1-Statement of Work.docx
DOCX document 34 KB Posted
- Attached to
- S. DeGoede Well (COW)
- Solicitation number
- 75H7012
About this file
This is a Statement of Work for the installation of a residential drinking water well at 297 DeGoede Dr., Mossyrock, WA 98564, in Lewis County, for homeowner Samantha DeGoede (samonella_b@hotmail.com; 360-269-5750). The project, designated PO-21-C87, is being executed under solicitation number 75H7012 by the Department of Health and Human Services Indian Health Service on behalf of the Cowlitz Tribe. The contractor shall drill a 6-inch well to an estimated depth of 400 feet, install welded steel casing, PVC liner as needed, sanitary seal, well screen as needed, and perform well development, test pumping, disinfection, and water quality sampling and testing. Upon completion, the well system will transfer to the homeowner for private operation. Work must be completed within 60 calendar days from the Notice to Proceed and comply with Washington Administrative Code Chapter 173-160 and Indian Health Service Technical Provisions.
The contractor is responsible for all permitting, including Department of Ecology Notice of Intent; site investigation and local well log research; utility location and protection; debris removal; site grading; and obtaining pre-construction approval. Required submittals include drilling method and mud containment details (if applicable), well casing specifications, well liner details, and post-construction water quality analysis and pumping test results. The contractor must contact the Contracting Officer's Representative (Jennifer Toth, jennifer.toth@ihs.gov) 48 hours prior to mobilization and attend a mandatory pre-construction meeting. All work must comply with specified codes and standards, with material substitutions requiring Tribe approval. Optional items include well screen installation and well abandonment, as needed. TERO fees do not apply.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IV. STATEMENT OF WORK
Project Name: Samantha DeGoede New Test Well
| Project Location: | 297 DeGoede Dr. |
| Mossyrock, WA 98564 |
Lewis County
| Homeowner contact: | Samantha DeGoede; samonella_b@hotmail.com; (360) 269-5750 |
| Project No: | PO-21-C87 |
A. Project Description
This project is for the installation of a residential drinking water well on fee land. The contractor shall drill the well, consisting of welded steel casing, PVC liner (as needed), sanitary seal, well screen (as needed), well development, test pumping, disinfection, and water quality sampling and testing. The estimated well depth based on existing nearby wells is 400 feet. All appurtenances, including a submersible pump and pressure system, will be contracted separately. Existing well logs from the surrounding area are provided (see Attachments). Further investigation of the site and locating other local well logs is the responsibility of the Contractor. Any permits, including the Department of Ecology Notice of Intent, are the responsibility of the Contractor.
B. Ownership
This project will provide sanitation facilities to a private home owned by a member of the Cowlitz Tribe. Upon completion, the facilities will be transferred to the homeowner. The system will be operated by the homeowner.
C. TERO & Other Fees
TERO fees do not apply.
D. Scope of Work
Work is to be completed on a private home, under the jurisdiction of Lewis County. The contractor must review site conditions and report any concerns or discrepancies to the Contracting Officer’s Representative (COR) in writing prior to beginning construction. The proposed well location is indicated in the drawings. IHS has verified that an adequate 100-foot sanitary control area is available at this spot. In accordance with the Site Plan, the contractor must:
1. Mobilize and Demobilize
2. Drill 6” Well
3. Install 6” Steel Well Casing
4. Place Sanitary Grout
5. Install PVC Well Liner (as needed)
6. Develop Well
7. Test Pump
8. Disinfect and Perform Water Quality Analysis (see Attachments) Optional Items, As Needed:
9. Well Screen (as needed)
10. Abandon Unusable Well
E. Technical Requirements
1. Codes, References, and Standards: Work under this contract must be performed in compliance with the codes, references, and standards listed below. If conflicts exist between these references, consult the Tribe for direction.
i. Washington Administrative Code (WAC Chapter 173-160, MINIMUM STANDARDS FOR CONSTRUCTION AND MAINTENANCE OF WELLS)
ii. Indian Health Service Technical Provisions (See Attachments)
2. Submittals: The Contractor shall provide submittals on the items listed below. Submittal approval is required for variations from equipment and materials specified.
Pre-Construction (5 days before beginning construction)
i. Type of drilling method: If mud rotary, method of mud containment
ii. Well Casing
iii. Well Liner Following drilling, if a screen is found to be necessary, the following submittals are required. The Tribe will make the final determination regarding screen installation:
iv. Well Screen
Post-Construction
i. Water quality analysis results
ii. Pumping test results (form provided in Attachments)
iii. WA DOE Well log
3. Material Specifications: Install materials as specified in sections D & E above. Materials specified may be substituted with equals upon approval from the Tribe.
4. Work Execution Requirements
i. The Contractor shall contact the COR 48 hours prior to mobilization.
ii. The Contractor must attend a pre-construction meeting before beginning work under this contract, unless otherwise explicitly authorized by the Contracting Officer.
iii. The Contractor is responsible for determining the exact location of any and all utilities. The Contractor is responsible for protecting utilities from damage during construction.
iv. All debris generated during construction shall be removed from site.
v. All areas disturbed by construction activities shall be finish-graded.
vi. The contractor must obtain approval from the Contracting Officer prior to installing material quantities in excess of those specified on the bid schedule.
vii. The Contractor must keep the COR notified and advised of all work to be done or work in progress sufficiently in advance so that proper inspection can be performed.
IHS Project Manager and Recommended COR:
Jennifer Toth, Project Manager/Engineering Technician, jennifer.toth@ihs.gov
Project Completion Time:
IV. STATEMENT OF WORK Page 2 of 2
60 calendar days from the notice to Proceed (NTP