75H70126Q00030-A00001.pdf

PDF 603 KB Posted

Attached to
S. DeGoede Well (COW)
Solicitation number
75H7012
Issued by

About this file

This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) for solicitation 75H701-26-Q-00030, Amendment A00001, issued by Indian Health Services (IHS) Division of Engineering Services (DES) in Dallas, Texas on August 5, 2026. The amendment pertains to Project No. PO-21-C87, S. DeGoede Well (COW).

The amendment provides government responses to three contractor questions received via email regarding the well drilling project and supplies three previously missing attachments: Local Well Logs, Pump Test Field Data Recording Form, and Water Quality Testing Requirements. In response to inquiries about anticipated well depth and ground composition, the government references the Statement of Work, indicating that existing well logs from surrounding areas are provided and the contractor is responsible for locating additional local well logs and investigating the site. Regarding utility surveys, the government clarifies that the proposed well location is indicated in the drawings and the contractor is responsible for determining the exact location of all utilities and protecting them from damage. Regarding depth limitations, the government states the Contracting Officer Representative will discuss with the Contracting Officer/Contracting Officer's Representative if drilling approaches or exceeds the 400-foot capability mark and will likely either grant permission or direct cessation of work. The proposal submission date remains unchanged at August 18, 2026 at 2:00 p.m. CST. Offerors must acknowledge receipt of this amendment by number and date on their cover letter or by submitting a signed copy of the SF30. All other terms and conditions remain unchanged and in full effect.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

4. REQUISITION/PURCHASE REQ. NO.

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED 16C. DATE SIGNED

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

2. AMENDMENT/MODIFICATION NO.

A00001

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project No. PO-21-C87, S. DeGoede Well (COW), Amendment A00001.

1. The purpose of this amendment is to provide the following: Government responses to the contractor's questions received-in, via email to the solicitation, page 2, as well as provide the three (3) missing Attachments: 1- Local Well Logs; 2-Pump Test Field Data Recording Form; and 3-Water Quality Testing Requirements.

2. The solicitation's proposal date remains unchanged at August 18, 2026 @ 2:00pm CST.

3. All other terms and conditions remain unchanged and in full effect.

Indian Health Services (IHS) Division of Engineering Services (DES) - Dallas 1301 Young Street, Suite 106-840 Dallas, TX 75202-5433

Indian Health Services (IHS) Division of Engineering Services (DES) - Dallas 1301 Young Street, Suite 106-840 Dallas, TX 75202-5433

10A. MODIFICATION OF CONTRACT/ORDER NO.

5. PROJECT NO. (If applicable)

PO-21-C87

PAGE OF PAGES

10B. DATED (SEE ITEM 13)

3. EFFECTIVE DATE

8-5-2026

75H701-26-Q-00030

7/16/2026 is not extended.

One (1)

X

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

X X

ROBERT S. MILLER

romiller Cross-Out

S. DeGoede Well (COW) Solicitation No.: 75H70126Q00030 A00001

Contractor Questions and Government Responses (bolded below), Dated 5 August 2026, S. DeGoede

Well (COW):

1. I am wondering the anticipated depth of the well. Is there any geographical data or something similar that outlines what depth we may find water? I am also curious of the ground composition as Samantha has told me that 10-20 feet down, we may begin to hit solid rock. Any clarification on this matter would be greatly appreciated?

Answer: Statement of Work, A. Project Description: “Existing well logs from the surrounding area are provided (see Attachments). Further investigation of the site and locating other local well logs is the responsibility of the Contractor.”

2. Has the ground already been surveyed? I ask this only because I do not want the sub-contractor we choose to go out there and start drilling blindly as they may hit a water line or some other underground pipes/wiring?

Answer: Statement of Work, D. Scope of Work: “The proposed well location is indicated in the drawings.” AND Statement of Work, E. Scope of Work, 4. Work Execution Requirements, iii.: “The

Contractor is responsible for determining the exact location of any and all utilities. The Contractor is responsible for protecting utilities from damage during construction.”

3. I spoke to Samantha and she says some of the neighbors up there have wells that have ranged from 250ft-

450ft. The contract says to have capability to go 400ft. Will we need to get approval from you if we end up having to go past our 400ft mark?

Answer: COR will discuss with CS/CO, at time of occurrence/when getting close, and more than likely either give permission or tell to stop.

*As stated within the solicitation, inquiries (questions) must be received no later than 2:00pm CST on 11

August 2026 to allow time for response(s). After which, no further questions are guaranteed to be answered*

NOTICE TO OFFERORS: Offerors must acknowledge receipt of any and all amendments by number and date on their cover letter in their offer or by submitting a signed copy of the SF30. All other terms and conditions remain unchanged.

Standard Detailed Drawings WPS Enclosure.pdf
WELL-Model.pdf
Sheets and Views
Model
ADP2A03.tmp
M96 Bid Abstract
ADP675E.tmp
Bid Schedule
B05 PLANSET - Miller Heights Sewer Main Replacement (Revised 3-1-2021) (signed).pdf
Sheets and Views
Miller Heights sewer main030121-COVER & LOCATION
Miller Heights sewer main030121-11x17 Notes and Legend
Miller Heights sewer main030121-11X17 Abbreviations
Miller Heights sewer main030121-PROPOSED
Miller Heights sewer main030121-DETAILS
Miller Heights sewer main030121-DETAILS (2)
B05 TECHNICAL SPECIFICATIONS - Miller Heights Sewer Replacement (revised 3-1-2021) (signed).pdf
00 01 01 Project Title Page
CONFEDERATED TRIBES OF WARM SPRINGS
INDIAN RESERVATION
JEFFERSON COUNTY, OREGON
CONTRACT DOCUMENTS
INDIAN HEALTH SERVICE
OFFICE OF ENVIRONMENTAL HEALTH
AND ENGINEERING
PORTLAND AREA OFFICE
WESTERN OREGON FIELD OFFICE
FEBRUARY 2020
00 01 10 Table of Contents - 20-M96
VOLUME I
Division 00 – Procurement and Contracting Requirements
Division 01 – General Requirements
Division 31 – Earthwork
Division 33 – Utilities
01 11 00 Summary of Work - 20-M96
PART 1 - GENERAL
1.01 SUMMARY
A. The work to be performed under this contract shall consist of furnishing the following to perform the work outlined in these specifications and as indicated by Project Drawings:
B. Location of Work: Warm Springs, Warm Springs Reservation, Jefferson County, Oregon
C. Incidentals Items: All work, materials, and services not expressly listed as being provided by others or not expressly called for in the contract but are necessary for the completion of the work in good faith, shall be furnished, installed, and per...
1.02 WORK REQUIRED
A. Furnish all labor, materials, equipment, and supervision necessary to construct the following facilities as described by these specifications and drawings. All work, materials, and services not expressly listed as being provided by others or that a...
B. Description of Work: This project proposes to make specific improvements to the Miller Heights Community Sewage Collection System. The proposed improvements include: 1. Cleanup of soils contaminated with raw sewage. 2. Replacement of failed 8” wo...
3. Install adapters and necessary pipe support structures to firmly connect the new 8” PVC sewer main to the existing manholes.
C. Sewer Main Replacement is shown on the drawings.
1.03 SITE CONDITIONS
A. Utilities
1. Known buried utilities are shown on the drawings as an indication as to what the contractor may encounter, NOT FOR LOCATION PURPOSES. Locations, material, and sizes of any shown are approximate and not meant as a complete representation. Contractor...
a. Water and Sewer, Warm Springs Public Works, https://warmsprings-nsn.gov/program/public-utilities-branch/
2. Protect existing utilities during construction.
3. Immediately notify project engineer and the utility owner of any damaged utilities.
4. Any and all damage that results from work under this contract shall be promptly repaired at the expense of the Contractor (exception is utilities owned and located incorrectly by the Tribe. Contractor will repair damage and be reimbursed for costs.)
B. Roads 1. Oregon Department of Transportation 63055 North Highway 97, Bldg. K Bend, OR 97703 Aaron Smith – ODOT Dist. 10 Permits Phone: (541)-388-6054 63055 N Hwy 97, Bldg. K Bend, OR 97703 aaron.k.s...
2. Bureau of Indian Affairs, https://www.bia.gov/regional-offices/northwest/warm-springs-agency
3. Warm Springs Public Works, https://warmsprings-nsn.gov/program/public-utilities-branch/
C. Tribal Employment Rights Ordinance (TERO) 1. Contractor must comply with the Warms Springs TERO. Visit https://warmsprings-nsn.gov/program/tribal-employment-rights-office/ to contact Warm Springs TERO and obtain the necessary forms.
D. Rights-of-Way 1. All the work will be performed within existing rights-of-way of the Warm Springs Tribe.
E. Site Ownership 1. The construction site is entirely located inside the Warm Springs Indian Reservation and on the land controlled by the Warm Springs Tribe.
1.04 SEQUENCE OF WORK
A. The Contractor shall construct in phases or stages to accommodate continuous and uninterrupted operation of the existing facility. The Contractor shall coordinate the construction schedule and operations with the Project Engineer. The contractor sh...
01 27 00 Price & Payment - 20-M96
PRICE AND PAYMENT
PART 1 - GENERAL
PART 2 – BID SCHEDULE ITEMS
A. SCHEDULE
1. Mobilization:
2. ODOT Permitting and Traffic Control:
3. Removal and Disposal of Contaminated Soils:
4. Temporary Erosion and Sediment Control:
5. Temporary Sewage Bypass Pumping:
6. Connections to Existing Manholes:
7. PVC Sanitary Sewer Pipe, 8 In. Diam.:
8. Fencing Repairs and Site Restoration:
01 31 00 Project Management and Coordination - 20-M96
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
END OF SECTION
01 33 00 Submittal Procedures - 20-M96
SUBMITTAL PROCEDURES
PART 1 - GENERAL
END OF SECTION
01 42 00 References - 20-M96
REFERENCES
PART 1 - GENERAL
B. Federal Agencies
C. State Agencies
END OF SECTION
American Association of State Highway and
American Water Works Association (AWWA)
01 43 00 Quality Assurance-Quality Control - 20-M96
QUALITY ASSURANCE/QUALITY CONTROL
PART 1 - GENERAL
END OF SECTION
01 50 00 Temporary Facilities and Controls - 20-M96
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
PART 2 – PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION
END OF SECTION
01 77 00 Closeout Procedures - 20-M96
CLOSEOUT PROCEDURES
PART 1 - GENERAL
END OF SECTION
01 78 00 Closeout Submittals - 20-M96
CLOSEOUT SUBMITTALS
PART 1 - GENERAL
PART 2 – PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION
END OF SECTION
31 23 10 Excavation,Trenching, & Backfill - 20-M96
SECTION 31 23 10
EXCAVATION, TRENCHING AND BACKFILL
PART 1 - GENERAL
A. This section includes excavation, trenching and backfill necessary for the construction of the facilities as indicated on the plans including, but not limited to concrete sewer manholes, piping, and other structures.
1.05 QUALITY ASSURANCE
PART 2 – PRODUCTS
PART 3 - EXECUTION
END OF SECTION
31 25 00 Erosion and Sediment Control - 20-M96
PART 1 - GENERAL
PART 2 - PRODUCTS
Sieve Size Percent Passing
PART 3 – EXECUTION
END OF SECTION
33 01 31 Temporary Sewer Bypass - 20-M96
TEMPORARY SEWER BYPASS
PART 1 - GENERAL
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION
33 30 00 Sanitary Sewerage - 20-M96
SANITARY SEWERAGE
PART 1 - GENERAL
PART 2 - PRODUCTS
A. Manholes:
1. Concrete compressive strength will meet or exceed 4000 pounds per square inch at 28 days.
B. Sewer Pipe Connection:
1. Connect pipes using a rigid watertight pipe adapter gasket conforming to ASTM C1173 and ASTM D5926.
2. Gasket
a. Manufactured to meet the material requirements of:
1) ASTM C1173 - Flexible Transition Couplings for Underground Piping Systems
2) ASTM D5926 – Poly (Vinyl Chloride) (PVC) Gaskets for Drain, Waste, and Vent (DWV), Sewer, Sanitary, and Storm Plumbing Systems
3) CSA B602 - Mechanical Couplings for Drain, Waste, Vent Pipe and Sewer Pipe
3. Clamps
a. Manufactured to meet the material requirements of:
1) CSA B602 - Mechanical Couplings for Drain, Waste, Vent Pipe and Sewer Pipe
4. Shear Ring
a. Length manufactured according to coupling diameter.
b. Clamps spot welded in place.
5. Couplings
a. Manufactured to conform to the performance requirements of:
1) ASTM C1173 - Flexible Transition Couplings for Underground Piping Systems
2) CSA B602 - Mechanical Couplings for Drain, Waste, Vent Pipe and Sewer Pipe
b. Maximum Test Pressure: 4.3 PSI
c. Maximum Operating Temperature: 140 F non-consistent
PART 3 - EXECUTION
END OF SECTION
00 01 01 Project Title Page.pdf
CONFEDERATED TRIBES OF WARM SPRINGS
INDIAN RESERVATION
JEFFERSON COUNTY, OREGON
CONTRACT DOCUMENTS
INDIAN HEALTH SERVICE
OFFICE OF ENVIRONMENTAL HEALTH
AND ENGINEERING
PORTLAND AREA OFFICE
WESTERN OREGON FIELD OFFICE
FEBRUARY 2020
01 11 00 Summary of Work - 20-M96.pdf
PART 1 - GENERAL
1.01 SUMMARY
A. The work to be performed under this contract shall consist of furnishing the following to perform the work outlined in these specifications and as indicated by Project Drawings:
B. Location of Work: Warm Springs, Warm Springs Reservation, Jefferson County, Oregon
C. Incidentals Items: All work, materials, and services not expressly listed as being provided by others or not expressly called for in the contract but are necessary for the completion of the work in good faith, shall be furnished, installed, and per...
1.02 WORK REQUIRED
A. Furnish all labor, materials, equipment, and supervision necessary to construct the following facilities as described by these specifications and drawings. All work, materials, and services not expressly listed as being provided by others or that a...
B. Description of Work: This project proposes to make specific improvements to the Miller Heights Community Sewage Collection System. The proposed improvements include: 1. Cleanup of soils contaminated with raw sewage. 2. Replacement of failed 8” wo...
3. Install adapters and necessary pipe support structures to firmly connect the new 8” PVC sewer main to the existing manholes.
C. Sewer Main Replacement is shown on the drawings.
1.03 SITE CONDITIONS
A. Utilities
1. Known buried utilities are shown on the drawings as an indication as to what the contractor may encounter, NOT FOR LOCATION PURPOSES. Locations, material, and sizes of any shown are approximate and not meant as a complete representation. Contractor...
a. Water and Sewer, Warm Springs Public Works, https://warmsprings-nsn.gov/program/public-utilities-branch/
2. Protect existing utilities during construction.
3. Immediately notify project engineer and the utility owner of any damaged utilities.
4. Any and all damage that results from work under this contract shall be promptly repaired at the expense of the Contractor (exception is utilities owned and located incorrectly by the Tribe. Contractor will repair damage and be reimbursed for costs.)
B. Roads 1. Oregon Department of Transportation 63055 North Highway 97, Bldg. K Bend, OR 97703 Aaron Smith – ODOT Dist. 10 Permits Phone: (541)-388-6054 63055 N Hwy 97, Bldg. K Bend, OR 97703 aaron.k.s...
2. Bureau of Indian Affairs, https://www.bia.gov/regional-offices/northwest/warm-springs-agency
3. Warm Springs Public Works, https://warmsprings-nsn.gov/program/public-utilities-branch/
C. Tribal Employment Rights Ordinance (TERO) 1. Contractor must comply with the Warms Springs TERO. Visit https://warmsprings-nsn.gov/program/tribal-employment-rights-office/ to contact Warm Springs TERO and obtain the necessary forms.
D. Rights-of-Way 1. All the work will be performed within existing rights-of-way of the Warm Springs Tribe. Use of Oregon DOT right-of-way to access site shall be coordinated with ODOT.
E. Site Ownership 1. The construction site is located inside the Warm Springs Indian Reservation along a utilities easement owned by the Warm Springs Tribe. The site access along OR HWY 26 requires permitting and coordination with ODOT.
1.04 SEQUENCE OF WORK
A. The Contractor shall construct in phases or stages to accommodate continuous and uninterrupted operation of the existing facility. The Contractor shall coordinate the construction schedule and operations with the Project Engineer. The contractor sh...
01 27 00 Price & Payment - 20-M96.pdf
PRICE AND PAYMENT
PART 1 - GENERAL
PART 2 – BID SCHEDULE ITEMS
A. SCHEDULE
1. Mobilization:
2. ODOT Permitting and Traffic Control:
3. Removal and Disposal of Contaminated Soils:
4. Temporary Erosion and Sediment Control:
5. Temporary Sewage Bypass Pumping:
6. Connections to Existing Manholes:
7. PVC Sanitary Sewer Pipe, 8 In. Diam.:
8. Fencing Repairs and Site Restoration:
ADPB9F1.tmp
Sheet2
ADP8A0B.tmp
Sheet2