2--3- 1.4 Section 2 Document 3.0 Schedule of Values.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
SLCo FAC133242 ADC Heat Exchangers – Final Phase- CONST
Solicitation number
SLCo FAC133242 ADC Heat Exchangers – Final Phase- CONST
Issued by
Utah

About this file

This is a Schedule of Values document for a construction project in Utah identified as FAC133242, concerning the replacement of heat exchangers at an ADC facility. The document serves as the bidding template for contractors to submit their proposed costs across multiple bid categories including base bid and three alternates, with supporting cost elements for Payment and Performance Bond, Insurance and Builder's Risk, and Division 01-General Conditions. The project requires bidders to specify their entire work scope and provide itemized pricing for each division of work, with all totals required to match amounts previously entered into the Online Solicitation System (OSS).

The Schedule of Values currently displays placeholder values of $0 across all bid categories and line items, indicating that this is a blank template awaiting contractor submissions. Bidders must complete the spreadsheet with their proposed costs for the base bid and each alternate, ensuring that final totals correspond exactly with amounts submitted through the OSS. The document includes a designated space for the bidding company name and references Section 2, Document 3.0 of the project documentation. All pricing must align with the project manual and plans that detail the scope of heat exchanger replacement work to be performed.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Section 2 - Document 3.0
Schedule Of Values
Project: FAC133242 ADC Heat Exchangers – Final Phase
Divisions of WorkBase BidAlternate 1Alternate 2Alternate 3
(Specify entire work scope; examples are listed below)Alternate CTotal
Payment & Performance Bond$ - 0$ - 0$ - 0$ - 0$ - 0
Insurance & Builder's Risk$ - 0$ - 0$ - 0$ - 0$ - 0
Division 01-General Conditions$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0
$ - 0$ - 0$ - 0$ - 0
Totals (Enter in OSS)$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
The total for the base bid must be the same total that was entered into the Online Solicitation System (OSS).
The total for each alternate must be the same total that was entered into the Online Solicitation System (OSS)
Name of Company Bidding ________________________________

Sheet2

Sheet3

File details come from the government source that posted it. Updated .