Clarifications for Solicitation 70Z08524QIBCT0018.docx

DOCX document 16 KB Posted

Attached to
USCGC SEQUIOA Post MMA DS FY24 Federal contract opportunity
Solicitation number
70Z08524QIBCT0018
Issued by
Department of Homeland Security US Coast Guard

About this file

This document contains clarifications for Solicitation 70Z08524QIBCT0018, which is a requirement for the contractor to provide dockside repairs to the U.S. Coast Guard Cutter (CGC) SEQUIOA (WLB 215) currently home-ported in Port Huron, Michigan. The clarifications address questions regarding the location of the dockside availability, the extent of preservation work required, the handling of deck equipment, and power requirements for breaker testing. The solicitation is a 100% Total Small Business Set Aside, with award to be made on a best value basis. Offerors must provide a 60-day warranty statement, submit required technical information, and relevant past performance. Responses to the solicitation are due by 8 AM PST on June 6, 2024, and the anticipated award date is on or about June 19, 2024.

View the file

Other files for this federal contract opportunity

Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Clarifications for Solicitation 70Z08524QIBCT0018

1. Please advise location of this Dockside Availability.

Answer: Homeport. Port Huron, Michigan

2. For WI-003 Compartment Bulkheads and Overheads, Partial Preserve; Do you have a square foot estimate for the Partial Preserve requirements of the spaces that are covered?

Answer: No specific area detail, the amount is to 33% percent of the compartments listed using the insulation schedule.

Coast Guard Drawing 225B WLB 635-001, Rev E, Hull Thermal and Acoustic Insulation Schedule.

3. Does the CG require the removal of the hydraulic chain stoppers, mechanical chain stoppers, inhaul winch, crossdeck winches to complete the preservation of the buoy deck? Or can the contractor achieve best effort in way of the aforementioned list of equipment?

Answer: There is no need or requirement to remove the deck equipment for preservation. Therefore, no weight testing is required. Protective measures must be taken to prevent damage to the equipment.

4. Can a 480V 60 amp power source be made available to test the breakers at a location on the ship?

3.2.3 Outages exceeding 15 minutes. The Contractor shall secure uninterruptable power supplies and supported loads when power interruption is expected to exceed 15 minutes.

**Need clarification of this requirement as all breaker testing would require extended outages and providing back up power would be a significant requirement.

3.5.2 Phase rotation test. The Contractor shall perform a phase rotation test for each CB supplying three phase motor loads, either directly or indirectly through intermediate panelboards, and check if any power wiring was disconnected.

**Would a phase rotation meter be acceptable Answer: I would require them to stick with the requirements.