RFQ 70Z08126QELIZ0020 Questions and Answers.pdf

PDF 38 KB Posted

Attached to
Z2JZ--Replace HVAC Units at Building 7 and 97, USCG Base Elizabeth CIty
Solicitation number
70Z08126QELIZ0020
Issued by

About this file

This document is a Questions and Answers (Q&A) addendum for RFQ 70Z08126QELIZ0020 issued as of August 19, 2026. The Q&A addresses three clarifications regarding project specifications and scheduling requirements.

The document confirms the project is tax exempt. It clarifies a specification discrepancy for Building 97, correcting the electric heat requirement from 15 KW (which was oversized for the 2.5-ton air handler unit) to 5 KW. Regarding the period of performance, the answer reconciles an apparent conflict between SF-1442 requirements (14 calendar days to begin, 56 calendar days to complete) and the SOW specifications (10 workdays mobilization, 40 workdays completion). The response establishes that the SF-1442 calendar day requirements are based on a 5-day workweek approximation, where 40 workdays equals 8 weeks or 56 calendar days. The exact period of performance will be calculated from the anticipated Notice to Proceed (NTP) at the time of award, based on 40 workdays of work.

Questions and Answers as of August 19

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ 70Z08126QELIZ0020

Questions and Answers as of August 19, 2026

1. Is the project tax exempt?

Answer: Yes.

2. The SOW specifies 15 KW of electric heat on the 2.5-ton unit at Building 97. That's oversized for a 2.5-ton air handler and looks like a copy-paste from the Building 7 spec.

Please confirm.

Answer: Yes. 15 KW is oversized for the 2.5-ton unit. The electric heat shall be five (5) KW for Building 97.

3. SF 1442 states the project must begin in 14 calendar days and be completed in 56 calendar days (mandatory). The SOW states mobilization in 10 workdays and completion in 40 workdays. Please confirm which is correct.

Answer: The SF-1442 requires use of calendar days, which was approximated based on a 5-day workweek. Forty (40) workdays equates to 8.0 weeks. Eight (8) weeks x 7 calendar days equals 56 calendar days. The exact period of performance will be calculated based on 40 workdays from the anticipated NTP at the time of award.