8--7- Project Manual- FAC133242 ADC Heat Exchangers – Final Phase.pdf

PDF 5 MB Posted

Attached to
SLCo FAC133242 ADC Heat Exchangers – Final Phase- CONST
Solicitation number
SLCo FAC133242 ADC Heat Exchangers – Final Phase- CONST
Issued by
Utah

About this file

This is a Project Manual and Construction Documents file for Salt Lake County's Adult Detention Center Remaining Heat Exchanger Replacements project, involving Salt Lake County as the owner, Architectural Nexus, Inc. as the architect, and Resolut Group as the mechanical and electrical engineer. The project involves the removal and replacement of existing water heaters, heat exchangers, associated piping, tanks, and valves at the facility located at 3415 South 900 West, South Salt Lake, Utah 84119, with construction documents dated May 2026 under Project Number AN-25049. The work is being conducted under a single prime contract initiated by Salt Lake County, with work restricted to normal business hours of 7:00 a.m. to 5:00 p.m., Monday through Saturday, and coordination required with the County's occupancy during the entire construction period. Contractor must provide 48 hours' advance notice for activities affecting Owner operations, maintain access to walkways and corridors, and remove all demolished materials carefully through a designated ramp to dumpsters in the visitors parking area.

The contract documents establish comprehensive requirements for submittal procedures, quality assurance and control, project coordination, and temporary facilities. Contractors must submit electronic PDF submittals with proper bookmarking and identification using the project number with sequential numbering; initial reviews allow 15 days with additional time for resubmittals. All submittals require Contractor approval stamps before Architect review, and fabrication cannot commence until written acceptance is received. The documents require coordination drawings where installation is complex, requests for information (RFIs) responses within 7 working days, and bi-weekly progress meetings. Special attention is given to photographic documentation with weekly construction photographs and preconstruction baseline images. Contractor is responsible for quality-control testing and inspections, with costs for retesting of failed work charged to Contractor. Temporary facilities must include field offices, fire safety compliance with NFPA 241, sanitary facilities, and environmental protection measures including erosion and sedimentation control per EPA Construction General Permit requirements.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION DOCUMENTS

MAY 2026 SALT LAKE COUNTY

ADULT DETENTION

CENTER - REMAINING

HEAT EXCHANGER

REPLACEMENTS

PROJECT MANUAL

3415 S 900 W

SOUTH SALT LAKE, UT 84119

PROJECT NO: AN-25049

SALT LAKE COUNTY ADULT DETENTION CENTER - REMAINING

HEAT EXCHANGER REPLACEMENTS

CONSTRUCTION DOCUMENTS

AN-25049

MAY 2026

TABLE OF CONTENTS 00 0110 – 1

TABLE OF CONTENTS

DIVISION 01 — GENERAL REQUIREMENTS

01 1000 SUMMARY

01 2500 SUBSTITUTION PROCEDURES

01 3100 PROJECT MANAGEMENT AND COORDINATION

01 3233 PHOTOGRAPHIC DOCUMENTATION

01 3300 SUBMITTAL PROCEDURES

01 4000 QUALITY REQUIREMENTS

01 4200 REFERENCES

01 5000 TEMPORARY FACILITIES AND CONTROLS

01 6000 PRODUCT REQUIREMENTS

01 7300 EXECUTION

01 7419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 7700 CLOSEOUT PROCEDURES

01 7823 OPERATION AND MAINTENANCE DATA

01 7839 PROJECT RECORD DOCUMENTS

01 7900 DEMONSTRATION AND TRAINING

DIVISION 02 — EXISTING CONDITIONS

02 4119 SELECTION DEMOLITION

DIVISION 22 — PLUMBING

22 0500 COMMON WORK RESULTS FOR PLUMBING

22 0519 METERS AND GAGES FOR PLUMBING PIPING

22 0523 GENERAL DUTY VALVES FOR PLUMBING PIPING

22 0529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

22 0548 VIBRATION AND SEISMIC CONTROL FOR PLUMBING PIPING AND EQUIPMENT

22 0553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

22 0719 PLUMBING PIPING INSULATION

22 1116 DOMESTIC WATER PIPING

22 1223 FACILITY INDOOR POTABLE-WATER STORAGE TANKS

22 3501 PACKAGED DOMESTIC WATER-TO-WATER HEAT EXCHANGERS

DIVISION 23 — HEATING VENTILATING AND AIR CONDITIONING

23 0100 MECHANICAL REQUIREMENTS

23 0500 COMMON WORK RESULT FOR HVAC

23 0519 METERS AND GAGES FOR HVAC

23 0523 GENERAL-DUTY VALVES FOR HVAC PIPING

23 0529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

23 0548 VIBRATION AND SEISMIC CONTROLS FOR HVAC

23 0550 OPERATION AND MAINTENANCE OF HVAC SYSTEMS

23 0553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

23 0593 TESTING ADJUSTING AND BALANCING FOR HVAC

23 0719 HVAC PIPING INSULATION

23 2113 HYDRONIC PIPING

23 2116 HYDRONIC PIPING SPECIALTIES

23 2123 HYDRONIC PUMPS

CONSTRUCTION DOCUMENTS

SUMMARY 01 1000 – 1

SECTION 01 1000 - SUMMARY

GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Scope of Work covered by Contract Documents.

3. Type of Contract

4. Permits and Fees

5. Special Inspection, Testing and Commissioning

6. Changes in the Work

7. Prior Approvals

8. Schedule of Values/List of Subcontractors

9. Contractor Supervision

10. Contractor Daily Record

11. Liquidated Damages

12. Access to Site

13. Coordination of Occupants

14. Specification and drawing conventions.

B. NOTICE TO BIDDERS:

1. During the bid process, all communications and questions are to be submitted via the online solicitation portal only. No communication is to be had directly with architect/engineer during, or prior, to bids being received. This paragraph supersedes all notes on the drawings and the specifications.

1.2 PROJECT INFORMATION

A. Project Identification:

1. SLCo Adult Detention Center Remaining Water Heat Exchanger Replacement:

3415 South 900 East, South Salt Lake City, Utah 84119

B. Owner’s Representatives: Salt Lake County (SLCo)

1. SLCo Facilities Project Manager: Jordan Gray (385.214.6750, jgray@slco.org)

C. Salt Lake County Jail – Adult Detention Center (ADC) Facility Representatives.

1. Lt. Chris Hansen (801.638.7847, cphansen@saltlakecounty.gov)

2. Facilities: Marco Morley (385.468.8453, mmorley@saltlakecounty.gov)

D. Architect: Architectural Nexus, Inc.

1. Principal-In-Charge: Stephen Springer (801.924.5000, sspringer@archnexus.com)

2. Project Manager: Ryan Bowker (801.924.5000, rbowker@archnexus.com)

E. Mechanical Engineer: Resolut Group

1. Engineer of Record: Jake Beck (801.530.3148, jbeck@resolutgroup.com) mailto:jgray@slco.org mailto:cphansen@saltlakecounty.gov mailto:mmorley@saltlakecounty.gov mailto:hadams@archnexus.com mailto:rbowker@archnexus.com mailto:jbeck@resolutgroup.com

CONSTRUCTION DOCUMENTS

SUMMARY 01 1000 – 2

F. Electrical Engineer: Resolut Group

1. Engineer of Record: Sang Truong (801.530.3148, struong@resolutgroup.com)

1.3 SCOPE OF WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. The removal and replacement of existing water heaters and associated piping, tanks and valves as shown in drawings.

1.4 TYPE OF CONTRACT

A. Project will be constructed under single prime contract as initiated and prepared by SLCo.

B. SLCo’s General Conditions and Supplemental Conditions will supersede all standard specifications.

PERMITS AND FEES

Specification Sections: For convenience or reference and to facilitate letting of subcontracts, the specifications are separated into respective divisions and sections. The forming of these separations shall not operate to make the Architect or the County or any of its representatives an arbiter to establish subcontract limits between contractor and subcontractor or suppliers.

2.1 ACCESS TO SITE

A. General: Contractor shall have limited use of Project site for construction operations during construction period as coordinated with owner. Contractor's use of Project site is limited by Owner's operational requirements and as described in attached documents.

B. Use of Site: Limit use of Project site to work in areas and parking lot staging area agreed to by Owner’s representative. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Condition of Existing Building: Maintain portions of existing building and systems affected by construction operations during construction period. Repair damage caused by construction operations.

D. Refer to General Notes – All demolished materials to be removed carefully down ramp to dumpsters located in visitors parking area as directed by facility manager.

2.2 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy site and existing building during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.

CONSTRUCTION DOCUMENTS

SUMMARY 01 1000 – 3

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.

2. Notify Owner not less than 48 hours in advance of activities that will affect Owner's operations.

3. Access site as directed by owner, complying with access and tool restrictions.

2.3 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Saturday, unless otherwise indicated.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than two days in advance of proposed utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify Architect & Owner not less than two days in advance of proposed disruptive operations.

2. Nonsmoking Building: Smoking is not permitted within the building, on the roof or within 25 feet of entrances, operable windows, or outdoor-air intakes.

2.4 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations

CONSTRUCTION DOCUMENTS

SUMMARY 01 1000 – 4

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

END OF SECTION 01 1000

CONSTRUCTION DOCUMENTS

SUBSTITUTION PROCEDURES 01 2500 – 1

SECTION 01 2500 - SUBSTITUTION PROCEDURES

1.1 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

1.2 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1.3 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use CSI Form 13.1A.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section.

Product Data, including drawings and descriptions of products and fabrication and installation procedures.

d. Samples, where applicable or requested.

e. Certificates and qualification data, where applicable or requested.

f. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

g. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time do not submit. Cost information, including a proposal of change, if any, in the Contract Sum.

h. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

i. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.

Architect will notify Contractor of acceptance or rejection of proposed substitution within 7 days of receipt of request

CONSTRUCTION DOCUMENTS

SUBSTITUTION PROCEDURES 01 2500 – 2

1.4 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials.

PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Requested substitution will not adversely affect Contractor's construction schedule.

c. Requested substitution has received necessary approvals of authorities having jurisdiction.

d. Requested substitution is compatible with other portions of the Work.

e. Requested substitution has been coordinated with other portions of the Work.

f. Requested substitution provides specified warranty.

B. Substitutions for Convenience: Not allowed.

END OF SECTION 01 2500

CONSTRUCTION DOCUMENTS

PROJECT MANAGEMENT AND COORDINATION 01 3100 – 1

SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Coordination Drawings

2. Requests for Information (RFIs).

3. Project meetings.

1.2 DEFINITIONS

A. RFI: Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.3 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Delivery and processing of submittals.

4. Construction Progress meetings.

5. Preinstallation conferences.

6. Project closeout activities.

1.4 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

CONSTRUCTION DOCUMENTS

PROJECT MANAGEMENT AND COORDINATION 01 3100 – 2

a. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return RFIs submitted to Architect by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

a. SLCo’s Project Number

b. Architect’s, AN Project Number

3. Date Issued.

4. Response date deadline if requested different then allowed Contract Time.

5. Name of Contractor.

6. Name of Architect

7. RFI number, numbered sequentially.

8. RFI subject.

9. Specification Section number and title and related paragraphs, as appropriate.

10. Drawing number and detail references, as appropriate.

11. Field dimensions and conditions, as appropriate.

12. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

13. Contractor's signature.

14. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. RFI Forms: AIA Document G716.

D. Architect's Action: Architect will review each RFI, determine action required, and respond.

Allow 7 working days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.

1. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt of additional information.

2. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal as required by Owner.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log weekly. Include the following:

1. Project name.

2. Name and address of Contractor.

CONSTRUCTION DOCUMENTS

PROJECT MANAGEMENT AND COORDINATION 01 3100 – 3

3. Name and address of Architect.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect's response was received.

F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within seven days if Contractor disagrees with response.

1. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.

2. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

1.6 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Contractor’s Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Architect, within 7 days of the meeting.

B. Preinstallation Conferences: Conduct a preinstallation conference at Project site before construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Architect and Owner of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

C. Progress Meetings: Bi-Weekly intervals or as determined.

1. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

CONSTRUCTION DOCUMENTS

PROJECT MANAGEMENT AND COORDINATION 01 3100 – 4

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do

so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present.

3. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

END OF SECTION 01 3100

CONSTRUCTION DOCUMENTS

PHOTOGRAPHIC DOCUMENTATION 01 3233 – 1

SECTION 01 3233 - PHOTOGRAPHIC DOCUMENTATION

1.1 SUMMARY

A. Section includes administrative and procedural requirements for the following:

1. Preconstruction photographs.

2. Periodic construction photographs.

B. Related Requirements:

1. Section 01 7700 "Closeout Procedures" for submitting photographic documentation as Project Record Documents at Project closeout.

1.2 INFORMATIONAL SUBMITTALS

A. Key Plan: Submit key plan of building area with notation of vantage points marked for location and direction of each photograph. Indicate elevation or story of construction. Include same information as corresponding photographic documentation.

B. Digital Photographs: Submit unaltered, original, full-size image files within seven days of taking photographs.

1. Digital Camera: Minimum sensor resolution of 8 megapixels.

2. Identification: Provide the following information with each image description in file metadata tag:

a. Name of Project.

b. Name and contact information for photographer.

c. Date photograph was taken.

d. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

PRODUCTS

2.1 PHOTOGRAPHIC MEDIA

A. Digital Images: Provide images in JPG format, with minimum size of 8 megapixels.

EXECUTION

3.1 CONSTRUCTION PHOTOGRAPHS

A. General: Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.

B. Digital Images: Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.

1. Date and Time: Include date and time in file name for each image.

CONSTRUCTION DOCUMENTS

PHOTOGRAPHIC DOCUMENTATION 01 3233 – 2

2. Field Office Images: Maintain one set of images accessible in the field office at Project site, available at all times for reference. Identify images in the same manner as those submitted to Architect.

C. Preconstruction Photographs: Before commencement of demolition take photographs of Project area, including existing items to remain during construction, from different vantage points

D. Periodic Construction Photographs: Take weekly, with timing each month adjusted to coincide with the cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last photographs were taken.

END OF SECTION 01 3233

CONSTRUCTION DOCUMENTS

SUBMITTAL PROCEDURES 01 3300 – 1

SECTION 01 3300 - SUBMITTAL PROCEDURES

1.1 SUMMARY

A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

B. Related Requirements:

1. Section 01 7823 "Operation and Maintenance Data" for submitting operation and maintenance manuals.

2. Section 01 7839 "Project Record Documents" for submitting record Drawings, record Specifications, and record Product Data.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Architect's responsive action.

B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's responsive action. Submittals may be rejected for not complying with requirements.

1.3 ACTION SUBMITTALS

A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Architect and additional time for handling and reviewing submittals required by those corrections.

1.4 SUBMITTAL ADMINISTRATIVE REQUIREMENTS

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.

Time for review shall commence on Architect's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

CONSTRUCTION DOCUMENTS

SUBMITTAL PROCEDURES 01 3300 – 2

1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Architect will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 15 days for review of each resubmittal.

C. Paper Submittals: Place a permanent label or title block on each submittal item for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space approximately 6 by 8 inches on label or beside title block to record

Contractor's review and approval markings and action taken by Architect.

3. Include the following information for processing and recording action taken:

a. Project name.

b. Date.

c. Name of Architect.

d. Name of Construction Manager.

e. Name of Contractor.

f. Name of subcontractor.

g. Name of supplier.

h. Name of manufacturer.

i. Submittal number or other unique identifier, including revision identifier.

1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01). Resubmit-tals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A).

j. Number and title of appropriate Specification Section.

k. Drawing number and detail references, as appropriate.

l. Location(s) where product is to be installed, as appropriate.

m. Other necessary identification.

D. Electronic Submittals: (Preferred) Identify and incorporate information in each electronic submittal file as follows:

1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item. Submittals not bookmarked will be returned without review.

Review time will not start until PDF is returned to the Architect with bookmarks.

2. Name file with the Architect’s project number with submittal number or other unique identifier, including revision identifier.

a. File name shall use Architect’s project identifier, Submittal Number and Specification Section number followed by a decimal point and then a sequential number (e.g., LNHS-061000.01). Resubmittals shall include the submittal revision number and an alphabetic suffix after another decimal point (e.g., LNHS-

061000.01. A).

3. Provide submittal log for insertion to permanently record Contractor's review and approval markings and action taken by Architect.

E. Options: Identify options requiring selection by Architect.

CONSTRUCTION DOCUMENTS

SUBMITTAL PROCEDURES 01 3300 – 3

F. Deviations: Identify deviations from the Contract Documents on submittals.

G. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Architect's action stamp.

H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

I. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Architect/Engineer action stamp(s).

PRODUCTS

2.1 SUBMITTAL PROCEDURES

A. General Submittal Procedure Requirements:

1. Submit electronic submittals via email as PDF electronic files.

a. Architect will return annotated file. Annotate and retain one copy of file as an electronic Project record document file.

2. Action Submittals: Submit three paper copies of each submittal unless otherwise indicated. Architect will return two copies, unless electronic.

3. Informational Submittals: Submit three paper copies of each submittal unless otherwise indicated. Architect will not return copies.

4. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

a. Provide a digital signature with digital certificate on electronically-submitted certificates and certifications where indicated.

b. Provide a notarized statement on original paper copy certificates and certifications where indicated.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

CONSTRUCTION DOCUMENTS

SUBMITTAL PROCEDURES 01 3300 – 4

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. Submit Product Data concurrent with Samples.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 30 by 42 inches.

3. Submit Shop Drawings in the following format:

a. PDF electronic file.

b. Three opaque copies of each submittal. Architect will retain two copies; remainder will be returned.

D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample.

b. Product name and name of manufacturer.

c. Sample source.

d. Number and title of applicable Specification Section.

3. For projects where electronic submittals are required, provide corresponding electronic submittal of Sample transmittal, digital image file illustrating Sample characteristics, and identification information for record.

4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit one full set of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Architect will return submittal with options selected.

5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the

CONSTRUCTION DOCUMENTS

SUBMITTAL PROCEDURES 01 3300 – 5

following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit three sets of Samples. Architect will retain two Sample sets; remainder will be returned.

1) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.

E. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Submit product schedule in the following format:

a. PDF electronic file.

Links

F. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

G. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

H. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

I. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

J. Design Data: Prepare and submit written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations.

Include list of assumptions and other performance and design criteria and a summary of loads.

Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.

EXECUTION

3.1 CONTRACTOR'S REVIEW

A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Architect/Engineer.

1. Sign or initial each sheet of Shop Drawings and product data, and each sample label to certify compliance with requirements of Contract Documents. Notify Architect/Engineer in writing at time of submittal, of any deviations from requirements of Contract Documents.

2. Do Not fabricate products or begin work that requires submittals until return of submittal review with Architect/Engineer acceptance.

CONSTRUCTION DOCUMENTS

SUBMITTAL PROCEDURES 01 3300 – 6

B. Project Closeout and Maintenance Material Submittals: See requirements in Section 01 7700 "Closeout Procedures."

C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

3.2 ARCHITECT'S/ENGINEER’S ACTION

A. General: Architect/Engineer will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. Action Submittals: Architect/Engineer will review each submittal, make marks to indicate corrections or revisions required, and return it. Architect/Engineer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.

C. Informational Submittals: Architect/Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements. Architect will forward each submittal to appropriate party.

D. Architect’s Review Stamp Disclaimer:

“CHECKING IS ONLY FOR GENERAL CONFORMANCE WITH THE DESIGN CONCEPT OF

THE PROJECT AND GENERAL COMPLIANCE WITH THE INFORMATION GIVEN IN THE

CONTRACT DOCUMENTS. ANY ACTION SHOWN IS SUBJECT TO THE REQUIREMENTS

OF THE PLANS AND SPECIFICATIONS. CONTRACTOR IS RESPONSIBLE FOR

DIMENSIONS AND QUANTITIES WHICH SHALL BE CONFIRMED AND CORRELATED AT

THE JOB SITE; FABRICATION PROCESSES AND TECHNIQUES OF CONSTRUCTION;

COORDINATION OF HIS OR HER WORK WITH THAT OF ALL OTHER TRADES; AND THE

SATISFACTORY PERFORMANCE OF HIS OR HER WORK.”

E. Architect’s Review Stamp Actions may be one or more of the following (Engineer review stamp(s) may be similar):

1. Reviewed

2. No Exception Taken

3. Rejected

4. Submit Specified Items

5. Make Corrections Noted

6. Revise and Resubmit

F. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

G.

Submittals not required by the Contract Documents may not be reviewed and may be discarded.

END OF SECTION 01 3300

CONSTRUCTION DOCUMENTS

QUALITY REQUIREMENTS 01 4000 – 1

SECTION 01 4000 - QUALITY REQUIREMENTS

1.1 SUMMARY

A. Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.

1. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.

2. Requirements for Contractor to provide quality-assurance and -control services required by Architect, Owner, or authorities having jurisdiction are not limited by provisions of this Section.

3. Specific test and inspection requirements are not specified in this Section.

1.2 DEFINITIONS

A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Architect.

C. Mockups: Full-size physical assemblies that are constructed on-site. Mockups are constructed to verify selections made under Sample submittals; to demonstrate aesthetic effects and, where indicated, qualities of materials and execution; to review coordination, testing, or operation; to show interface between dissimilar materials; and to demonstrate compliance with specified installation tolerances. Mockups are not Samples. Unless otherwise indicated, approved mockups establish the standard by which the Work will be judged.

D. Preconstruction Testing: Tests and inspections performed specifically for Project before products and materials are incorporated into the Work, to verify performance or compliance with specified criteria.

E. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements.

F. Source Quality-Control Testing: Tests and inspections that are performed at the source, e.g., plant, mill, factory, or shop.

G. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

CONSTRUCTION DOCUMENTS

QUALITY REQUIREMENTS 01 4000 – 2

H. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

I. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1. Use of trade-specific terminology in referring to a trade or entity does not require that certain construction activities be performed by accredited or unionized individuals, or that requirements specified apply exclusively to specific trade(s).

J. Experienced: When used with an entity or individual, "experienced" means having successfully completed a minimum of five previous projects similar in nature, size, and extent to this Project;

being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

1.3 CONFLICTING REQUIREMENTS

A. Referenced Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer conflicting requirements that are different, but apparently equal, to Architect for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits.

To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.

1.4 INFORMATIONAL SUBMITTALS

A. Contractor's Statement of Responsibility: When required by authorities having jurisdiction, submit copy of written statement of responsibility sent to authorities having jurisdiction before starting work.:

B. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

1.5 REPORTS AND DOCUMENTS

A. Test and Inspection Reports: Prepare and submit certified written reports specified in other Sections. Include the following:

1. Date of issue of test.

2. Project title, and number.

3. Name, address, and telephone number of testing agency.

4. Dates and locations of samples and tests or inspections.

5. Names of individuals making tests and inspections.

6. Description of the Work and test and inspection method.

7. Identification of product and Specification Section.

8. Complete test or inspection data.

9. Test and inspection results and an interpretation of test results.

CONSTRUCTION DOCUMENTS

QUALITY REQUIREMENTS 01 4000 – 3

10. Record of temperature and weather conditions at time of sample taking and testing and inspecting.

11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.

12. Name and signature of laboratory inspector.

13. Recommendations on retesting and re-inspecting.

B. Manufacturer's Field Reports: Prepare written information documenting tests and inspections specified in other Sections. Include the following:

1. Name, address, and telephone number of representative making report.

2. Statement on condition of substrates and their acceptability for installation of product.

3. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.

4. Results of operational and other tests and a statement of whether observed performance complies with requirements.

5. Other required items indicated in individual Specification Sections.

C. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.6 QUALITY ASSURANCE

A. General: Qualifications paragraphs in this article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.

B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

D. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar in material, design, and extent to those indicated for this Project.

F. Specialists: Certain Specification Sections require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

1. Requirements of authorities having jurisdiction shall supersede requirements for specialists.

G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented

CONSTRUCTION DOCUMENTS

QUALITY REQUIREMENTS 01 4000 – 4

according to ASTM E 329; and with additional qualifications specified in individual Sections;

and, where required by authorities having jurisdiction, that is acceptable to authorities.

1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.

2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory

Accreditation Program.

H. Manufacturer's Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that…