8-GE Final – CT Sim GE HealthCare Pre-Installation Manual Drawings.pdf
PDF 2 MB Posted
- Solicitation number
- 25/0286
- Issued by
- Harris County, Texas
About this file
This is a GE HealthCare pre-installation manual and technical drawing set for a CT (Computerized Tomography) scanner system being installed at Harris Health's Smith Clinic in Houston, Texas, as part of a renovation project. The document provides comprehensive technical specifications and site preparation requirements for the DISCOVERY RT CT system, including equipment layout, radiation protection specifications, structural requirements, HVAC specifications, and electrical installation guidelines. The gantry unit weighs 1,816 kg (4,004 lbs), the GT1700 table weighs 446 kg (984 lbs), and the system requires a maximum power demand of 150 kVA with an average continuous demand of 30 kVA at 380-480V, three-phase power. The installation encompasses two rooms: the exam room (S1122) measuring 24'-0" by approximately 16'-8", and the control room (S1124), with a finished floor-to-slab height of 15'-0" and false ceiling height of 9'-0". The document specifies that equipment delivery requires a minimum opening of 1400 mm by 2150 mm (55 in by 85 in), contingent on a 2438 mm (96 in) corridor width.
The pre-installation manual establishes comprehensive customer responsibilities for site preparation, including floor leveling tolerances of 6 mm (1/4 in) over 3,048 mm (10 ft), provision of structural supports for ceiling-mounted equipment, and concrete floor strength requirements of minimum f'c = 1.4 X10^7 Pa (2,000 PSI). Environmental specifications require ambient static magnetic fields less than 1 Gauss at the gantry and less than 10 Gauss at the operator console, with maximum gantry noise levels of 75 dBA at 1 meter distance. Temperature and humidity conditions must be maintained at 18-26°C (64-79°F) with 30-60% relative humidity for both exam and control rooms. The system generates maximum heat output of 8.96 kW (30,570 BTU/h) from the gantry and 0.3 kW (1,030 BTU/h) from the patient table. The document mandates that a qualified radiological physicist determine suitable radiation protection in accordance with local regulations, and all structural engineering for load-bearing elements supporting ceiling-mounted equipment is the customer's responsibility. GE HealthCare provides the Main Disconnect Panel, Partial UPS unit, Power Distribution Unit, gantry, table, console, and associated system components, while the customer must supply and install all structural supports, wall backing, electrical infrastructure, ductwork, grounding systems, and site preparation work.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 - C1 - Cover Sheet 02 - C2 - Disclaimer - Site Readiness Checklist 03 - A1 - General Notes 04 - A2 - Equipment Layout 05 - A3 - Radiation Protection 06 - A4 - Radiation Protection Details 07 - A5 - Equipment Dimensions (1) 08 - A6 - Equipment Dimensions (2) 09 - A6 - Delivery
Houston, TX
Kelly Martin
DISCOVERY RT
JM
GE HealthCare does not take responsibility for any damages resulting from changes on drawings made by others. Errors may occur by not referring to the complete set of final issue drawings. GE HealthCare cannot accept responsibility for any damage due to the partial use of GE HealthCare final issue drawings, however caused. All dimensions are in millimeters unless otherwise specified. Do not scale from printed pdf files. GE HealthCare accepts no responsibility or liability for defective work due to scaling from these drawings. /18CT-M447727-FIN-01-A.DWG
713-248-7733
Vinson.martin@gehealthcare.com
JM 5366636-1EN
United States of America
1/4"=1'-0"
5582312
23/Jun/2025
Harris Health Smith Clinic
REV DATE MODIFICATIONS
A 23/Jun/2025 Final (DC-482240)
A mandatory component of this drawing set is the GE HealthCare Pre Installation manual. Failure to reference the Pre Installation manual will result in incomplete documentation required for site design and preparation.
Pre Installation documents for GE HealthCare products can be accessed on the web at: https://www.gehealthcare.com/support/manuals -
Drawn by Verified by PIM Manual
SheetFormat
Concession
Scale DateFile Name
RevGON/Quote
A3
FINAL STUDY
10 - S1 - Structural Notes 11 - S2 - Structural Layout 12 - S3 - Structural Details (1)
13 - M1 - HVAC
14 - E1 - Electrical Notes 15 - E2 - Electrical Layout 16 - E3 - Electrical Elevations 17 - E4 - Power Requirements 18 - E5 - Electrical Details - Interconnect
GENERAL SPECIFICATIONS
· GE is not responsible for the installation of developers and associated equipment, lighting, cassette trays and protective screens or derivatives not mentioned in the order.
· The final study contains recommendations for the location of GE equipment and associated devices, electrical wiring and room arrangements. When preparing the study, every effort has been made to consider every aspect of the actual equipment expected to be installed.
· The layout of the equipment offered by GE, the dimensions given for the premises, the details provided for the pre-installation work and electrical power supply are given according to the information noted during on-site study and the wishes expressed by the customer.
· The room dimensions used to create the equipment layout may originate from a previous layout and may not be accurate as they may not have been verified on site. GE cannot take any responsibility for errors due to lack of information.
· Dimensions apply to finished surfaces of the room.
· Actual configuration may differ from options presented in some typical views or tables.
· If this set of final drawings has been approved by the customer, any subsequent modification of the site must be subject to further investigation by GE about the feasibility of installing the equipment. Any reservations must be noted.
· The equipment layout indicates the placement and interconnection of the indicated equipment components.
There may be local requirements that could impact the placement of these components. It remains the customer's responsibility to ensure that the site and final equipment placement complies with all applicable local requirements.
· All work required to install GE equipment must be carried out in compliance with the building regulations and the safety standards of legal force in the country concerned.
· These drawings are not to be used for actual construction purposes. The company cannot take responsibility for any damage resulting therefrom.
CUSTOMER RESPONSIBILITIES
· It is the responsibility of the customer to prepare the site in accordance with the specifications stated in the final study. A detailed site readiness checklist is provided by GE. It is the responsibility of the customer to ensure all requirements are fulfilled and that the site conforms to all specifications defined in the checklist and final study. The GE Project Manager of Installation (PMI) will work in cooperation with the customer to follow up and ensure that actions in the checklist are complete, and if necessary, will aid in the rescheduling of the delivery and installation date.
· Prior to installation, a structural engineer of record must ensure that the floor and ceiling is designed in such a way that the loads of the installed system can be securely borne and transferred. The layout of additional structural elements, dimensioning and the selection of appropriate installation methods are the sole responsibility of the structural engineer. Execution of load bearing structures supporting equipment on the ceiling, floor or walls are the customer's responsibility.
RADIO-PROTECTION
· Suitable radiological protection must be determined by a qualified radiological physicist in conformation with local regulations. GE does not take responsibility for the specification or provision of radio-protection.
DISCLAIMER
THE UNDERSIGNED, HEREBY CERTIFIES THAT I HAVE READ AND APPROVED THE PLANS IN THIS DOCUMENT.
DATE NAME SIGNATURE
· A mandatory component of this drawing set is the GE HealthCare Pre-installation manual. Failure to reference the Pre-installation manual will result in incomplete documentation required for site design and preparation.
· The items on the GE HealthCare Site Readiness Checklists listed below are REQUIRED to facilitate equipment delivery to the site. Equipment will not be delivered if these requirements are not satisfied.
CUSTOMER SITE READINESS REQUIREMENTS
REQUIRED MANUALS FOR SYSTEM PRE-INSTALLATION
Description Document Number*
Product specific Pre-installation Manual Refer to cover page
*documents can be accessed in multiple languages at https://www.gehealthcare.com/support/manuals
· Any deviation from these drawings must be communicated in writing to and reviewed by your local GE HealthCare installation project manager prior to making changes.
· Make arrangements for any rigging, special handling, or facility modifications that must be made to deliver the equipment to the installation site. If desired, your local GE HealthCare installation project manager can supply a reference list of rigging contractors.
· New construction requires the following;
1. Secure area for equipment,
2. Power for drills and other test equipment,
3. Restrooms.
· Provide for refuse removal and disposal (e.g. crates, cartons, packing)
· For CT systems it is required to minimize vibrations within the scan room. It is the customer's responsibility to contract a vibration consultant/engineer to implement site design modifications to meet the GE vibration specification. Refer to the system Pre-installation manual for vibration specifications.
REQUIRED SITE-READINESS CHECKLISTS FOR SYSTEM PRE-INSTALLATION
Modality Document Number*
Computerized Tomography DOC2949059
Radiology, Radiology and Fluouroscopy, Mammography, Bone Mass Densitometry DOC2949063
All modality Customer/Contractor Worksheet DOC2949068 *documents can be accessed in multiple languages at https://www.gehealthcare.com/support/manuals
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic Delivery - Disclaimer 02
ENVIRONMENT
ALTITUDE
· The system shall meet all functional and performance specifications when placed in a room that is at an elevation of -150 m to 2,400 m [-492 ft to 7,875 ft] above sea level. For different altitudes refer to the PIM.
MAGNETIC FIELD SPECIFICATIONS
· Limit the magnetic interference to guarantee specified imaging performance.
GANTRY:
· Ambient static magnetic fields less than 1 Gauss.
· Ambient AC magnetic fields less than 0.01 Gauss peak.
OPERATOR CONSOLE:
· Ambient static magnetic fields less than 10 Gauss.
SYSTEM COMPONENT NOISE LEVEL
· Maximum Gantry Audible Noise Level: The maximum ambient noise level is produced by the gantry during a CT scan acquisition. It is less than 75 dBA when measured at a distance of 1 m [3.3 ft] from the nearest gantry surface, in any direction.
· Maximum Console Audible Noise Level: The maximum ambient noise levels is less than or equal to 56 dBA when measured 1 m [3.3 ft] up and 1 m [3.3 ft] away from the console at an ambient temperature of 26°C [79°F].
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic Delivery - Disclaimer 03
BY ITEM DESCRIPTION
MAX
HEAT
OUTPUT
(BTU/h)
WEIGHT
(lbs)
MAX
HEAT
OUTPUT
(W)
WEIGHT
(kg)
A 1 GANTRY 30585 4004 8964 1816
A 2 GT1700 TABLE 1024 983 300 446
A 3 REAR CABLE COVER - - - -
A 4 PARTIAL UPS 2832 265 830 120
A 5 POWER DISTRIBUTION UNIT (PDU) 3412 816 1000 370
B 6 MAIN DISCONNECT PANEL (MDP) - 63 - 28.6
A 7 GE STORAGE CABINET - 150 - 68
A 8 AURORA SWS TABLE - 88 - 40
A 9 OPERATOR'S CHAIR - - - -
A 10 OPEN CONSOLE 8189 142 2400 64.2
A 11 ULRICH CT MOTION INJECTOR
CONTROL - 9 - 4
A 12 ULRICH CT MOTION INJECTOR ON
PEDESTAL - 174 - 79
E 13 LASER SYSTEM - - - -
E 14 TABLET PC FOR LASER - 2 - 1
E 15 INJECTOR ON CEILING - 79 - 36
E 16 INJECTOR CONTROL - 14 - 6.2
EXAM ROOM HEIGHT
FINISHED FLOOR TO SLAB HEIGHT
FALSE CEILING HEIGHT
15'-0"
9'-0"
C 17 LEAD GLASS WINDOW
C 18 MINIMUM OPENING FOR EQUIPMENT DELIVERY IS 1400 mm x 2150 mm [55 in x 85 in], CONTINGENT ON A 2438 mm [96 in] CORRIDOR WIDTH
LEGEND
A GE SUPPLIED D AVAILABLE FROM GE
B GE SUPPLIED/CONTRACTOR INSTALLED E EQUIPMENT EXISTING IN ROOM
C CUSTOMER/CONTRACTOR SUPPLIED AND
INSTALLED * ITEM TO BE REINSTALLED FROM
ANOTHER SITE
For Accessory Sales: (866) 281-7545 Options 1, 2, 1, 2 or mail to: gehcaccessorysales@ge.com
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic A2 - Equipment Layout 041/4"=1'-0"
16'-8"
8'-3"
9' -6
7'-11" 3'-0"
2' -2
EX
ST
1'
-7 5 8"
'-0
'-9
10 11
EXAM
ROOM
S1122
CONTROL
ROOM
S1124
4' -2
8'-3" 2'-5"
2' -5
3'
-1 1"
0.66
1.31
2.63
5.26
5.26
2.63
1.31
0.66
RADIATION PROTECTION LAYOUT
SHIELDING REQUIREMENTS SCALING
CHANGED PARAMETER (mAs) MULTIPLICATION FACTOR (new mAs/100)
80 kV 0.21
120 kV 0.71
140 kV 1.00 4x3.75 mm images 0.82
16x0.625 LD 8x1.25 LD Fluro 5 mm
0.59
4x1.25 LD 5 mm (1i) Fluro 2.5 mm
0.40
1x1.25 mm images 0.20
4x0.625 LD 1x1.25 0.10
SHIELDING REQUIREMENTS:
Engage a qualified radiological health physicist to review your scan room shielding requirements, taking into consideration:
· Scatter radiation levels within the scanning room
· Equipment placement
· Weekly projected work-loads (number of patients/day technique (kvp*ma))
· Materials used for construction of walls, floors, ceiling, doors, and windows
· Access to surrounding scan room areas
· Equipment in surrounding scan room areas (e.g., film developer, film storage)
The illustration on this page depicts measurable radiation levels within the scanning room while scanning a 32 cm CTDI phantom (body) with the technique shown:
- 140 kVA
- 100 mA
- 1 sec
- 4x5.00 mm
NOTE: All measurements have an accuracy of ± 20% because of measurement equipment, technique, and system-to-system variation. Use the correction factors shown in the table above to adjust exposure levels to the usual scan technique at your site.
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic A3 - Radiation Protection 051/4"=1'-0"
8'-3"
9' -6
EX
ST
1' -7
5 8"
EXAM
ROOM
S1122
CONTROL
ROOM
S1124
RADIATION SCATTER - BODY PHANTOM
Plan ViewElevation
APPROX.
50"0"
0.5 1.0m
5.26 2.63 1.31 0.66 μGy/scan
NOTE: 140 kV 100 mAs/scan 1 sec 4 x 5.00m scan acquisition
5.262.631.310.66
2.63 5.26
1.31 2.63
0.66 5.26
1.31 0.66 μGy/scan
RADIATION SCATTER - HEAD PHANTOM
Plan ViewElevation
APPROX.
50"0"
0.5 1.0m
NOTE: 140 kV 100 mAs/scan 1 sec 4 x 5.00m scan acquisition
0.66
1.31
2.63 2.63 1.31 0.66 0.33 μGy/scan
0.33
1.312.63 0.66
1.31 0.33
2.63 0.66
0.33 μGy/scan
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic A4 - Radiation Protection Details 061/4"=1'-0"
SCALE 1:20
TOP VIEWFRONT VIEW
AURORA SWS TABLE
Table weight: 40 kg [88 lbs]
[51 in]
[3 in
[3 in
[24 in]
[26 in]
[1 in ] 50
[2 in
] 74
[2 in
[3 in
OPERATOR CONSOLE
OPERATOR CONSOLE (Z8G4)
SIDE VIEW FRONT VIEW
SCALE 1:20
TOP VIEW
[15.7 in]
[2 2.
in
[15.8 in]
[24.3 in]
[2.2 in]
[2 2.
in
Weight: 64.2 kg [141.5 lbs]
1.
[1
1.
in
[7 in]
[1 2.
in
Center of Gravity
POWER DISTRIBUTION UNIT (PDU)
SCALE 1:20 Indicates air flow (Convection)
Center of Gravity
[35.4 in]
[14.2 in]
[5 .9 in
[2 1.
in
[3
5.
in ] 700
[27.6 in]
[9.3 in]
Service Area
TOP VIEW
Minimum air flow clearance
FRONT VIEW SIDE VIEW
[4 1.
in
[1 9.
in
[13.8 in] 12
[5
.1 in
[5.9 in]
[5 .5 in
[8 .7 in
[15.3 in]
[15.3 in]
Seismic mounting brackets Weight: 10 kg [22 lbs]
GANTRY WITH GT1700 TABLE
SCALE 1:50
RearFront
Sc an c en te rli ne
Sc an c en te rli ne
[4 0.
in
]19
[7 8.
in
[96.4 in]
936.5 [36.9 in]
936.5 [36.9 in]
[39.9 in]
[24.8 in]
[6.7 in]
302.2 [11.9 in]
[4 in
[124.3 in]
[4 0.
in
[7 8.
in
[4 1.
in
]46
[1 8.
in
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic A5 - Equipment Dimensions (1) 07
PARTIAL UNINTERRUPTIBLE POWER SUPPLY
SCALE 1:20
[3 0.
in
[10.3 in] 52
[2
0.
in
[26.8 in]
[30.3 in]
Plan view Front view Side view
MAIN DISCONNECT PANEL
FRONT VIEW SIDE VIEWTOP VIEW
SCALE 1:10
[14.5 in]
[2 8.
in
[16.7 in]
[3 0.
in
[8.3 in]
[10 in]
4xØ10
[Ø
0.4 in]
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic A6 - Equipment Dimensions (2) 08
DELIVERY
THE CUSTOMER/CONTRACTOR SHOULD:
· Provide an area adjacent to the installation site for delivery and unloading of the GE equipment.
· Ensure that the dimensions of all doors, corridors, ceiling heights are sufficient to accommodate the movement of GE equipment from the delivery area into the definitive installation room.
· Ensure that access routes for equipment will accommodate the weights of the equipment and any transportation, lifting and rigging equipment.
· Ensure that all necessary arrangements for stopping and unloading on public or private property not belonging to the customer have been made.
DIMENSIONS OF DELIVERY WITH DOLLY TRANSPORT EQUIPMENT
EQUIPMENT DIMENSIONS WEIGHT
GANTRY
LENGTH 3100 mm 122 in 2016 kg 4445 lbsWIDTH 1290 mm 51 in
HEIGHT 2030 mm 80 in
GT1700 TABLE
LENGTH 2489 mm 98 in 607 kg 1337 lbsWIDTH 762 mm 30 in
HEIGHT 1143 mm 45 in
GANTRY DELIVERY
· The gantry is shipped on a dolly equipped with elevating casters (normal shipping configuration).
NOT TO SCALE
[122 in]
[96.4 in]
[7 9.
in
[4 in
[39.9 in]
[50.8 in]
W=
H=
L=
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic A6 - Delivery 09
STRUCTURAL NOTES
· all steel work and parts necessary to support ceiling mounted equipment is to be supplied by the customer or his contractors.
· methods of support for the steelwork that will permit attachment to structural steel or through bolts in concrete construction should be favored. Do not use concrete or masonry anchors in direct tension.
· all units that are wall mounted or wall supported are to be provided with supports where necessary. Wall supports are to be supplied and installed by the customer or his contractors. See plan and detail sheets for suggested locations and mounting hole locations.
· all ceiling mounted fixtures, air vents, sprinklers, etc. To be flush mounted, or shall not extend more than 1/4" below the finished ceiling.
· floor slabs on which equipment is to be installed must be level to 1/4" in 10'-0"
· dimensions are to finished surfaces of room.
· customers contractor must provide all penetrations in post tension floors.
· customers contractor must provide and install any non-standard anchoring. Documents for standard anchoring methods are included with GE equipment drawings for geographic areas that require such documentation.
· customers contractor must provide and install hardware for "through the floor" anchoring and/or any bracing under access floors. This contractor must also provide floor drilling that cannot be completed because of an obstruction encountered while drilling by the GE installer such as rebar etc.
· it is the customer's responsibility to perform any floor or wall penetrations that may be required. The customer is also responsible for ensuring that no subsurface utilities (e.g., electrical or any other form of wiring, conduits, piping, duct work or structural supports (i.e. post tension cables or rebar)) will interfere or come in contact with subsurface penetration operations (e.g. drilling and installation of anchors/screws) performed during the installation process. To ensure worker safety, GE installers will perform surface penetration operations only after the customer's validation and completion of the "GE surface penetration permit"
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic S1 - Structural Notes 10
ITEM DESCRIPTION
1 Gantry leveling pads. See Structural Detail
2 Table leveling pads. See Structural Detail
(CONTRACTOR SUPPLIED & INSTALLED)
3 Support Backing, locate as shown
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic S2 - Structural Layout 111/4"=1'-0"
8'-3" [2511]
9' -6
EX
ST
1'
-7 5 8"
[5
EXAM
ROOM
S1122
CONTROL
ROOM
S1124
7' -1
0" [2
4]
5'-2" [1575]
11'-4" [3448]
EXST. 5'-11" [1803]
NOT TO SCALE
FLOOR REQUIREMENTS
FINISHED FLOOR REQUIREMENTS
· Installation requires a finish floor in the scan and control rooms
· The floor surface in the scan room directly under the gantry and table must be level.
· The floor levelness tolerance of the floor surface that the gantry and table will rest on is 6 mm [1/4 in] over a 3048 mm [10 ft] distance.
· Shims should not be used to compensate for a floor that does not meet this requirement.
· Eight or more floor covering openings that are 102 mm [4 in] in diameter are made to ensure the table and gantry rest on a solid surface.
These floor penetrations can be sealed if required.
· Concrete floors must have a minimum strength of f'c = 1.4 X10⁷ Pa [2000 PSI] at 28 days for (curing time) mounting floor anchors. It is the responsibility of each customer to have appropriate tests performed to determine and measure concrete strength.
· These requirements apply to all installation types.
M in m m
[4 in th ic k co nc re te
Leveling pad
Adjuster lock ring Gantry/Table stationary base
Leveling screw Anchor washer
13 mm [0.5 in] min - 25 mm [1 in] max after proper torque
Anchor bolt
GE SUPPLIED TABLE/GANTRY ANCHORS
NOTES:
· The distance from central line of anchor to the edge of concrete basement of Gantry/Table should not be less than 178 mm [7 in].
· Torque anchor to 54 Nm [40 ft-lb]
25 mm [1 in] for Table 13 mm [0.5 in] for Gantry
[2 5.
in
[32.3 in]
[2 4.
in
[8 in
[5 4.
in
[1 9.
in
[5
.2 in
[12 in]
[1 4.
in
[36.9 in]
[41.4 in]
[45.1 in]
[73.7 in]
ANCHORING/LOADING DISTRIBUTION TO THE FLOOR
Gantry 1816 kg [4003 lbs]
SCALE 1:20
3B
GT1700 Table 446 kg [984 lbs] with 227 kg [500 lbs] patient
[3 2.
in
[6 .7 in
[7.9 in]
[5 7.
in
[8 4.
in
[28.6 in]
(1) Tilting axis
(2) Longitudinal axis
(3) Cable inlet area
(with rear cable cover in option) (3B) Alternative cable inlet area
(4) 8 Gantry anchoring points
(5) First anchor to be drilled "Anchor A"
(6) 8 Table anchoring points
Center of gravity Main anchoring points Backup anchoring points
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic S3 - Structural Details (1) 12
HEAT DISSIPATION DETAILS
ROOM DESCRIPTION Max kW Max BTU
Exam Room
Gantry 8.96 30570
Patient Table 0.3 1030
TOTAL 9 31600
Exam Room or Technical Room*
Power Distribution Unit 1.0 3400
Partial UPS 0.83 2828
TOTAL 2 6228
Control Room Operator Console with 2 LCD monitors 2.4 8189
TOTAL 2 8189
*Technical Room is not mandatory, the placements of these elements are recommended in the Exam Room.
NOTE
In case of using air conditioning systems that have a risk of water leakage it is recommended not to install it above electric equipment or to take measures to protect the equipment from dropping water.
TEMPERATURE AND HUMIDITY SPECIFICATIONS
STORAGE CONDITIONS
IN-USE CONDITIONS
AIR RENEWAL
According to local standards.
Temperature 0°C to 30°C
32°F to 86°F Relative humidity (1) up to 70%
Temperature gradient ≤ 3C/h
5°F/h Humidity gradient ≤ 5%/h
Material should not be stored for more than 6 months.
(1) non-condensing
EXAM ROOM CONTROL ROOM
Temperature Min Recommended Max Min Recommended Max
18°C 22°C 26°C 18°C 22°C 26°C
64°F 72°F 79°F 64°F 72°F 79°F Relative humidity (1) 30% to 60% 30% to 60%
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic M1 - HVAC 13
ELECTRICAL NOTES
· All junction boxes, conduit, duct, duct dividers, switches, circuit breakers, cable tray, etc., are to be supplied and installed by customers electrical contractor. All junction boxes shall be provided with covers.
· Conduit and duct runs shall have sweep radius bends.
· Conduits and duct above ceiling or below finished floor must be installed as near to ceiling or floor as possible to reduce run length.
· Ceiling mounted junction boxes illustrated on this plan must be installed flush with finished ceiling.
· All ductwork must meet the following requirements:
1.Ductwork shall be metal with dividers and have removable, accessible covers.
2. Ductwork shall be certified/rated for electrical power purposes.
3. Ductwork shall be electrically and mechanically bonded together in an approved manner.
4. PVC as a substitute must be used in accordance with all local and national codes.
· All openings in raceway and access flooring are to be cut out and finished off with grommet material by the customers contractor.
· Electrical contractor to insert pull cords for all cable run conduits.
· Provide 10 foot pigtails at all junction points.
· Grounding is critical to equipment function and patient safety. Site must conform to wiring specifications shown on this plan.
1. Aluminum or solid wires are not allowed.
2. Wire sizes given are for use of equipment. Larger sizes may be required by local codes.
3. It is recommended that all wires be color coded, as required in accordance with national and local electrical codes.
4. Conduit sizes shall be verified by the architect, electrical engineer or contractor, in accordance with local or national codes.
5. Convenience outlets are not illustrated. Their number and location are to be specified by others. Locate at least one convenience outlet close to the system control, the power distribution unit and one on each wall of the procedure room. Use hospital approved outlet or equivalent.
6. General room illumination is not illustrated. Caution should be taken to avoid excessive heat from overhead spotlights.
Damage can occur to ceiling mounting components and wiring if high wattage bulbs are used. Recommend low wattage bulbs no higher than 75 watts and use dimmer controls (except MR). Do not mount lights directly above areas where ceiling mounted accessories will be parked.
7. Routing of cable ductwork, conduits, etc., must run direct as possible otherwise may result in the need for greater than standard cable lengths (refer to the interconnection diagram for maximum usable lengths point to point).
8. Conduit turns to have large, sweeping bends with minimum radius in accordance with national and local electrical codes.
9. In some cases GE will specify ground wires to be sized larger than code. In these situations, the GE specification must be followed.
10. A special grounding system is required in all procedure rooms by some national and local codes. It is recommended in areas where patients might be examined or treated under present, future, or emergency conditions. Consult the governing electrical code and confer with appropriate customer administrative personnel to determine the areas requiring this type of grounding system.
11. The maximum point to point distances illustrated on this drawing must not be exceeded.
12. Physical connection of primary power to GE equipment is to be made by customers electrical contractor with the supervision of a GE representative. The GE representative would be required to identify the physical connection location, and insure proper handling of GE equipment.
13. GEHC conducts power audits to verify quality of power being delivered to the system. The customer's electrical contractor is required to be available to support this activity.
14. Every installation is unique. The electrical contractor will be required to support the installation of the GE equipment by providing knockouts, grommeted openings, bushings, etc. as required. All power connections to be performed by the electrician.
CONNECTIVITY REQUIREMENTS
Your new GE Healthcare imaging modality will require local and remote connectivity to enable our full range of digital support:
· Local connectivity - This allows your system to connect to local devices such as PACS and modality worklist.
We will require network information to configure the system(s), and a live ethernet port(s) prior to the delivery of the system(s).
· Remote connectivity - Your GE Healthcare service warranty includes InSite™ (applicable to InSite capable products), a powerful broadband-based service which enables digital tools that can help guard your hospital against equipment downtime and revenue loss by quickly connecting you to a GE Healthcare expert.
Depending on product family and software version, imaging systems can be connected in one of the following methods:
1. TLS over TCP Port 443 (Preferred method for new products) via:
a. DNS resolution
b. Customer-provided Proxy or
c. GE Proxy (Available in some regions)
2. Site-to-Site IPsec VPN tunnel
Please provide the GE project manager with the contact information for the resource that can provide information required to set up these connections. GEHC will send out communication to these contacts, which will include the project's Connectivity requirements, and a Connectivity form. This form will need to be completed and returned to GEHC prior to delivery of the system to ensure the system is tested and connectivity is enabled prior to the completion of the installation.
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic E1 - Electrical Notes 14
B
A
ITEM QTY
Electrical Outlet Legend
Customer/contractor supplied and installed items unless otherwise specified.
Height above floor determined by local codes unless otherwise specified.
Duplex hospital grade, dedicated wall outlet 120-v, single phase power
Dedicated telephone line(s)
Network outlet System emergency off (SEO), (recommended height 1.2m [48"] above floor)
X-Ray room warning light control panel
X-Ray ON lamp (L1) - 24V
Door interlock switch (needed only if required by state/local codes)
Existing Electrical Note:
Use existing duct/conduits where possible. Additional duct/conduit runs may be necessary if existing system is inadequate in size and/or location for this installation. Verify existing size and location.
Additional Conduit Runs (Contractor Supplied and Installed)
From (Bubble # / Item)
To (Bubble # / Item) Qty
Size In. mm
3 Phase Power 1 Main Disconnect Panel 1 As req'd As req'd
1 Main Disconnect Panel Emergency Off 1 1/2 13
5 Power Distribution Unit 1 As req'd As req'd
5 Power Distribution Unit Door Switch 1 1/2 13
Warning Light Control 1 1/2 13
Warning Light 1 1/2 13
1 Phase Power 1 1/2 13
1 Main Disconnect Panel 7 Partial UPS 1 1 1/4 30
Item Electrical Layout Item List
1 Main disconnect panel (MDP)
2 Suitable chase nipples, refer to Anchoring/Loading Distribution to the Floor detail on sheet S3 (Gantry)
3 Grommeted opening (Power Distribution Unit)
4 Grommeted opening (Operator's Console)
5 12" x 16" x 4" [150 x 150 x 100] box (Power Distribution Unit)
6 12" x 3" [300 x 100] trench duct with minimum 2 dividers
7 [Existing] 4" x 4" x 4" [100 x 100 x 100] box (Partial UPS)
8 [Existing] 9" x 4" [230 x 100] trench duct with minimum 2 dividers
9 [Existing] 10" x 3 1/2" [250 x 100] surface wall duct with minimum 2 dividers
10 10" x 3 1/2" [250 x 100] surface wall duct with minimum 2 dividers
11 [Existing] 1 1/2" [38] conduit above ceiling
12 [Existing] 3" [76] conduit above ceiling
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic E2 - Electrical Layout 151/4"=1'-0"
8'-3"
9' -6
EX
ST
1' -7
5 8"
EXAM
ROOM
S1122
CONTROL
ROOM
S1124
2'-11"
EXST. 5'-11"
2' -7
0'-7"
A
B
* * * EXISTING ROOM * * *
NOTE: ALL OTHER JUNCTION POINTS IN ELEVATIONS ARE EXISTING, AND
THUS ARE NOT SHOWN.
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic E3 - Electrical Elevations 161/4"=1'-0"
15'-0"
0'-0"
9'-0"
15'-0"
0'-0"
9'-0"
EX
ST
. 5 '-0
0' -9
1' -0
7 5
8 4
POWER DISTRIBUTION
SEO3
24 V
PDU
For Scan Room
Warning Light and Door Interlock
Connections Detail refer to the next page
Emergency OFF (Control room)
Emergency OFF (Exam room) If applicable
Emergency OFF (Technical room)
If applicable
Notes :
(1) Wire size: 4x2mm² [14AWG] and 1x2mm² [14AWG] GND
(2) Power control cable: 3 Meter [10 ft], multi-conductor, 24V DC
(3) GE supplied MDP option E45021BC includes a 10 meter long power cable (H07RN-F) with wire size
4x50mm² and a 50 meter long control cable with wire size 2x1.5mm²
Refer to Table1
Table1:
MDP MDP Main Disconnect Panel PDU Power Distribution Unit SEO Emergency OFF Button latching twist-to release style with two normally closed (NC) contacts
Y Remote Operator Control Station with "ON" and "OFF" buttons
Table2:
24 V
24 V (1)
Cable SUPPLIED BY CUSTOMER Cable SUPPLIED BY GE Equipment SUPPLIED BY
CUSTOMER
Equipment SUPPLIED BY GE
(1)
(1)
YRemote ON/OFF (Control room)
If applicable 24 V
(2)
SEO2
SEO1
For Main Supply (3 phases) Feeder and Ground wire size Refer to Table2
For Sub-Feeder and Ground wire size refer to Table2 (3)
Feeder Table The information below assumes the use of copper wire, rated 75 C and run in steel conduit. All ampacity is determined in accordance with the National Electrical Code (NFPA 70), Table 310-16 (2002). The ampacity of the circuit protection device listed above determines the minimum feeder size, except where total source regulation limits require a larger size. If the wire size does not match the lists below, please select the nearest wire size as per to local standards.
Feeder length from Power Substation to MDP - ft (m)
Minimum Wire Size, AWG or MCM (mm²)/VAC
380 VAC 400 VAC 420 VAC 440 VAC 460 VAC 480 VAC
50 (15) 1/0 (50) 1/0 (50) 1/0 (50) 1 (45) 1 (45) 1 (45)
100 (30) 1/0 (50) 1/0 (50) 1/0 (50) 1 (45) 1 (45) 1 (45)
150 (46) 1/0 (50) 1/0 (50) 1/0 (50) 1 (45) 1 (45) 1 (45)
200 (61) 1/0 (50) 1/0 (50) 1/0 (50) 1 (45) 1 (45) 1 (45)
250 (76) 2/0 (70) 2/0 (70) 1/0 (50) 1/0 (50) 1 (45) 1 (45)
300 (91) 3/0 (85) 3/0 (85) 2/0 (70) 2/0 (70) 1/0 (50) 1/0 (50) 350 (107) 4/0 (100) 3/0 (85) 3/0 (85) 2/0 (70) 2/0 (70) 1/0 (50) 400 (122) 250 (125) 4/0 (100) 3/0 (85) 3/0 (85) 3/0 (85) 2/0 (70)
Sub-Feeder length from MDP to PDU
- ft (m)
32 (9.7536) 1/0 (50) 1/0 (50) 1/0 (50) 1 (45) 1 (45) 1 (45) Grounding
Run a dedicated 1/0 [50 mm²] or larger insulated copper ground wire from the power source to the MDP and from MDP to the PDU. Run the ground wire in the same raceway with the three-phase wires.
GE Supplied Main Disconnect Panel (MDP)
Region CAT number Amps Global except
EMEA(440~480 V) E4502BE 125
Global except
EMEA(380~420 V) E4502BF 150
EMEA(400 V) E45021BC (3) 160
Partial UPS (option)
POWER REQUIREMENTS
· Power supply should come into a Main Disconnect Panel (MDP) containing the protective units and controls.
· The section of the supply cable should be calculated in accordance with its length and the maximum permissible voltage drops.
· There must be discrimination between supply cable protective device at the beginning of the installation
(main low-voltage transformer side) and the protective devices in the MDP.
SUPPLY CHARACTERISTICS
· Power input must be separate from any others which may generate transients (elevators, air conditioning, radiology rooms equipped with high speed film changers...).
· All equipment (lighting, power outlets, etc...) installed with GE system components must be powered separately.
· The minimum recommended transformer size for a dedicated distribution transformer provided for the system is 225kVA, rated 2.4% regulation at unity power factor.
· Phase imbalance 2% maximum.
· Maximum voltage variation at 150kVA = 5% (Including line impedance.)
· Transients must be less than 1500V peak. (on a 400V line)
GROUND SYSTEM
· System of equipotential grounding.
· Equipotential: The equipotential link will be by means of an equipotential bar. This equipotential bar should be connected to the protective earth conductors in the ducts of the non GE cableways and to additional equipotential connections linking up all the conducting units in the rooms where GE system units are located.
CABLES
· Power and cable installation must comply with the distribution diagram.
· All cables must be isolated and flexible, cable color codes must comply with standards for electrical installation.
· The cables from signaling and remote control (Y, SEO, L...) will go to MDP with a pigtail length of 1.5m [4.9'], and will be connected during installation. Each conductor will be identified and isolated (screw connector).
CABLEWAYS
The general rules for laying cableways should meet the conditions laid down in current standards and regulations, with regard to:
· Protecting cables against water (cableways should be waterproof).
· Protecting cables against abnormal temperatures (proximity to heating pipes or ducts).
· Protecting cables against temperature shocks.
· Replacing cables (cableways should be large enough for cables to be replaced).
· Metal cableways should be grounded.
POWER SUPPLY 3 PHASES+G 380/400/420/440/460/480 V ± 10%
FREQUENCIES 50/60 Hz ± 3 Hz MAXIMUM POWER DEMAND 150 kVA AVERAGE (CONTINUOUS) POWER DEMAND 30 kVA
POWER FACTOR 0.85
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic E4 - Power Requirements 17
SCAN ROOM WARNING LIGHT AND DOOR INTERLOCK
PDU
DOOR SWITCH (2)
EXP_INTLK
PGND
CONTROL
BOARD
KD6
KD5
KD7
TS6
FUSE
24V max
READY LIGHT
SYS-ON LIGHT
L N
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
X-RAY LIGHTR1 R1
R2
R3
Facility Input Power (3)
PDU Power Distribution Unit TS6 Terminal Block 6
Cable SUPPLIED BY CUSTOMER Cable SUPPLIED BY GE Equipment SUPPLIED BY CUSTOMER Equipment SUPPLIED BY GE
Fuse Relay coil and contact -normally open (de-energized state)
Control power transformer
R2
R3
Notes :
(1) Wire size: 2mm² [14 AWG] at 24V
(2) Door Interlock circuit is jumpered out if a door switch is not provided.
(3) Grounding not shown on the detail, but must comply with local codes.
INTERCONNECTIONS
Orderable from GE
CONTROL ROOM
PARTIAL
UPS
(OPTION)
PDB
Customer supply
PDU11.00 m [37']
2.00 m [7']
18.30 m or 22.86 m [60' or 75']
6.00 m or 16.76 m [20' or 55']
17.40 m or 22.86 m [57' or 75']
Operator Console
1.50 m or 3.00 m [4.9' or 9.8']
EXAM ROOMEXAM ROOM / TECHNICAL ROOM
DateRev /18CT-M447727-FIN-01-A.DWG A 23/Jun/2025DISCOVERY RTHarris Health Smith Clinic E5 - Electrical Details - Interconnect 18
TYPICAL CABLE MANAGEMENT
FLUSH FLOOR DUCT
Waterproof joint removable cover Dividers as required per local code
Rev Date:
15.Dec.21
NOT TO SCALE
Removable coverplate
DUCT ON THE WALL
Dividers as required per local code
Rev Date:
15.Dec.21
| Sheets and Views |
| CT-M447727-FIN-01-A-C1 - Cover Sheet |
| OLE1 |
| CT-M447727-FIN-01-A-C2 - Disclaimer - Site Readiness Checklist |
| OLE1 |
| CT-M447727-FIN-01-A-A1 - General Notes |
| OLE1 |
| CT-M447727-FIN-01-A-A2 - Equipment Layout |
| OLE1 |
| CT-M447727-FIN-01-A-A3 - Radiation Protection |
| OLE1 |
| CT-M447727-FIN-01-A-A4 - Radiation Protection Details |
| OLE1 |
| CT-M447727-FIN-01-A-A5 - Equipment Dimensions (1) |
| OLE1 |
| CT-M447727-FIN-01-A-A6 - Equipment Dimensions (2) |
| OLE1 |
| CT-M447727-FIN-01-A-A6 - Delivery |
| OLE1 |
| CT-M447727-FIN-01-A-S1 - Structural Notes |
| OLE1 |
| CT-M447727-FIN-01-A-S2 - Structural Layout |
| OLE1 |
| CT-M447727-FIN-01-A-S3 - Structural Details (1) |
| OLE1 |
| CT-M447727-FIN-01-A-M1 - HVAC |
| OLE1 |
| CT-M447727-FIN-01-A-E1 - Electrical Notes |
| OLE1 |
| CT-M447727-FIN-01-A-E2 - Electrical Layout |
| OLE1 |
| CT-M447727-FIN-01-A-E3 - Electrical Elevations |
| OLE1 |
| CT-M447727-FIN-01-A-E4 - Power Requirements |
| OLE1 |
| CT-M447727-FIN-01-A-E5 - Electrical Details - Interconnect |
| OLE1 |