This document provides clarifications for Solicitation 70Z08524QIBCT0018, which is for dockside repairs to the U.S. Coast Guard Cutter (CGC) SEQUIOA (WLB 215), a 225-foot Seagoing Buoy Tender currently home-ported in Port Huron, Michigan. The solicitation is a 100% Total Small Business Set Aside, and award will be made on a best value basis, with technical and past performance factors more important than price. Key requirements include providing a 60-day warranty, and submitting information such as a list of subcontractors, welder qualifications, property control system for government-furnished property, and qualifications of sil-brazers. Proposals are due by 8 AM PST on June 6, 2024, and the anticipated award date is on or about June 19, 2024. Clarification questions were due by May 23, 2024, and the last day to request drawings was May 17, 2024.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clarifications for Solicitation 70Z08524QIBCT0018
1. Please advise location of this Dockside Availability.
Answer: Homeport. Port Huron, Michigan
2. For WI-003 Compartment Bulkheads and Overheads, Partial Preserve; Do you have a square foot estimate for the Partial Preserve requirements of the spaces that are covered?
Answer: No specific area detail, the amount is to 33% percent of the compartments listed using the insulation schedule.
Coast Guard Drawing 225B WLB 635-001, Rev E, Hull Thermal and Acoustic Insulation Schedule.
3. Does the CG require the removal of the hydraulic chain stoppers, mechanical chain stoppers, inhaul winch, crossdeck winches to complete the preservation of the buoy deck? Or can the contractor achieve best effort in way of the aforementioned list of equipment?
Answer: There is no need or requirement to remove the deck equipment for preservation. Therefore, no weight testing is required. Protective measures must be taken to prevent damage to the equipment.
4. Can a 480V 60 amp power source be made available to test the breakers at a location on the ship?
3.2.3 Outages exceeding 15 minutes. The Contractor shall secure uninterruptable power supplies and supported loads when power interruption is expected to exceed 15 minutes.
**Need clarification of this requirement as all breaker testing would require extended outages and providing back up power would be a significant requirement.
3.5.2 Phase rotation test. The Contractor shall perform a phase rotation test for each CB supplying three phase motor loads, either directly or indirectly through intermediate panelboards, and check if any power wiring was disconnected.
**Would a phase rotation meter be acceptable Answer: I would require them to stick with the requirements.
5. Can you please confirm if the quantity for the composite labor rate is correct in the attached schedule?
Answer: It should be 420 hours at whatever their composite labor rate is