Inclusions in the Scope of Work.pdf

PDF 132 KB Posted

Attached to
Level 2 FRP Over Lab Ceilings Installation- COFC0401
Solicitation number
75D301-26-R-73423
Issued by

About this file

This is an Architect's Supplemental Instructions (ASI) Amendment #1 to a federal construction contract for the Centers for Disease Control and Prevention (CDC) Ft. Collins Campus, Building 401. The amendment, dated August 21, 2025, modifies contract P20231008229 for Level 2 Fiberglass Reinforced Panels (FRP) over lab ceiling installation at 3156 Rampart Road, Ft. Collins, Colorado 80521. The amendment includes revisions to the Statement of Work (with previous edits highlighted in red) and updated drawings: Drawing G000 reflecting the current index of drawings with ASI revision dates, and Drawing A102 expanding the scope to include additional rooms and walls for FRP system coverage.

The contractor is required to submit a cost proposal as soon as possible, coordinated with the CDC's Office of Federal Readiness (OFR) Contracting Officer, including construction costs, project and management costs, discipline-specific breakdowns, and a construction schedule for government review and approval. The contractor must provide a reasonable timeframe for cost proposal submission. All materials and adhesories require approval, with adhesives specifically requiring certification by the FRP panel manufacturer and compliance with low volatile organic compound (VOC) standards. The contractor is responsible for providing all labor, materials, badging support, design, coordination, installation, building occupant signage, and user notifications to deliver a complete and functional installation.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SENSITIVE BUT UNCLASSIFIED INFORMATION (SBU)

ARCHITECT’S SUPPLEMENTAL INSTRUCTIONS: AMENDMENT #1

August 21, 2025

P20231008229- COFC 0401 Level 2 FRP OVER LAB CEILING INSTALLATION

Centers for Disease Control and Prevention (CDC) Ft. Collins Campus – Building 401 3156 Rampart Road Ft. Collins, CO 80521

I. AMENDMENT #1 INCLUSIONS: SCOPE OF WORK

This Amendment includes changes to the Statement of Work and the Drawings. This Amendment consists of:

A. Revisions to the Statement of Work, all edits from the previous set are highlighted in red and the new S.O.W.

is dated August 21, 2025.

B. Revisions to the Drawings:

1. Drawing G000: Updated Index of Drawings with dates of ASI revisions added. Date of updated

G000: 8/21/25.

2. Drawing A102: Amended with additional scopes of work, including new rooms and walls that are proposed to be covered with the FRP system. Date of updated A102: 8/21/25.

II. SCHEDULE AND CONTRACTOR RESPONSIBILITIES

A. As soon as possible, and as coordinated with the CDC’s OFR Contracting Officer (C.O.), submit a proposal with the proposed construction cost, including all other project and management costs, to include this Amendment’s scope of work. Include breakdowns by discipline, as well as the Construction Schedule for Government review and approval. Provide to the CO a reasonable time frame for when the Cost Proposal can be submitted.

B. Submit all materials and accessories for approval. All adhesives must be approved and certified for use by the FRP panel manufacturer, and be low VOC.

C. Provide all labor, materials, badging support, design, coordination, installation, building occupant signage, and user notifications to make a complete and functional building.

END OF AMENDMENT 1