May 20, 2026, to June 24, 2026, at 1:00 PM at City Council Chambers, 435 Hamilton Street, Allentown, PA 18101. The project involves renovating the existing police station adjacent to City Hall with a four-story addition for expanded capacity, modernization of HVAC and electrical systems, and construction of a new pedestrian bridge connecting to the adjacent Allentown Parking Authority parking garage. The addendum incorporates revisions from project architects Alloy5 and construction manager Alvin H. Butz, Inc., including comprehensive updates to structural steel drawings, material specifications, and architectural details across 30 separate bid packages (2026-02 through 2026-30) covering sitework, demolition, concrete, masonry, structural steel, mechanical systems, electrical work, and specialty trades. A non-mandatory pre-bid meeting was held on May 18, 2026, at 9:00 AM with attendance sign-in required.

The addendum requires bidders to acknowledge receipt of all addenda on bid forms and submit a signed acknowledgment form with their proposals. All bidders must provide a bid bond equal to 10 percent of the bid value, with awarded contractors required to furnish performance bonds and labor/material payment bonds at 100 percent of contract value each. The project is subject to Pennsylvania prevailing wage requirements with certified payroll submissions mandated for on-site labor. Contractor personnel working within the operating police building must undergo criminal background checks and CJIS certification. The project will execute in three phases, with Phase 1 including demolition and the new four-story addition, Phase 2 consisting of renovations to the existing building's first and third levels, and Phase 3 completing renovation of remaining building spaces. Critical site logistics include closure of northbound Hamilton Street lanes during Phase 1 for crane operations and material delivery, with potential off-hour and holiday work required for pedestrian bridge demolition. The project uses the AIA A132 contract form, and no modification of contract terms is permitted; all clarifications must occur through the RFI (Request for Information) process via PennBid.

View the file

Other files

File Type Posted
5-2026-85 Form M1.pdf PDF
4-2026-85 Forms for Electronic Signature.pdf PDF
2-2026-85 Signature Page.pdf PDF
6-2026-85 Standard Board Up Rebid Final.pdf PDF
3-2026-85 Proposal Page.pdf PDF
4-Signature Page.pdf PDF
1-Bid 2026-45 Lehigh Parkway Staircase WPA Repair Phase 4.pdf PDF
2-BID 2026-45 PROPOSAL PAGE.pdf PDF
3-Forms For Submission.pdf PDF
7-Public Safety Headquarters Addendum 3.pdf PDF
28-2026-70 Allentown Police Headquarters Special Inspections Rebid.pdf PDF
16-2026-58 Allentown Police Headquarters Overhead Doors Rebid.pdf PDF
19-2026-61 Allentown Police Headquarters Equipment Specialties (Furnish Only) Rebid.pdf PDF
23-2026-65 Allentown Police Headquarters Testing Balancing (TAB) Rebid.pdf PDF
15-2026-57 Allentown Police Headquarters Doors Frames Hardware (Furnish Only) Rebid.pdf PDF
10-2026-52 Allentown Police Headquarters Sitework Excavation Site Demolition Rebid.pdf PDF
25-2026-67 Allentown Police Headquarters Telecommunications, Safety Security Rebid.pdf PDF
27-2026-69 Allentown Police Headquarters Final Cleaning Rebid.pdf PDF
9-Public Safety Headquarters Addendum 4.pdf PDF
12-2026-54 Allentown Police Headquarters Masonry Rebid.pdf PDF
13-2026-55 Allentown Police Headquarters Structural Steel Rebid.pdf PDF
22-2026-64 Allentown Police Headquarters Laboratory Casework Rebid.pdf PDF
6-Public Safety Headquarters Addendum 6.pdf PDF
11-2026-53 Allentown Police Headquarters Abatement Selective Demolition Rebid.pdf PDF
3-Attachments 1-5 Summary of Work, Prevailing Wages, PLA, NDA, AIA.pdf PDF
20-2026-62 Allentown Police Headquarters Miscellaneous Metals Rebid.pdf PDF
21-2026-63 Allentown Police Headquarters Casework (Furnish Only) Rebid.pdf PDF
14-2026-56 Allentown Police Headquarters Aluminum, Glass Glazing Rebid.pdf PDF
17-2026-59 Allentown Police Headquarters Elevators Rebid.pdf PDF
4-Public Safety Headquarters Addendum 2.pdf PDF
24-2026-66 Allentown Police Headquarters Electrical Rebid.pdf PDF
18-2026-60 Allentown Police Headquarters Building Specialties (Furnish Only) Rebid.pdf PDF
2-Attachments 1-3 Summary of Work, NDA, AIA.pdf PDF
26-2026-68 Allentown Police Headquarters Audio Visual Rebid.pdf PDF
5-Public Safety Headquarters Addendum 1.pdf PDF
2-2026-50 M1 Page.pdf PDF
1-2026-50 Forms for Electornic Submission.pdf PDF
4-2026-50 Demolition Services Final.pdf PDF
2-Bid 2026-48 FIFTEENTH STREET IMPROVEMENT PROJECT Final.pdf PDF
3-Bid 2026-48 Forms for Submission.pdf PDF
4-RFP 2026-49 Construction Inspection Management Services Final.pdf PDF
1-RFP 2026-49 Forms for Submission.pdf PDF
2-RFP 2026-49 Page M1.pdf PDF
26-2026-26 Allentown Police Headquarters Electrical.pdf PDF
17-2026-17 Allentown Police Headquarters Equipment Specialties (Furnish Only).pdf PDF
9-2026-09 Allentown Police Headquarters Aluminum, Glass Glazing.pdf PDF
21-2026-21 Allentown Police Headquarters Fire Protection.pdf PDF
1-General NDA for APD.pdf PDF
27-2026-27 Allentown Police Headquarters Telecommunications, Safety Security.pdf PDF
16-2026-16 Allentown Police Headquarters Building Specialties (Furnish Only).pdf PDF
Show 40 more

Latest 50 of 92 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sarrah McNeil Purchasing Agent

Purchasing Office

Department of Finance

435 Hamilton Street, Room 234

Allentown, PA 18101

Office: (610) 437-7500

Purchasing@allentownpa.gov

An Equal Opportunity Employer ● www.allentownpa.gov ● Hearing Impaired – TTY 610.437.7551 ● Printed on Recycled Paper

MAY 27, 2026

ADDENDUM NO. 5

BID PUBLIC SAFETY HEADQUARTERS

BID OPENING: JUNE 24, 2026, 1:00 PM

NOTIFICATION: THE PROVISIONS OF THIS ADDENDUM SHALL TAKE PRECEDENCE OVER

ALL OTHER CONTRACT DOCUMENTS WHENEVER THEY CONFLICT.

Please see attached an addendum being issued by the City of Allentown, Alloy5 (Attachment No. 1) and

Butz (Attachment No. 2) in regard to the bidding documents. The revisions can be found at the link previously provided.

Please see attached the sign-in sheet along with the Agenda from the Non-Mandatory Pre-Bid Meeting held on May 18, 2026, 9:00AM. (Attachment No. 3)

Please see attached the signed PLA. (Attachment No. 4)

Please note this addendum being issued updates the cover page for all packages to reflect an extension on the questions due date and extension of time for the bid opening. Please see below:

QUESTIONS DUE (DATE – PREVAILING TIME)

June 10, 2026, 4:00 PM

Submit All Questions via the “Ask a Question” feature in PennBid at https://pennbid.bonfirehub.com/, by the aforementioned date.

BID OPENING (DATE – PREVAILING TIME)

LOCATION: 435 HAMILTON STREET, ALLENTOWN, PA 18101: COUNCIL CHAMBERS

JUNE 24, 2026, 1:00 PM

Sincerely, In acknowledgement of your receipt and review of this addendum, please complete the form below and include it in the BID response prior to the public opening, as set forth above.

mailto:Purchasing@allentownpa.gov http://www.allentownpa.gov/ https://pennbid.bonfirehub.com/

ADDENDUM NO. 5

PUBLIC SAFETY HEADQUARTERS

An Equal Opportunity Employer ● www.allentownpa.gov ● Hearing Impaired – TTY 610.437.7551 ● Printed on Recycled Paper

May 27, 2026

To: Vendors

From: Sarrah McNeil

SUBJECT: ADDENDUM NO. 5

NOTE: THIS ADDENDUM SHOULD BE SIGNED AS ACKNOWLEDGMENT OF ITS RECEIPT

AND RETURNED WITH YOUR BID.

PLEASE COMPLETE FORM AND INCLUDE WITH PROPOSAL PAGES.

Company Name: ____________________________________________________________________

Signature: _________________________________________________________________________

Date: ______________________________________________________________________________

The following should be recognized as ADDENDUM NO. 5 to the aforementioned bid.

http://www.allentownpa.gov/

ATTACHMENT NO. 1

530 WEST BROAD STREET

BETHLEHEM, PA 18018

610.419.4055

WWW.ALLOY5.COM

City of Allentown

435 Hamilton St.

Allentown, PA 18101

May 22, 2026

Please find revised bidding documents for “Addendum 05” at the link previously provided.

DRAWINGS:

General note to be added to the following sheets: A1.10, A1.11, A1.12, A1.13, A1.20, A1.21, A1.22, A1.23, A1.40, A1.60, A1.61, A1.62, A1.63, A3.03, A4.00, A4.01, A4.02, A4.03, A4.04, A5.06, A5.40, A5.41, A5.42, A5.43, A7.03, A7.04, A8.00, A8.01

“WHERE EXPOSED, STRUCTURAL STEEL IN THE FOLLOWING INTERIOR LOCATIONS SHALL BE

A.E.S.S. ALL STEEL SHALL BE THOROUGHLY CLEANED IN ACCORDANCE WITH SSPC-SP3 PRIOR

TO COATING. LOCATIONS, AS NOTED ON DRAWINGS, ARE AS FOLLOWS: DECON. RM 005,

SALLYPORT 006, PASSAGE C001, STAIR 01 (ALL LEVELS), STAIR 04 (ALL LEVELS), VESTIBULE

100, COMPLAINT DESK PATROL OPEN OFFICE 102, CONFERENCE ROOM ‘3-1’ 317, & PEDESTRIAN

BRIDGE”

SHEET G0.00

1. Drawings S2.05 and A9.01 added to Drawing Index

SHEET C3.2

1. Landscape Wall #5 denoted

SHEET S0.00

1. CHANGE STEEL NOTES #7B as follows: CHANGE text mid-sentence to “Allowable loads on beams design for the given member.”

2. ADD DESIGN CRITERIA -SPECIAL LOAD: Add text “REFER TO DRAWINGS S2.05 FOR

BRIDGE DESIGN CRITERIA.”

SHEET S1.10

1. Change Section 2 Title: “MECHANICAL REMOTE FUEL TANK FOUNDATION PLAN”

2. In Section 3 Add text “Remote” and “17,000 Pounds”

SHEET S1.11

1. Add Plan Note #15. “REFER TO DRAWING SERIES MOMENT FRAME ELEVATIONS S2.0

THRU S2.04 FOR VERTICAL AND MOMENT BEAM END REACTIONS.”

2. Remove the STEEL CONNECTIION SCHEDULE AND MOMENT CONNECTION SCHEDULE with Footnotes from the sheet.

SHEET S1.12

1. Add Plan Note #15. “REFER TO DRAWING SERIES MOMENT FRAME ELEVATIONS S2.0

THRU S2.04 FOR VERTICAL AND MOMENT BEAM END REACTIONS.”

http://www.alloy5.com/

SHEET S1.13

1. Add Plan Note #14. “REFER TO DRAWING SERIES MOMENT FRAME ELEVATIONS S2.0

THRU S2.04 FOR VERTICAL AND MOMENT BEAM END REACTIONS.”

2. Remove the STEEL CONNECTIION SCHEDULE AND MOMENT CONNECTION SCHEDULE with Footnotes from the sheet.

3. Add Column Grid E.6 PRIME

4. Add Column Grid F PRIME

SHEET S1.14

1. Add Plan Note #9 to both plans. “REFER TO ELEVATIONS ON DRAWINGS S2.0 THRU S2.4

FOR BEAM END REACTIONS AT FRAME LINES FOR SHEAR AND MOMENT CONNECTION

DESIGNS.”

2. Remove the STEEL CONNECTIION SCHEDULE AND MOMENT CONNECTION SCHEDULE with Footnotes from the sheet.

3. At FRAMING PLAN – PED BRIDGE Add Steel Post at Grid F.1 - S2.3

4. At FRAMING PLAN - PARTIAL LEVEL 3 – Change 3 Beam sizes at F.1 Line and 4.1 Line

5. Add Column Grid E.6 PRIME to both plans.

6. Add Column Grid F PRIME to both plans.

SHEET S1.15

1. Add Plan Note #8 to both plans. “REFER TO DRAWING SERIES MOMENT FRAME

ELEVATIONS S2.0 THRU S2.4 FOR VERTICAL AND MOMENT BEAM END REACTIONS.”

2. Remove the STEEL CONNECTIION SCHEDULE AND MOMENT CONNECTION SCHEDULE with Footnotes from the sheet.

3. Add Column Grid E.6 PRIME

4. Add Column Grid F PRIME

SHEET S1.16

1. Add Plan Note #8. “REFER TO ELEVATIONS ON DRAWINGS S2.0 THRU S2.4 FOR BEAM

END REACTIONS AT FRAME LINES FOR SHEAR AND MOMENT CONNECTION DESIGNS.”

2. Remove the STEEL CONNECTIION SCHEDULE AND MOMENT CONNECTION SCHEDULE with Footnotes from the sheet.

3. Add Column Grid E.6 PRIME

4. Add Column Grid F PRIME

SHEET S1.17

1. Add ROOF FRAMING Plan Note #7. “REFER TO ELEVATIONS ON DRAWINGS S2.0 THRU

S2.4 FOR BEAM END REACTIONS AT FRAME LINES FOR SHEAR AND MOMENT CONNECTION

DESIGNS.”

2. Add UPPER ROOF FRAMING Plan Note #6. “REFER TO ELEVATIONS ON DRAWINGS S2.0

THRU S2.4 FOR BEAM END REACTIONS AT FRAME LINES FOR SHEAR AND MOMENT

CONNECTION DESIGNS.”

3. Remove the STEEL CONNECTIION SCHEDULE AND MOMENT CONNECTION SCHEDULE with Footnotes from the sheet.

4. Add Column Grid E.6 PRIME to the ROOF FRAMING PLAN.

5. Add Column Grid F PRIME to the ROOF FRAMING PLAN.

6. Change 5 Beam sizes at F.1, 2.1, and 6 Lines.

7. Change Beam sizes at Roof Framing Plan – Stair #1- 5 Line.

SHEET S2.00

1. Change Foot Notes at all Frame Elevations to be: “VERTICAL SHEAR AND MOMENT

REACTIONS ARE “SERVICE LEVEL” ASD VALUES.”

2. Add “SHEAR AND MOMENT VALUES WITH (4) Sub notes.

3. At 3 MOMENT FRAME ELEVATION – COLUMN LINE 2.3 – Change W21x93 Beam End

Reactions.

SHEET S2.01

1. Change Foot Notes at all Frame Elevations to be: “VERTICAL SHEAR AND MOMENT

REACTIONS ARE “SERVICE LEVEL” ASD VALUES.”

2. Add “SHEAR AND MOMENT VALUES WITH (4) Sub notes.

SHEET S2.02

1. Add “SHEAR AND MOMENT VALUES WITH (4) Sub notes.

SHEET S2.03

1. Change Foot Notes at all Frame Elevations to be: “VERTICAL SHEAR AND MOMENT

REACTIONS ARE “SERVICE LEVEL” ASD VALUES.”

2. Add “SHEAR AND MOMENT VALUES WITH (4) Sub notes.

3. At 1 MOMENT FRAME ELEVATION – COLUMN LINE B change (2) column sizes.

SHEET S2.04

1. Change Foot Notes at all Frame Elevations to be: “VERTICAL SHEAR AND MOMENT

REACTIONS ARE “SERVICE LEVEL” ASD VALUES.”

2. Add “SHEAR AND MOMENT VALUES WITH (4) Sub notes.

3. At 4 MOMENT FRAME ELEVATION – COLUMN LINE F.2 change (1) beam reaction value.

SHEET S2.05 (NEW SHEET)

1. Add Moment Frame Elevations E.6 Prime and F Prime.

2. Add Bridge KEY PLAN

3. Add PEDESTRIAN BRIDGE DESIGN CRITERIA AND DELEGATED CONNECTION DESIGN

NOTES.

SHEET S4.00

1. Modify Section 2. Add Wind Girt below Level 3 and Roof Framing connection to Curtain wall.

2. Modify Section 2. Modify Limestone supports at ramp.

SHEET S4.01

1. Modify Section 2. Add Tube Girt at Level 2 with plate. Modify masonry wall segment to be

6” reinforced.

2. At Section 2. Add beam to curtain wall connection. Add HSS tube below the Roof Framing

Elevation with plate.

SHEET S4.06

1. Modify Limestone shelf supports. Sections 3,4,5, 6 and 7.

SHEET S5.05

1. Modify title of TYPICAL DETAIL 9 to be: “TYPICAL MASONRY WALL OPENING

REINFORCEMENT LAYOUT.”

SHEET S6.00

1. Modify (2) Column sizes on B Line.

SHEET S6.01

1. Add Post Up Column at F.1 Line.

A1-10 - FLOOR PLAN - LEVEL 00

1. Concrete piers coordinated grid F.1 per revised structural drawings

2. City Hall parking garage exhaust plenum/ductwork updated on mechanical drawing background

A1-11 - FLOOR PLAN - LEVEL 01

1. Omitted EJ note

2. City Hall parking garage exhaust plenum/ductwork updated on mechanical drawing background

A1-12 - FLOOR PLAN - LEVEL 02

1. Column added grid F.1 per revised structural drawings, glazing tags updated

A1-13 - FLOOR PLAN - LEVEL 03

1. Column added grid F.1 per revised structural drawings, glazing tags updated

A1-50 - DESIGN SELECTION SUMMARY

1. TZT-01 thickness updated

2. Note FRP-03 omitted

A4-00 - WALL SECTIONS

1. WS1: Perimeter fire barrier system noted, continuous aluminum trim noted

2. WS1: Footings coordinated per revised structural drawings

3. WS4: Perimeter fire barrier system noted, continuous aluminum trim noted

A4-01 - WALL SECTIONS

1. WS6: Diagonal bracing coordinated per revised structural drawings

2. WS7: Footing coordinated per revised structural drawings

3. WS7: Curtain wall head and sill revised per updated structural drawings

A4-02 - WALL SECTIONS

1. WS8: Perimeter fire barrier system noted, continuous aluminum trim noted

2. WS8: Pedestrian ramp floor framing coordinated per revised structural drawings

A4-41 – DETAILS

1. Detail 6: Diagonal bracing coordinated per revised structural drawings

2. Detail 12: Pedestrian ramp floor framing coordinated per revised structural drawings

A5-01 - ENLARGED PLANS & DETAILS

1. Details 1&7: Pedestrian ramp floor framing coordinated per revised structural drawings

A5-05 - ENLARGED PLANS & DETAILS

1. FRP-03 revised to FRP-02 in interior elevations

A5-41 - PLAN DETAILS

1. Notes on window sill finishes revised

A5-42 - PLAN DETAILS

1. Notes on window sill finishes revised

2. Details 5&8: Coordinated structural column C/6

3. Detail 4&11: Coordinated structural column F/6

A5-43 - PLAN DETAILS

1. Notes on window sill finishes revised

2. Detail 8: Coordinated concrete pier per revised structural drawings

A6-21 - GLAZING ELEVATIONS

1. Details “BG2” & “BG7” revised per additional steel column added in revised structural drawings

A6-44 - GLAZING DETAILS

1. Detail BR3 clarified to include more components of fire barrier system

A6-45 - GLAZING DETAILS

1. Details BCW1 & BCW5: Curtain wall head and sill revised per updated structural drawings

A9-01 – MOCKUP (NEW SHEET)

SPECIFICATIONS:

New Specification Sections:

Section 08 3950 - FIRE RATED BULLET RESISTANT DOORS AND FRAMES

Section 08 4429 – SURFACE MOUNTED GLASS CANOPY SYSTEM

Section 08 8100 - FIRE-RATED GLASS

Section 08 8723 – SAFETY AND SECURITY WINDOW FILMS

Section 08 8853.30 - BR GLAZING - GLASS-CLAD NO POLY IGU - LOW SPALL – (OWIG)

Section 08 8853.45 - BR GLAZING - GLASS-CLAD NO POLY IGU - LOW SPALL – (BRIG)

Section 10 2239 - BULLET RESISTANT WALL PANELS

Revised Specification Sections - DELETE in their entirety and REPLACE with the revised and re-issued

Specification Sections:

Section 05 5000-REV1 – METAL FABRICATIONS-REV1

Section 05 7313 - ARCHITECTURAL GLASS RAILINGS- REV1

Section 08 8000 – GLAZING-REV1

Section 08 8050 - DICHROIC LAMINATED GLASS-REV1

Section 09 5000 - ACOUSTICAL CEILINGS-REV1

Section 09 5400 - SPECIALTY CEILINGS - ACT-04 - REV1

Section 09 5423 - METAL TORSION SPRING CEILING MPC-03-REV1

Modify Portions of Specification Sections as follows:

SECTION 05 1200

a. Section 2.1.A.1.a – REPLACE entry with the following sentence: Use Allowable Stress

Design; data are given at service-load level.

b. Section 2.10.B – Add 2. [SSPC-SP3, “Power Tool Cleaning” for exposed steel indicated on Architectural and/or Structural drawings to receive primed & finished paint coating.]

END OF ADDENDUM 05.

Jeffrey S. Gendell, AIA – Project Architect cc Wendy Silfies – Senior Project Manager, Alvin H. Butz Inc.

ATTACHMENT NO. 2

City of Allentown 435 Hamilton Street Allentown PA 18101

May 26, 2026

Ms. McNeil, Please find the revised bid documents for “Addendum #5” at the link previously provided.

DIVISION 00

00 01 15 LIST OF DRAWINGS (REVISED)

00 01 15-1 LIST OF SPECIFICATIONS

DIVISION 01

01 11 00 SUMMARY OF WORK (REVISED)

Wendy S Silfies Sr. Project Manager

Alvin H. Butz, Inc.

A Butz Family of Companies

ATTACHMENT NO. 3

CITY OF ALLENTOWN

PRE-BID CONFERENCE MEETING AGENDA

DATE/TIME: 9AM May 18, 2026

LOCATION: Allentown City Hall

435 Hamilton Street Allentown PA 18101

PROJECT: Public Safety Headquarters

INTRODUCTION

Owner – City of Allentown Allentown Police Department

Chief Charles Roca & Assistant Chief James Gress Purchasing Department

Sarrah McNeil & Danielle Ammary Finance Department Bina Patel

Construction Manager – Alvin H. Butz, Inc.

Wendy Silfies – Sr. Project Manager

Brad Vavra – Project Manager Dave Laitila - Superintendent Christ-Anigael – Project Engineer Ty Reed – Safety Director

Designers

Alloy5 Architects Jeff Gendell Reuther+Bowen Laura Eberly

CHA

Kevin Burns Nolan Zambelli Dean Batten

ATTENDANCE SIGN-IN IS REQUIRED – PLEASE SURE YOU HAVE SIGNED THE

ATTENDANCE SHEET AND PROVIDED THE REQUESTED INFORMATION

ALVIN H. BUTZ, INC.

840 HAMILTON STREET, SUITE 600

P.O. BOX 509

ALLENTOWN, PENNSYLVANIA 18105—0509

P 610-395-6871 F 610-395-3363 www.butz.com

ALVIN H. BUTZ, INC.

CONSTRUCTION MANAGER

PROJECT OVERVIEW

This project involves renovating the existing police station on Hamilton St. adjacent to City Hall.

The project includes a four-story addition for expanded capacity. Key upgrades include modernizing HVAC and electrical systems to improve efficiency, comfort, safety, and security.

The renovation aims to enhance functionality, support law enforcement operations, and meet the department’s growing needs for expansion. The addition incorporates new pedestrian bridge connected to the adjacent parking garage on College St., owned by the Allentown Parking Authority.

BID PACKAGES

2026-02 Allentown Police Headquarters Sitework, Excavation & Site Demolition 2026-03 Allentown Police Headquarters Abatement & Selective Demolition 2026-04 Allentown Police Headquarters Cast In Place Concrete 2026-05 Allentown Police Headquarters Masonry 2026-06 Allentown Police Headquarters Structural Steel 2026-07 Allentown Police Headquarters Carpentry & General Trades 2026-08 Allentown Police Headquarters Waterproofing & Roofing 2026-09 Allentown Police Headquarters Aluminum, Glass & Glazing 2026-10 Allentown Police Headquarters Doors, Frames & Hardware (Furnish Only) 2026-11 Allentown Police Headquarters Overhead Doors 2026-12 Allentown Police Headquarters Tile 2026-13 Allentown Police Headquarters Flooring 2026-14 Allentown Police Headquarters Painting 2026-15 Allentown Police Headquarters Elevators 2026-16 Allentown Police Headquarters Building Specialties (Furnish Only) 2026-17 Allentown Police Headquarters Equipment Specialties (Furnish Only) 2026-18 Allentown Police Headquarters Miscellaneous Metals 2026-19 Allentown Police Headquarters Casework (Furnish Only) 2026-20 Allentown Police Headquarters Laboratory Casework 2026-21 Allentown Police Headquarters Fire Protection 2026-22 Allentown Police Headquarters Plumbing 2026-23 Allentown Police Headquarters HVAC 2026-24 Allentown Police Headquarters Testing & Balancing (TAB) 2026-25 Allentown Police Headquarters Furniture 2026-26 Allentown Police Headquarters Electrical 2026-27 Allentown Police Headquarters Telecommunications, Safety & Security 2026-28 Allentown Police Headquarters Audio & Visual 2026-29 Allentown Police Headquarters Final Cleaning 2026-30 Allentown Police Headquarters Special Inspections

BIDDING PROCEDURES:

Obtaining Bidding Documents: The Bid Form, Front End Specifications, Plans, Surveys and other Contract Documents will be provided via link upon signature and submission of the non-disclosure agreement, available through PennBid, to Purchasing@alletownpa.gov. This link must be obtained through the PennBid/NDA to COA process.

Bid Due Date/Submission: Bids shall be submitted via PennBid by 9AM May 20, 2026 and will be electronically opened during a public opening located at 435 Hamilton Street, Allentown

PA 18101.

Documents Required to be Submitted with Bids:

COA

Signature Page A Bid Response Form Page B Contractors Qualification Statement Page C Work Experience Page D Equipment Page E Resident Preference Form Page F IBE Preference Form Page G MBE/WBE Subcontractors and Supplier Solicitation and Commitment Form Page M1 Political Disclosure Form Page H Public Works Employment Verification Form Page I Most Recent W-9 Form 00 11 54 Agreement of Surety 00 11 54 Letter of Insurer 00 45 19 Non-Collusion Affidavit

Bonds:

Bid Bond - All bidders shall provide a bid bond in the amount of 10% of the bid value

Performance and Materialman’s & Labor Bonds - The awarded contractors will be required to furnish both a Performance Bond and a Labor and Material Payment Bond for 100% of the contract value each, issued by a surety company satisfactory to the Owner and Construction Manager. The costs of the bond shall be included in the base bid.

A break out line item has been included on the bid form for the cost of the bond.

Bid Forms: Proposals must be submitted on the bid form included in the project manual. No other form of proposal will be accepted. Any alterations, additions, or deletions to the bid form may result in immediate rejection of the proposal.

Exceptions are not permitted and will result in no bid. All clarifications are to happen through the bid process RFI format. Qualification/clarification to bids is not acceptable. Fully executed and sealed COA signature forms, along with the bid forms must be submitted.

Post Bid Scope Review: Post bid scope review meetings will be held in the days immediately following the bid opening. Please plan to be available for attendance should your bid require a bid review meeting.

Sales Tax: City of Allentown

Form of Agreement: The AIA A132, a draft of which is included in the project manual, shall be used for these packages. By submitting a bid, bidders agree to execute said Contract without modification.

Specified Alternates: Alternates are specified on each bid form.

ALTERNATE #1 – Any work associated with Alternate 1: Remove existing finish and provide & install slate panels on the existing retaining wall along Hamilton Street as indicated on the drawings.

ALTERNATE #2 – Any work associated with Alternate 2: Remove existing built-up roof system on the existing Allentown Public Safety Headquarters building and replace it with the basically specified Thermoset Single-Ply EPDM roof system as indicated on the drawings.

ALTERNATE #3 –

Any work associated with Alternate 3: Remove existing glazing and provide UL rated ballistics glazing on the east elevation of the existing building as indicated on the drawings.

Voluntary Alternates: Voluntary Alternates can be specified on the bid form for discussion during Descope Meetings.

Unit Rates: Bid Forms include a section for unit rates. This form must be completed and accompany the bid submission, if additional unit pricing lists are requested, the list can be attached within PennBid.

Questions During Bidding: All questions shall be submitted via PennBid. Questions and answers will be part of a future addendum. The final date for Pre-Bid RFI submission will be May 7, 2026.

Addenda: Bidders must ensure that they acknowledge all Addenda in the spaces provided on the bid forms or risk being declared non-responsive.

DIVISION 00 & 01 REQUIREMENTS:

All Subcontractors are encouraged to read all sections of the Project Manual in great detail.

Section 00 50 00 Project Labor Agreement: Bidders shall be aware that signature and adherence to the project labor agreement, a draft of which is included in the project manual, shall be required.

Section 00 73 46 Wage Rate Determination: PA Prevailing wages shall be applied to this project. The wage determination is included in the project manual and all bids must comply with this requirement. Should a bid be awarded, certified payroll submission shall be required for all on-site labor.

Section 01 11 00 – Summary of Work: Bidders are advised to thoroughly review Section 01 11 00 – Summary of Work. Care should be taken to note both the items that apply to all bid packages as well as those that apply to individual specific bid packages.

SITE UTILIZATION PLANNING & SCHEDULE

Project Schedule: The preliminary project schedule is included in the bid documents. The project will take place in 3 separate phases. The first phase will include the demolition of the existing pedestrian bridge, sitework associated with the new four-story addition, completion of the new four-story addition, completion of the new pedestrian bridge from the new building to the APA Parking Garage, as well as the replacement of the existing elevator located in the existing police building which is currently out of order. The second phase of the project will take place as soon as the APD have occupied the new addition, and will consist of the abatement and renovations of the entire 3rd and 1st levels of the existing police building. The final phase, phase 3 shall complete the abatement and renovation of the existing police building once the remaining APD departments have moved into the newly renovated Phase 2 spaces. Therefore, multiple mobilizations and potential for material storage exist. Please review and be prepared to discuss during the post-bid review process.

Final project CPM schedule will be developed after award of the contracts based on each contractor’s schedule input.

Site Logistics: Site access will change several times during the process of the project. During Phase 1, the parking and North Bound lanes of Hamilton Street will be closed for construction.

These lanes will be required for the placement of the crane for steel erection, as well as for delivery of materials. Due to the lane closures, north bound traffic will be reduced to APA parking deck turns only at 4th and Linden Street. One lane of College Street will also be fenced for use by construction activities during Phase 1. The demolition of the existing pedestrian bridge cannot interrupt the entrance of vehicles to the APA parking deck for an extended period of time, so off-hour work or holiday weekend hours will likely be required for this work. The closure of the Hamilton Street lanes will end with the completion of Phase 1, however the lane of College Street will remain closed for construction purposes.

Phase 2 will require a shared entrance, for both construction personnel and police personnel, for the existing building, as the holding cells and CID departments will remain operational during this phase.

Critical Activities:

o Demolition of Existing Pedestrian Bridge o Relocation of Existing Emergency Generator o Support of Existing City Hall Plaza/Parking Structure during new building foundation work and tie-in o Existing Building Openings & Temporary Protections o Structural Steel Tie-Ins to Existing Building – Façade & Roof o New Pedestrian Bridge Installation & Tie-In to APA Parking Deck o Containment and Abatement in Existing Building o Steel, Decking & Concrete Infill in Existing Building o Installation of New Detention/Holding Cells – Specialty Construction Methods

Required

SECURITY & SAFETY

Security measures for the site are critical for this project. Temporary partitions between the operating police building and the new construction areas shall be constructed and maintained securely. construction personnel will be prohibited from entering the operating police building spaces without proper certification or police escort.

Background Checks & CJIS Certification: Contractor personnel who shall work within the existing police building during any phase of the construction will be required to undergo a criminal background check process, including fingerprinting. Completion of the CJIS certification will also be necessary for those personnel working inside the operating police spaces. APD will provide additional information for these processes upon contract award.

Site Specific Safety Manual is included in the bid documents.

REQUIRED AT ALL TIMES: High Vis clothing (shirts or vests) Hard Hats Safety Glasses Work Boots (Steel Toe or Composite)

On-Site Safety Orientation Training and Testing is mandatory for all persons entering the project site. Personnel shall receive a QR code to the training video and the required test, to be completed prior to coming to the project site.

Contractors must follow all OSHA, City of Allentown and Alvin H. Butz, Inc. regulations.

EXISTING BUILDING WALKTHROUGH PROCEDURES

A walkthrough of the existing police building will be held at the end of the pre-bid meeting.

Any bidders wishing to take part in the walkthrough must remain with a police escort throughout their time inside the police building. Access to the existing holding area will not be permitted.

ATTACHMENT NO. 4

Insert from: "Public Safety Headquarters Addendum 5 draft 3.pdf"
Public Safety Headquarters Addendum 5 draft.pdf
Public Safety Headquarters Addendum 5.pdf
ExtractPage1
Alloy5 - 2026-05-21 ADDENDUM 05.pdf
ExtractPage2
AHB Addendum 5.pdf
ExtractPage3
05.18.26 Pre-Bid Conference Sign In Sheet.pdf
COA PSH Pre-Bid Agenda.pdf

COA PSH Pre-Bid Agenda 5.18.26.pdf

File details come from the government source that posted it. Updated .