8-3. Price Form.pdf
PDF 100 KB Posted
- Attached to
- Boulder Community Hub Solar PV System
- Solicitation number
- RFP-306-26
- Issued by
- Boulder County, Colorado
About this file
This is a Price Form document for Boulder County, Colorado's procurement process for the Boulder Community Hub Solar PV System project. Boulder County is soliciting proposals from qualified contractors to design, fabricate, deliver, install, and maintain a rooftop utility-interactive solar photovoltaic system with a maximum capacity of 100 kW. The project scope encompasses all work described in the specifications and addenda, with site work anticipated to begin in the fourth quarter of 2026. Contractors are required to submit pricing for the total system cost, including system size specifications in both direct current (DC) and alternating current (AC), estimated annual production in kilowatt-hours (kWH), and cost per watt (AC).
The price form requires contractors to provide two separate line items: Item #1 for the total system cost with duration in working days, and Item #2 for two-year operations and maintenance (O&M) costs. Contractors may propose alternate system designs on a separate page, noting any impacts on cost or project timing. Larger capacity systems exceeding the 100 kW minimum will only be evaluated as alternatives. All pricing submissions must follow Boulder County's established submittal instructions, and prospective bidders with questions should contact procurement@bouldercounty.gov.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Boulder County Procurement 1325 Pearl Street
Boulder, CO 80302
RFP PRICE FORM
Provide a price for one and/or each item as listed below. All work described in the Specifications and Addenda for this project:
Proposed System Cost
System Size (DC)
System Size (AC)
Estimated Annual Production (kWH)
Cost - $$/Watt
(AC)
ITEM #1 – Total System Cost:
__________________________________________________dollars ($____________________)
Duration_____________________________________ Working Days
ITEM #2 – Two-Year O&M:
__________________________________________________dollars ($____________________)
Alternates: Provide a separate page for any proposed alternates, with description of alternate and any impact on cost or timing of work.
| Proposed System CostRow1: |
| System Size DCRow1: |
| System Size ACRow1: |
| Estimated Annual Production kWHRow1: |
| Cost Watt ACRow1: |
| dollars: |
| undefined: |
| Working Days: |
| dollars_2: |
| undefined_2: |
File details come from the government source that posted it. Updated .