This document is a Standard Form 30 (SF30) Amendment to Solicitation/Modification of Contract for the TPPIHC Roof Replacement and Fall Protection project (Solicitation 75H701-25-R-00037). Amendment A00003 makes several key modifications: 1) Provides Pre-Proposal Inquiries 1-9 spanning 3 pages, with no additional inquiries to be accepted unless the Government determines a response is necessary, 2) Revises SF-1442 to extend the proposal due date to April 01, 2025, at 2:00 PM MST, 3) Updates the Wage Determination attachment J02 dated 03/07/2025, and 4) Extends the proposal submission deadline from March 26, 2025, to April 01, 2025.
The amendment is issued by the Indian Health Service Division of Engineering Services (DES) in Seattle for a roof replacement and fall protection project at the Taos-Picuris Pueblos Indian Health Center. Offerors must acknowledge receipt of the amendment by completing specific items on the form or by separate letter/electronic communication referencing the solicitation and amendment numbers. The notice emphasizes that failure to acknowledge the amendment prior to the specified hour and date may result in offer rejection, and contractors are not required to sign and return the document to the issuing office.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A00003
Jennifer J. Scroggins
See the following SF30 continuation page.
Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
75H701-25-R-00037
03/25/2025
02/19/2025
SF30 CONTINUATION OF BOX 14.
Solicitation 75H701-25-R-00037 Amendment A00003 TPPIHC Roof Replacement and Fall Protection
SUMMARY OF CHANGES:
Amendment A00003 to solicitation 75H701-25-R-00037 hereby addresses the following:
1. Provides Pre-Proposal Inquiries 1 through 9; 3 pages. No additional Pre-Proposal Inquiries will be accepted unless the Government determines a response is necessary and practicable.
2. Revises SF-1442, extending the proposal due date until April 01, 2025, by 2:00 PM MST;
3. Updates attachment J02 Wage Determination, dated 02/07/2025 with J02 Wage Determination, dated 03/07/2025.
4. Extends the proposal due date/time from March 26, 2025, at 2:00 PM MST to April 01, 2025, at
2:00 PM MST.
NOTICE TO OFFERORS: Offerors must acknowledge receipt of any and all amendments by number and date on their cover letter in their offer or by submitting a signed copy of the SF30. All other terms and conditions remain unchanged.
END SUMMARY OF CHANGES
Amendment A00003 under Solicitation 75H701-25-R-00037 TPPIHC Roof Replacement and Fall Protection
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00037
TPPIHC Roof Replacement and Fall Protection
Item No. COMMENTS IHS Approved Response
1. Item 2 under 1.1 Summary, Sub-part A, Roof Layup, calls out structural metal deck, 4” polyisocyanurate insulation adhered, ½” cover-board adhered, and adhered PVC. Detail’s 3, 4, & 5 on A4.3 and Details 1, 3, & 4 on A4.4 all call out new underlayment, new insulation, new coverboard mechanically fastened thru insulation into steel deck and fully adhered 60 mil PVC roofing. Is a thermal barrier required under the iso, coverboard, and PVC roofing?
Is an initial layer of ½” glass mat gypsum board required over the metal deck, but under the iso and glass mat gypsum cover-board as is noted in many of the roof details?
No. Disregard reference to new underlayment between existing steel roof deck and new polyiso insulation board.
2. Are new nailer and coping to be installed at the short parapet walls of the north entry canopy to provide additional flashing height? The current metal cap is screwed through the horizontal portion and is not a warrantable condition as is.
Attached are highlighted Roof Plan and photos of west and east entry coping conditions. (See, Attachment IHS Taos Roof Plan)
Yes, include work required for warrantable condition.
3. Solicitation, Page 7 of 59, Section V.B On-site work hours:
Working hour limitations may be imposed by the COR upon the Contractor at the Pre-construction conference or during construction. Work hour limitations would extend the project duration and increase costs. Will the Government modify the contract to address this.
Proposed work hours are to be based on the solicitation clause H.1. WORK HOURS. Any restrictions imposed by IHS that impact price/period of performance will be handled post-award via contract clause H.39. EQUITABLE
ADJUSTMENTS DUE TO CHANGES.
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00037
TPPIHC Roof Replacement and Fall Protection
4. Low voc glue for roofing materials.
Fasteners will need to be adhered to the TPO for the lightning protection, the roofers will need glue to adhere their roofing materials if mechanically fastened method is not an option There were numerous conduits installed in the upper portion of the pro panel roof decking- this poses a high potential of conduits getting hit with the fasteners and causing power outage
Roofing system may be fully adhered. Confirm wind speed rating requirements are met.
5. Attachment point for lightning protection to the TPO material.
We need to know if the lightning protection wires will need to be reinstalled over the new TPO surface and where? The Manufacturer will need to approve the installation process for warranty reasons.
Yes. Our assumption is that routing will match existing configuration. Completed system requires UL Master Label recertification.
6. Do all garden walls get stucco installed There are multiple ‘garden walls’ that are stucco’ d throughout the site. Are these all to get redone? See Attachment Garden Walls_Taos.
Yes.
7. Do they want to go under existing Z-Metal flashing or install new?
The new roof will be terminated on the parapet walls under the existing Z-Metal flashing, which will require bending the metal flashing in order to install the new roofing material. The Z-Metal will still have functionality after installation but will not look the same due to having to bend during roof installation. The other option will be installing new z-metal flashing during the roofing process and prior to stucco installation.
We assume and recommend all new flashing/reglet/counterflashing at roof side of parapet walls.
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00037
TPPIHC Roof Replacement and Fall Protection
8. On sheet A4.3, details 5 and 6, it shows the air terminal base being secured to the roof using single-ply sealant. NFPA 780 4.9.3 states "Roofing membrane strapped over the conductor shall not be considered a suitable fastener." Please provide code compliant detail for attachment. Air terminals.
We are unsure how the language of this NFPA excerpt applies to the detail in question. Installation details that are compatible and compliant are ultimately the responsibility of the general contractor and the lightning protection subcontractor.
9. We intend to use PPQs from RFPs we submitted on within the last year as a part of this proposal. These would be the same format as those attached to the solicitation. I just don't want to bother the folks who were kind enough to fill these out a few months ago and want to confirm this is acceptable with ya'll when evaluating our proposal.
Yes, that is okay. It’s when PPQs are “incorporated by reference” within proposals that are not acceptable.
"General Decision Number: NM20250031 03/07/2025
Superseded General Decision Number: NM20240031
State: New Mexico
Construction Type: Building
Counties: Cibola, Guadalupe, Harding, Mora, Quay and Taos Counties in New Mexico.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on |
3/24/25, 11:58 AM SAM.gov https://sam.gov/wage-determination/NM20250031/3 1/9
| | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025 1 01/24/2025 2 02/07/2025 3 03/07/2025
CARP1245-003 06/01/2018
Quay
Rates Fringes
Carpenter Drywall Hanging Only........$ 24.08 10.79
CARP1319-006 01/01/2025
Cibola
Rates Fringes
CARPENTER
Drywall Hanging Only........$ 27.31 13.18
CARP1353-008 06/01/2018
Guadalupe, Harding, Mora, and Taos
Rates Fringes
CARPENTER
Drywall Hanging Only........$ 24.08 10.79
ELEC0611-019 01/01/2024
https://sam.gov/wage-determination/NM20250031/3 2/9
Rates Fringes
ELECTRICIAN
Zone 1......................$ 38.30 12.98
ZONE 1: Mileage calculated from the main post office in the following towns: Albuquerque-40 miles, Artesia-12 miles, Belen-12 miles, Carlsbad-12 miles, Carrizozo-12 miles, Clovis-12 miles, Espanola-14 miles, Farmington-6 miles, Gallup-10 miles, Hobbs-12 miles, Las Vegas-8 miles, Los Lunas-12 miles, Lovington-12 miles, Portales-12 miles, Raton-6 miles, Roswell-12 miles, Ruidoso-12 miles, Santa Fe-10 miles, Tucumcari-6 miles.
ZONE 2: Extending up to 20 miles beyond Zone 1, EXCEPT ALBURQUERQUE, shall receive 9% above Zone 1 rate.
ZONE 3: Extending up to 30 miles beyond Zone 1, EXCEPT ALBURQUERQUE, shall receive 15% above Zone 1 rate.
ZONE 4: Extending more than 30 miles beyond Zone 1, EXCEPT ALBURQUERQUE, shall receive 26% above Zone 1 rate.
ENGI0953-008 01/01/2024
Rates Fringes
Power Equipment Operator
(2) Roller(Dirt and Grade Compaction).................$ 26.75 4.65
(4) Bobcat/Skid Loader......$ 27.70 4.65
IRON0495-010 01/01/2023
Rates Fringes
IRONWORKER, STRUCTURAL AND
ORNAMENTAL.......................$ 28.05 18.11
LABO0016-005 06/01/2024
Rates Fringes
Laborer, Mason Tender Brick (3).........................$ 23.69 7.89
PAIN0823-007 01/01/2023
https://sam.gov/wage-determination/NM20250031/3 3/9
Rates Fringes
PAINTER: Brush and Roller, Excludes Drywall Finishing/Taping.................$ 18.25 8.80
* PLUM0412-007 01/02/2025
Rates Fringes
PIPEFITTER (Including HVAC Pipe Installation)...............$ 43.07 16.60 PLUMBER (Excluding HVAC Pipe Installation)....................$ 43.07 16.60
SHEE0049-012 01/01/2024
Rates Fringes
Sheet Metal Worker (HVAC Duct and System Installation Only)....$ 37.50 18.51
* SUNM2010-019 11/09/2010
Rates Fringes
ACOUSTICAL CEILING MECHANIC......$ 12.00 ** 0.00
BOILERMAKER......................$ 21.77 3.98
BRICKLAYER.......................$ 20.80 5.10
CARPENTER (Batt Insulation Only)............................$ 26.07 5.96
CARPENTER (Form Work Only).......$ 18.80 5.61
CARPENTER, Excludes Acoustical Ceiling Installation, Batt Insulation, Drywall Hanging, and Form Work....................$ 19.27 4.29
CEMENT MASON/CONCRETE FINISHER...$ 16.27 ** 3.94
DRYWALL FINISHER/TAPER...........$ 18.34 4.38
FLOOR LAYER: Carpet.............$ 18.05 4.49 https://sam.gov/wage-determination/NM20250031/3 4/9
GLAZIER..........................$ 20.15 3.63
IRONWORKER, REINFORCING..........$ 19.75 8.71
LABORER: Asphalt Raker..........$ 10.25 ** 0.00
LABORER: Common or General......$ 12.99 ** 3.56
LABORER: Landscape & Irrigation.......................$ 12.42 ** 1.47
LABORER: Mason Tender - Cement/Concrete..................$ 11.51 ** 0.85
LABORER: Pipelayer..............$ 13.78 ** 2.20
OPERATOR: Backhoe...............$ 18.79 3.47
OPERATOR: Crane.................$ 24.38 4.60
OPERATOR: Forklift..............$ 20.86 4.60
OPERATOR: Grader/Blade..........$ 20.33 4.94
OPERATOR: Loader (Front End)....$ 19.76 4.84
PAINTER: Spray (Excludes Drywall Finishing/Taping)........$ 15.47 ** 2.09
PLASTERER........................$ 17.65 ** 5.29
ROOFER...........................$ 18.84 0.00
SHEET METAL WORKER, Excludes HVAC Duct and Unit Installation.....................$ 22.01 9.65
SPRINKLER FITTER (Fire Sprinklers)......................$ 20.00 4.16
TILE FINISHER....................$ 14.02 ** 0.00
TILE SETTER......................$ 14.30 ** 1.02
TRUCK DRIVER: Dump Truck........$ 11.00 ** 0.00
TRUCK DRIVER: Pickup Truck......$ 15.91 ** 3.13 https://sam.gov/wage-determination/NM20250031/3 5/9
TRUCK DRIVER: Water Truck.......$ 15.16 ** 4.69
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.75) or 13658 ($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular https://sam.gov/wage-determination/NM20250031/3 6/9 rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 https://sam.gov/wage-determination/NM20250031/3 7/9
6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division https://sam.gov/wage-determination/NM20250031/3 8/9
U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"