7b) Infection Control Risk Assessment (ICRA) bldg128.pdf

PDF 288 KB Posted

Attached to
Z1DA--578-23-010 (CON) Roof Repairs - Bldgs 113, 128, & 220
Solicitation number
36C25223B0026
Issued by

About this file

This document is an Infection Control Risk Assessment for roof repair projects at several buildings on a Veterans Affairs medical center campus. The assessment identifies construction activities by risk group based on dust level and scope of work. It provides contractors with actions required for each project class, including isolating work areas, installing barriers, maintaining negative air pressure, conducting cleaning procedures, and obtaining necessary approvals.

The related federal contract opportunity is a solicitation from the Department of Veterans Affairs for roof repairs at buildings 113, 128, and 220 on Veterans Integrated Service Network 12's campus. Solicitation number 36C25223B0026 corresponds to work order 578-23-010 for the project. The start date is listed as November 1, 2023 and projected completion is May 1, 2024.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infection Control Risk Assessment for Construction / Renovation Projects Project Name: Roof Repairs - Buildings 113,128, & 220 Project or Work-Order Number: 578-23-010

Project Manager or COR: Samir Qaisar Extension: 21153

Building Number: 128 Floor(s)/Room(s):

Start date: November 1, 2023 Projected completion date: May 1, 2024

Construction Activity Infection Control Risk Group

☒ TYPE A: DUST LEVEL Low

Non-invasive activity, low noise, no vibration.

☐ GROUP 1: LOW

Office areas, FMS areas, all non-patient care areas.

☐ TYPE B: DUST LEVEL: Moderate to High

Small scale, short duration, low-moderate noise, low-moderate vibration.

☒ GROUP 2: MEDIUM

All other patient care areas including general medicine floors, ultrasound, Rehab, Occupational Therapy.

☐ TYPE C: DUST LEVEL Moderate to High

Requires more than one work shift (independent of working days) to complete, low-moderate noise, moderate–high vibration

☐ GROUP 3: MEDIUM/HIGH

ED, Radiology/MRI, admissions, food service areas, laboratories.

☐ TYPE D: DUST LEVEL High

Major demolition and construction activities. Requires consecutive work shifts, moderate-high noise, moderate-high vibration

☐ GROUP 4: HIGHEST

Operating rooms, SPS, ICU’s, Outpatient areas, oncology, anesthesia, post anesthetic recovery, all endoscope areas, Pharmacy, Renal Dialysis

Project Class Determination Matrix Construction Activity Type →

Risk Group

Type

“A”

Type

“B”

Type

“C”

Type

“D”

Group 1 I II II III

Group 2 I II III IV

Group 3 I III III IV

Group 4 III IV IV IV Contractors Actions by Project Class

All personnel will have Emergency Preparedness training/posting/ID card.

CLASS

I

1. Execute work to minimize air-borne dust dispersed into atmosphere from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Contain construction waste before transport in tightly covered containers.

4. Clean work area upon completion of task including wiping surfaces with disinfectant.

5. Contact EMS for appropriate preparation for return to operation(s).

CLASS

II

In addition to above:

6. Post the signed ICRA at the entrance.

7. Isolate work area from patients/staff. Use appropriate temporary barriers and more permanent containment methods (i.e., seal holes in walls, tape gaps in doors, etc.)

8. Water mist work surfaces to control dust while cutting.

9. Block off and seal supply air vents. Place filter over return/exhaust vents.

10. Place dust mat or wipe feet at entrance/exit of work area.

11. Wet mop and/or vacuum w/HEPA filtered vacuum before leaving work areas.

CLASS

III

In addition to above:

12. Install barriers to create a negative pressure ante room and/or workroom.

13. Maintain negative air pressure in work area at all times until completion utilizing HEPA-equipped air filtration units.

14. Vacuum personnel with HEPA vacuum before leaving. Or, Don-Doff coveralls each time leaving work site. All wear shoe covers changed each time exiting the area.

15. Vacuum the entire work area with HEPA vacuums or wet mop with disinfectant at the completion of project.

16. Do not remove barriers until completed project is inspected by Safety, IC-Team, EMS, and Area Manager.

17. Carefully remove barriers to minimize spread of dirt and debris. Contact EMS for final clean.

CLASS

IV

In addition to above:

18. Provide a disinfectant wipe down of any tool carts or waste transports prior to leaving the containment area.

19. Do not remove barriers until terminal clean is performed inside work zone and barriers are included in the cleaning process.

20. Perform 2nd terminal cleaning after removal of barriers. Contact EMS for final clean.

Signatures Date

Contractor’s Signature:

(Projects Only)

Project Planner or

Maintenance Worker Signature:

Supervisor Signature:

Infection Control:

VHAHINFraidR Typewritten Text 05/08/2023

2023-05-05T11:48:00-0500
SAMIR M. QAISAR 3518076
2023-05-05T17:27:26-0500
SUJA M. MATHEW 394079
2023-05-08T12:01:38-0500
Richard F Fraider 3548196