This document is an Amendment (Amendment 0001) to a federal solicitation for a design-build project to rebuild family housing at Fort Wadsworth, U.S. Coast Guard Sector in Staten Island, NY. The amendment includes multiple modifications to the original Request for Proposal (RFP), such as corrections to road reconstruction references (changing "Avery Road" to "Ayers Road"), updates to technical specifications for windows, insulation, metering, and utility connections, and clarifications on various project requirements.
Key changes include adjustments to the performance period (810 calendar days for the Base Item, 1403 calendar days total), modifications to window and building envelope specifications, updates to energy efficiency and sustainable design requirements, and revisions to utility metering and connection procedures. The amendment also provides a site visit attendance list and incorporates responses to numerous contractor requests for information (RFIs), addressing technical details, design considerations, and scope clarifications for the multi-phase housing reconstruction project.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or
(c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
REBUILD FAMILY HOUSING FORT WADSWORTH PHASE I AT U. S. COAST GUARD SECTOR NEW YORK, STATEN
ISLAND, NY.
Description of Amendment 0001: RFI Q & A, amendment language, attachments, and site visit attendees list.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
Contracting Division U. S. Coast Guard Facilities Design & Construction Center 5505 Robin Hood Road, Suite K Norfolk, VA 23513-2431
9A. AMENDMENT OF SOLICITATION NUMBER
70Z04725RPCNI0005
1 2 1
June 27, 2025
9B. DATED (SEE ITEM 11)
05/27/2025
XX
73001PR250000035 21-14089081
Amendment 0001
70Z04725RPCNI0005
SOLICITATION 70Z04725RPCNI0005 IS AMENDED AS FOLLOWS:
Incorporate RFI Q&A log and Site Visit Attendance List as part of the Solicitation:
TASK ORDER ANNOUNCMENT:__________________________
1. Refer to RFI #125:
Delete: Insurance/Bonds: Please review Section H.2 of the IDIQ contract for insurance requirements and FAR 52.228-15 for bonding requirements.
Replace with: Insurance/Bonds: Please review Section H.3 of the contract for insurance requirements and Section L.18 of the contract for bonding requirements.
A bid guarantee is not required for this task order.
2. Refer to RFI #127:
Delete: Period of Performance: The contract performance period is 1489 calendar days after award of the Task Order for the Base and all Option Items. If awarded, the Option Items shall be completed within the contract completion date in accordance with FAR Clause 52.211-10 Commencement, Prosecution and Completion of Work (APR 1984).
Replace with: Period of Performance: The contract performance period for the Base Item is 810 calendar days after award of the Task Order. The contract performance period is 1403 calendar days after award of the Task Order for the Base and all Option Items. If awarded, the Option Items shall be completed within the contract completion date in accordance with FAR Clause 52.211-10 Commencement, Prosecution and Completion of Work (APR 1984).
RFP GUIDE SPECIFICATIONS 21-14089081 (Phase I):___________________
RFP SPECIFICATIONS
With respect to the below RFP Specifications, the Contractor is responsible for revisions the Solicitation as noted below:
RFI #8, #115, and #160 RFP Specification Section 01800-1.1.1 DELETE: ‘OPTIONAL BID ITEM-5, 1. Reconstruct Avery Road within the limits as shown on RFP Drawings.’
REPLACE: Where deleted, replace ‘Avery’ with ‘Ayers’ and insert ‘OPTIONAL BID ITEM-6, 1.
Reconstruct Ayers Road within the limits as shown on RFP Drawings.’
RFP Specification Section 01800-1.1.3 ADD: Add the following text to the bottom of the REFERENCES, CODES AND STANDARDS list:
“Exterior building enclosure system shall comply as a minimum with the requirements of:
(a) New York City Energy Conservation Code (NYCECC)”
RFP Specification Section 01800-1.4.11.5 DELETE: Avery Road Reconstruction (BID OPTION #6). Reference Bid Option #6, the Contractor shall complete a full depth reconstruction of Avery Road and clear all overhanging tree branches to a height of 14’-6” above final surface. Reconstruction shall include replacement of any unsuitable asphalt base course, sub-base, or subgrade.
REPLACE: Where deleted, replace ‘Avery’ with ‘Ayers’
Ayers Road Reconstruction (BID OPTION #6). Reference Bid Option #6, the Contractor shall complete a full depth reconstruction of Ayers Road and clear all overhanging tree branches to a height of 14’-6” above final surface. Reconstruction shall include replacement of any unsuitable asphalt base course, sub-base, or subgrade.
RFI#146 RFP Specification Section 01800-1.4.5 DELETE: “The Contractor shall provide and install new meters for each family housing unit. Each family housing unit shall be individually metered for all incoming utility services and connected to the CG enterprise reporting system to accurately monitor the consumption and cost data.”
REPLACE: “The Contractor shall provide and install new meters for each family housing unit.
Each family housing unit shall be individually metered for all incoming utility services and connected to the CG enterprise reporting system to accurately monitor the consumption and cost data. Install all metering in accordance with SILC-CSTO-36-11 31 17 11-01 Advanced Metering Infrastructure (Rev A).”
RFI#146 RFP Specification Section 01900-1.3 ADD: Appendix G - SILC-CSTO-36-11 31 17 11-01 Advanced Metering Infrastructure (Rev A).”
RFI#23 RFP Specification Section 01800-1.7.5.6.1 DELETE: “Provide vinyl windows with a whole-window”
REPLACE: “Provide windows with a whole-window”
RFI#23 RFP Specification Section 01800-1.7.5.6.1(a)
DELETE: “ASTN E2112.”
REPLACE: “ASTM E2112.”
RFI#23 RFP Specification Section 01800-1.7.5.6.2(a) DELETE: “U-Factor: 0.25 Btu/sq. ft x h x deg F or less”
REPLACE: “Each window must meet or exceed (be rated for a lower U-Factor than) the NYCECC maximum U-Factor for the type of fenestration designed by the Designer of Record (DOR).
NYCECC prescriptive U-Factor for Climate Zone 4 per Table R402.1.2 is 0.27.”
RFI#23 RFP Specification Section 01800-1.7.5.6.2(b) DELETE: “Solar Heat-Gain Coefficient (SHGC): Provide windows with a whole-window SHGC maximum of
0.30 determined according to NFRC 200 procedures”
REPLACE: “Solar Heat-Gain Coefficient (SHGC): Provide all windows with a maximum whole-window SHGC as prescribed by the NYCECC in accordance with NFRC 200 procedures.
NYCECC prescriptive maximum SHGC is 0.40 in accordance with NFRC 200 procedures.”
RFI#23 RFP Specification Section 01800-1.7.5.6.2(e) DELETE: “The window shall have successfully passed the impact and cycle requirements of South Florida protocols, TAS-201, TAS-202 and TAS-203, and have NOA’s and Florida Product Approval for large missile impact.”
REPLACE: “The window shall have successfully passed Missile Level D testing in accordance with ASTM E1886-05 and ASTM E1996-05 as well as Impact Pressure Cycling at +55/-65 psf in accordance with ASTM E1886-05 and ASTM E1996-05. Provide forced entry resistance complying with ASTM F588. Provide impact glazing where necessary to meet applicable building codes and in accordance with window manufacturer’s recommendations (as selected by Designer of Record (DOR)), consisting of sandwich panels including laminated glass and annealed or tempered glass.”
RFI#24 RFP Specification Section 01800-1.7.5.9.1 DELETE: “Louvers shall be designed to meet the stringent criteria established by the Florida Building Code”
REPLACE: “Louvers shall be designed to meet the stringent criteria established by the New York City Construction Code”
RFI#37 RFP Specification Section 01800-1.12.12.1 DELETE: “Executive Order (EO) 14057”
RFI#121 RFP Specification Section 01800-1.7.5.6.1 DELETE: “Performance Class CW-50 or greater.”
REPLACE: “Performance Class LC or greater and AAMA/WDMA 101/I.S.2/NAFS Performance Grade PG35 or greater.”
RFI#146 RFP Specification Section 01800-1.7.5.9.2 DELETE: “under Miami-Dade structural tests TAS-201, TAS-202 and TAS-203.”
REPLACE: “under Air Movement and Control Association (AMCA) structural tests AMCA 500-L, AMCA 540 and AMCA 550.”
RFI #13 Specification Section 01500 3.1
DELETE:
3.1 AVAILABILITY AND USE OF UTILITY USAGE
3.1.1 Temporary Utilities
Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
3.1.2 Meters and Temporary Connections
Provide and maintain necessary temporary connections, distribution lines, and meter bases (Government will provide meters) required to measure the amount of each utility used for the purpose of determining charges. Notify the Contracting Officer, in writing, 5 working days before final electrical connection is desired so that a utilities contract can be established. The Government will provide a meter and make the final hot connection after inspection and approval of the Contractor's temporary wiring installation. Do not make the final electrical connection.
3.1.3 Electricity
The contractor will be responsible for providing their own electricity at the site and making the necessary arrangements with the local utility provider.
3.1.4 Water
The contractor will be responsible for providing their own potable water at the site.
3.1.5 Sanitation
Provide and maintain within the construction area minimum field-type sanitary facilities in accordance with EM 385-1-1 Section 02. Locate the facilities behind the construction fence or out of the public view. Clean units and empty wastes at least once a week or more frequently into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Obtain approval from the system owner prior to discharge into a municipal, district, or commercial sanitary sewer system. Penalties or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system. Maintain these conveniences at all times. Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel
3.1.6 Telephone
Make arrangements and pay all costs for telephone facilities desired.
3.1.7 Fire Protection
Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.
REPLACE:
3.1 AVAILABILITY AND USE OF UTILITY USAGE
3.1.1 Temporary Utilities
Provide and pay for temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
3.1.3 Electricity
The contractor will be responsible for providing and paying for their own electricity at the site and making the necessary arrangements with the local utility provider.
3.1.4 Water
The contractor will be responsible for providing and paying for their own potable water at the site.
3.1.5 Sanitation
Provide chemical toilets or equally effective units for employees and require their use.
Periodically empty and dispose of waste. Keep facilities clean and free of nuisance such as pests, odor, and vermin. Coordinate location with the COR. Upon completion of the work remove the sanitary facilities and leave the area clean and free of nuisance.
3.1.6 NATURAL GAS
The contractor will be responsible for providing and paying for their own natural gas at the site.
3.1.7 Telephone
The contractor will be responsible for providing and paying for their own telephone facilities if desired.
Specification Section 01800 1.7.2.4.1 DELETE: “in the New York State (NYS) Energy Code 2020 for climate zone 4 – Richmond County.”
REPLACE: “in the NYCECC for Climate Zone 4.”
Specification Section 01352
DELETE: 1.6.1- 1.6.3
1.6.1 Subcontractor Safety Requirements
For this Contract, neither Contractor nor any subcontractor may enter into Contract with any subcontractor that fails to meet the following requirements. The term subcontractor in this and the following paragraphs means any entity holding a Contract with the Contractor or with a subcontractor at any tier.
1.6.2 Experience Modification Rate (EMR)
A. Subcontractors on this Contract must have an effective EMR less than or equal to 1.10, as computed by the National Council on Compensation Insurance (NCCI) or if not available, as computed by the state agency's rating bureau in the state where the subcontractor is registered, when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier. The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable EMR range cannot be achieved. Relaxation of the EMR range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval. Contractor's Site Safety and Health Officer (SSHO) must collect and maintain the certified EMR ratings for all subcontractors on the project and make them available to the Government at the Government's request.
1.6.3 OSHA Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate Subcontractors on this Contract must have a DART rate, calculated from the most recent, complete calendar year, less than or equal to 3.4 when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier. The OSHA Dart Rate is calculated using the following formula:
(N/EH) x 200,000 Where:
N = number of injuries and illnesses with days away, restricted work, or job transfer EH = total hours worked by all employees during most recent, complete calendar year 200,000 = base for 100 full-time equivalent workers (working 40-hours per week, 50 weeks per year) The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable OSHA Dart rate range cannot be achieved for a particular subcontractor.
Relaxation of the OSHA DART rate range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval. Contractor's Site Safety and Health Officer (SSHO) must collect and maintain self certified OSHA DART rates for all subcontractors on the project and make them available to the Government at the Government's request.
Specification Section 01352 DELETE: 1.7.3 to 1.7.4 Fulltime SSHO is not a requirement of this contract.
1.7.3 ROLES AND RESPONSIBILITIES OF PRIME CONTRACTOR AND SSHO
The Prime Contractor and SSHO must ensure that the requirements of all applicable OSHA and EM 385-1-1 are met for the project. The Prime Contractor must ensure an SSHO or an equally qualified Alternate
SSHO(s) is at the worksite at all times to implement and administer the Contractor's safety program and Government accepted Accident Prevention Plan. If the required SSHO has to temporarily (that is, up to 24 hours / 1 day) leave the site of work due to unforeseen or emergency situations, a Level One, Two, or Three SSHO may be used in the interim and must be on the site of work at all times when work is being performed. If the SSHO must be off-site for a period longer than 24 hours / 1 day, a qualified alternate that meets the contract requirements must be onsite.
a. Prime contractor must ensure all SSHOs will:
(1) Are designated on an ENG Form 6282.
(2) Meet minimum training and experience requirements identified in EM 385-1-1.
(3) Execute roles and responsibilities identified in EM 385-1-1.
1.7.4 CONTRACT SITE SAFETY AND HEALTH OFFICER(SSHO) MINIMUM REQUIREMENTS
Provide a minimum of one Level One SSHO that meets the requirements of EM 385-1-1 for this project
Specification 01900 ADD: Specification 01900 was unintentionally omitted from the RFP Specification.
RFP DRAWINGS
With respect to the below Amended drawings, replace both PDF files and ACAD files (*dwg).
C-101, REPLACE DRAWING: Summary of changes includes the following:
1. Note 2. Replace ‘Avery’ with ‘Ayers’
2. Note 2: Add Ayers road width of 20-FT
3. Adjust Contractor Laydown Area
4. Add alternate Contractor Laydown Area
C-102, REPLACE DRAWING: Summary of changes includes the following:
1. Replace label of Ayers Road work from ‘OPTION 5’ to ‘OPTION 6’
C-103, REPLACE DRAWING: Summary of changes includes the following:
1. Replace label of Ayers Road work from ‘OPTION 5’ to ‘OPTION 6’
A-102, REPLACE DRAWING: Summary of changes includes the following:
1. Plan Legend, Change ‘Frost’ to ‘Freeze’
A-103, REPLACE DRAWING: Summary of changes includes the following:
1. Plan Legend, Change ‘Frost’ to ‘Freeze’
2. In space between LIVING and KITCHEN, remove ceiling fan. Maintain light fixture, this location.
A-104, REPLACE DRAWING: Summary of changes includes the following:
1. Plan Legend, Change ‘Frost’ to ‘Freeze’
2. In space between LIVING and KITCHEN, remove ceiling fan. Maintain light fixture, this location.
RFP APPENDICES
With respect to the below RFP Appendices, amended (revised) PDF files are included.
RFI #15, Appendix F - Duplex - 3 Bedroom and 4 Bedroom, Garage REPLACE: Replace with Amended space criteria sheet. Summary of changes are shown below.
1. Building Type - Duplex - 3 Bedroom and 4 Bedroom, Garage
a. Paragraph 7.0 Openings, Garage Doors: Replace ‘R-13’ with ‘R-7’
b. Paragraph 11 Plumbing; Replace ‘Frost-proof’ with ‘Freeze-proof’
RFI #15, Appendix F - Townhouse - 3 Bedroom and 4 Bedroom, Garage REPLACE: Replace with Amended space criteria sheet. Summary of changes are shown below.
a. Paragraph 7.0 Openings, Garage Doors: Replace ‘R-13’ with ‘R-7’
b. Paragraph 11 Plumbing; Replace ‘Frost-proof’ with ‘Freeze-proof’
RFP ATTACHMENTS
With respect to the below RFP Attachments, PDF files are included.
RFI #146, Attachment G ADD: SILC-CSTO-36-11 31 17 11-01 Advanced Metering Infrastructure (Rev A)
Amendment attachments:
1. Site Visit Attendance List
2. RFI Log.
3. RFP Drawings (PDF & ACAD)-attached via DoDSafe.
4. Appendix F-attached via DoDSafe.
5. Appendix G-attached via DoDSafe.
END OF AMENDMENT LANGUAGE
Note
Failure to acknowledge amendments may be cause for rejection of your offer.
AMENDMENT 0001 PRE-PROPOSAL INQUIRY/REQUEST FOR INFORMATION - Family Housing Fort Wadsworth
RFI
Date
Received Reference Contractor's RFI Government response
1 6/23/2025 TOA TOA General Submission Instructions, page 7 states to include representation in FAR 52.204-24(d) with the submission of our proposal. Please confirm this is the only Reps and Certs required to be included in our proposal?
Please submit 52.204-8, 52.204-24(d) and 52.204-26(c).
2 6/23/2025 TOA We do not see any technical submission required for the proposal. Please confirm no technical submission is required for the proposal?
This is a PRICE ONLY solicitation. See page Task Order Announcement, pg. 23: Award will be made to the Contractor proposing the lowest total evaluated price. Award shall be made to the lowest price offer. The initial proposal must include the contractor’s best terms, since the award decision will be based solely on the lowest price.
3 6/23/2025 Price Proposal
Form
The Price Proposal Form, Bid Option 5, Item 001 is very general in its scope.
Please confirm the scope for Bid Option 5, Item 001 is just the scope detailed on RFP Drawing C-104?
The Price Proposal Form is not the authoritative document for requirements. Refer to RFP Specifications and Drawings.
4 6/23/2025 Price Proposal
Form
The Price Proposal Form, Bid Option 5, Item 001 is very general in its scope and includes "utilities". Please define what utilities are to be included in Bid Option 5, Item 001?
Refer to RFP 01800-1.1.2 and similar RFI responses.
5 6/23/2025 Solicitation Please confirm the award will be evaluated on the Total Price - Base Items + all Options Items (1 thru 6)?
See Task Order Announcement, pg. 23: The Government will evaluate offers for award purposes by adding the total price for all options to the total price of the basic requirement.
Evaluation of options will not obligate the Government to exercise the option(s). The order will consist of the Base Item and may include any single Option Item or combination of Option Items deemed to be in the Government’s best interest.
6 6/23/2025 Solicitation Please confirm if SF30s are to be provided in the proposal to acknowledge Amendments or do we just complete the "Amendments Acknowledged" section at the end of the Price Proposal Form, or both?
Refer to SF50 form, block 11.
7 6/23/2025 Drawing C-101
RFP Drawing C-101, Note 2 states if Option 6 is awarded to reconstruct Avery Road and redirect all construction traffic onto Avery Road. If Option 6 is awarded, is it the USCG intent to reconstruct Avery Road upon construction NTP and use Avery Road as the construction haul route? If so, can we still use USS Tennessee Road as well?
Concur. See Amendment. Amendment will provide correction to Drawing C-101, Note #2.
The Contractor will not be restricted to phase the repair of Avery Road 'for the purpose of redirecting all construction traffic away from the primary hau route.'
8 6/23/2025 Drawing C-102
RFP Drawing C-102 labels work as Option 5, but believe it should be Option 6.
Please confirm / revise?
See Amendment. Avery roadway work shown on C-102 is listed as 'Bid Option 5' is 'Bid Option 6'. Refer to Amended Drawing C-102.
9 6/23/2025 Drawing C-103
RFP Drawing C-103 identifies Drainage Improvements Known Problem Areas 1, 2, 3. We do not see where this scope is detailed or called out to be included in this scope and price. Please confirm this work is not part of this task order? If so, please provide scope details.
Confirmed. Data is provided for information purposes.
10 6/23/2025 Drawing C-103
In review of RFP Drawing (C-103) and utilizing the floor plans provided with the RFP Drawings, the base bid multiplex housing building with the designated 4 units will not fit in the area identified on C-103. Please provide direction or alternate location where the base bid multiplex housing building is to be located?
The requirement to construct the base bid on the site of the demolished housing Unit #428 (Ref Drawing C-102) remains. However, the Government's intent that the Contractor is to fully utilize the site was not clear. The existing Architectural drawings, Civil Site Plans along with the approximate limits of the laydown areas on Drawings C-102 and C-103 did not adequately convey this requirement.
The Contractor is expected to utilize the entire site, as Amended, to construct the four base units. Drawings C-102 and C-103 are included within this Amendment. The list of modifications include;
1. Shrinking the size of the Contractor laydown area.
2. Expanding the footprint for the base bid (Note, the building arrangement need not resemble the multiplex conceptual arrangement that was provided).
3. Adds a second Contractor laydown area, which makes up for the lost laydown area.
11 6/23/2025 Specification 01800-1.1
In review of Specification section 01800, 1.1.2.4 it is not a requirement for the contractor to perform work on the primary side of the transformers or to replace or relocate transformers. In review of the proposed locations of the multiplex family housing buildings for the base bid and options against the provided Attachment A, ICAM Utilities Survey and it appears the underground network for the medium voltage feeder will be close or in conflict with the proposed multiplex family housing building. Please confirm if the DOR determines after award during design the medium voltage feeder will be close or in conflict with the proposed multiplex family housing building, the Contractor is not responsible for the relocation of the medium voltage feeder in conflict and it will be handled as a scope change?
The DOR will make the determination after award during the design stage. Each instance will need to be looked at on a case-by-case basis.
12 6/23/2025 Specification 01800-1.4
Specification section 01800, 1.4.6 specifies that the "Contractor shall determine the most efficient and economical main building finish floor elevation based upon the closest 100-year floodplain elevation to the site established by FEMA, the International Building Code and ASCE 24-14." "The site is in Zone X, per FEMA map 3604970331F dated September 5, 2007 & 360497V000B (dated December 5, 2013). The proposed buildings shall be designed to an ASCE 24 Flood Design Class 2 (moderate risk)." No base flood elevations or depths are shown within this zone. FEMA map 3604970331F shows the closest 100-year floodplain elevation to the site as Zone AE (EL 11/ NGVD 29). Please clarify the base flood elevation to be used for the project site?
This shall be determined by the DOR. However, if flood elevation information is not provided for Zone X, the DOR can use the nearest floodplain elevation to that zone.
13 6/23/2025 Existing Utilities
Please confirm if the Contractor should include consumption costs for existing utilities (water, electric, natural gas) used during the construction of the project?
See Amendment and refer to RFP Specification 01110-1.12
14 6/23/2025 Specification 01800-1.9
Specification section 01800, 1.9.3 states there are no salvage requirements.
Please confirm who (contractor or Government) will be responsible for the removal and salvage of any appliances (ranges, washers/dryers, refrigerators, dishwashers, furnaces, water heaters) USCG wants to retain. If no appliances are being retained by USCG, please confirm the contractor is responsible for removal and disposal of all appliances.
Per RFP Specification 01800-1.9.3 there is no salvage. The Contractor is responsible for demolition of all existing appliances.
15 6/23/2025 Appendix F Appendix F for the Building Type - Duplex - 3 Bedroom and 4 Bedroom and Building Type - Townhouse - 3 Bedroom and 4 Bedroom as well as Drawings A- 102, A-103, and A-104 references frost proof hose bibbs. Specification section 01800, 1.11.3.5 references Freeze proof hose bibbs. Please confirm freeze proof and not frost proof are to be provided?
See Amendment. Freeze proof is the correct requirement. References to 'frost proof' have been eliminated via amendment. Updated Appendix F Individual Space Criteria Sheets included within this Amendment.
16 6/23/2025 Existing Utilities
Confirm the existing housing units HVAC and water heater units are natural gas?
Existing housing utilize natural gas for both furnaces and water heaters.
17 6/23/2025 Existing Utilities
Confirm it is to be assumed for bidding purposes the existing sanitary and water service can accommodate the new buildings usage?
Confirmed. For bidding purposes, assume the existing sanitary sewer main lines and the existing water main lines can accommodate the new buildings usage.
18 6/23/2025 General For bidding purposes, please confirm we should assume all existing utilities are in good working condition?
Confirmed. For bidding purposes, assume the existing utilities are in good working condition.
19 6/23/2025 Specification 01800-1.6
Specification section 01800, 1.6.5 for bidding purposes please confirm that we should assume the percolation test will be acceptable and no corrective work resulting from the percolation test shall be included on our bid price?
Specification 01800-1.6.5 provides specific guidance and does not require additional clarification.
20 6/23/2025 Specification 01800-1.6
Specification section 01800, 1.6.6 & 1.6.7.4 for bidding purposes please confirm that we should assume the soil test will be acceptable and no corrective work resulting from the soil test shall be included on our bid price?
Shall be determined by the DOR. The Government cannot reasonably forecast the Contractor's demolition and construction activities impact to site soil conditions.
21 6/23/2025 Specification 01800-1.7
Specification section 01800, 1.7.2.1 states a sample wall shall be constructed on site prior to ordering and installing any exterior materials. Please provide more detail / specifics of the exterior wall mockup elements that are required?
Sample walls are a standard of practice in building construction projects. Having a wall ready for exterior finish materials, once received, is necessary to display how the construction of this building comes together and allows a complete understanding of how materials are to be attached, punctured, or connected.
22 6/23/2025 Specification 01800-1.7
Specification section 01800, 1.7.2.3 Roof Systems, Confirm downspout splash blocks allowed?
The Family Housing Design CSTO SILC-CSTO-36-11 55 13 11-01 that is a requirement for this RFP already requires splash blocks to be part of this RFP. Where downspouts are not adjacent to sidewalks, provide precast concrete splash blocks and set splash blocks to redirect water away from the foundation along perimeter. At or adjacent to sidewalks and other hard surfaces, no splash blocks are allowed to be provided as part of this RFP: Instead, at or adjacent to concrete surfaces, provide rubber boots at downspouts to directly connect to below-grade stormwater system at bottom of downspout (assume minimum 12" from-grade boot) to prevent slippery conditions that may occur during inclement weather.
23 6/23/2025 Specification 01800-1.7
Specification section 01800, 1.7.5.6 states windows need to pass South Florida protocols, TAS-201, TAS-202, TAS- 203, have NOAs and Florida Product Approvals for large missel impact. Please confirm these South Florida hurricane requirements are required?
See Amendment.
24 6/23/2025 Specification 01800-1.7
Specification section 01800, 1.7.5.9 states louvers are to meet Miami-Dade structural tests. Please confirm if this requirement can be waived?
See Amendment.
25 6/23/2025 Specification 01800-1.9
Specification section 01800, 1.9.6. For bidding purposes, please confirm we shall assume PFAS is not known to be present and not part of our scope?
PFAS is not known to be present.
26 6/23/2025 Specification 01800-1.4
Specification section 01800, 1.4.8.1 states "For bidding purposes, see Attachment-E Flow Test on recent flow data taken CEUP Project PSN 17140123 M&R (Maintenance & Repair) Ft. Wadsworth Housing Buildings 438 & 440 USS Iowa Circle." Please confirm that the provided flow test Attachment E, file name “E_USCG_1.PDF” dated April 3, 2023 is to be used for bidding purposes?
Confirmed, yes.
27 6/23/2025 Specification 01800-1.11
Specification section 01800, 1.11.3.1 states handicap water closets and lavatories shall confirm to ADA standards. Please confirm that only Accessible or "ADA" dwelling units are to receive and comply with ADA standards?
Confirmed, yes.
28 6/23/2025 Specification 01800-1.12
Specification section 01800, 1.12.1.3.7, please confirm that radiant floor heating is required for all bathrooms? Even ones that are on above floors that have conditioned space below? Even bathrooms without showers?
Confirmed. Comply with 01800-1.12.1.3.7 that requires 'radiant floor heating (electric or hydronic) for all bathrooms.'
29 6/23/2025 Specification 01800-1.13
Specification section 01800, 1.13.1 Electrical Service. Please confirm the primary service is in good working condition and adequate for this project?
For bidding purposes, assume existing utilities will support the load demand of the new buildings. Primary service and work on it is outside the scope of this contract.
30 6/23/2025 Specification 01800-1.13
Specification section 01800, 1.13.1 Electrical Service. Please confirm the primary service and transformer is not part of this scope of work?
Confirmed. Primary service and transformer work is outside the scope of this contract.
31 6/23/2025 Specification 01800-1.13
Specification section 01800, 1.13.10 Lighting. We do not find any requirements for lighting controls. Please confirm automated lighting controls are not intended and not part of this project scope?
In paragraph 1.13 there is a reference to the design complying with the Family Housing Design CSTO SILC-CSTO-36-11 55 13 11-01. In this document there is guidance to lighting controls and references that the DOR should make note.
32 6/23/2025 Specification 01800-1.14
Specification section 01800, 1.14.1 requires camera at Entry Gate. We cannot find any other camera locations. Please confirm only camera is at Entry Gate?
Confirmed, yes.
33 6/23/2025 Specification 01800-1.18
Specification section 01800, 1.18 states to comply with all applicable federal, state and local environmental requirements. Being a Federal project, does NY state and local AHJ / jurisdictions apply? Are we required to obtain NY state and local permits?
Shall be determined by the DOR. The Government cannot reasonably forecast the Contractor's demolition and construction activities impact to site soil conditions.
34 6/23/2025 Specification 01800-1.18
Specification section 01800, 1.18.2 mentions FAA and FCC. Please confirm there are no requirements with respect to FAA and FCC?
Not confirmed. The Contractor shall be responsible for identifying and obtaining all required permits.
35 6/23/2025 Specification 01800-1.18
Specification section 01800, 1.18.6, for bidding purposes, please confirm we shall assume there are no cultural, historic or archaeological resources known to be on the project site?
Not confirmed. Refer to RFP Attachment B - Environmental.
36 6/23/2025 Advertiseme nt
Please confirm the Option Items will be awarded at the same time as the Base award and the contract completion time for the Options are within the project Period of Performance?
See Task Order Announcement, pg. 3: The design and construction costs will be subject to the funds available for this project. The contract price limitation for the contract award is approximately $18 Million for the total Base Items. The contract price limitation for the contract award is approximately $45 Million for the total Option Items. Contractors are notified that they are under no obligation to approach this ceiling; however, the Government may not be able to make an award if the dollar amount set for this project is exceeded. Also see pg. 23: Evaluation of options will not obligate the Government to exercise the option(s).
Refer to FAR provision 52.217-5.And see pg. 5, Period of Performance.
37 6/23/2025 Specification 01800-1.12
We have noticed EO 14057 is referenced in Specification section 01800,
1.12.12. However EO 14057 has been rescinded by the current Administration through EO 14148. Please confirm EO 14057 is not a bid requirement?
See Amendment. The Amendment removes compliance with EO 14057.
38 6/23/2025 Drawing C-101
RFP Drawing (C-101) shows area for contractor laydown area. Can we use the project site for trailers and parking?
Refer to RFP Specification sections 01500-1.3 construction site plan
39 6/23/2025 Specification 01800-1.12
Exceptional Energy Performance states, "For modeling purposes, the ductless mini-split heat pump should be allocated no more than 70% of the heating load." 1.12.1.3.6 states "ductless split units are prohibited for residential construction." Please confirm use of ductless mini-split systems are prohibited for this project?
Confirmed.
40 6/23/2025 Existing Utilities
Can the government confirm the output voltage/phase of the existing to remain 300 KVA transformers?
For bidding purpose, the contractor may assume the output to the units is 208-3. This assumption must be confirmed by the DOR.
41 6/23/2025 Attachment D
Attachment D, Watershed Study mentions a negative slope in the pipe between MH-6 and MH-41. The area of the park interior to Iowa Circle drains to CB-14 which flows towards MH-6. If stormwater cannot flow downstream from MH-6 due to the negative slope, the drainage issues noted in the park area may not be able to be resolved. Confirm the reverse slope pipe between MH-6 and MH- 41 is not part of the project scope?
The reverse slope pipe between MH-6 and MH-41 is not part of the project.
42 6/23/2025 Specification 01800-1.11
Floor drains are only noted in utility rooms per 01800, 1.11.3.9.9. Confirm floor drains are not required in the garage floors?
Floor drains are not required in garages.
43 6/23/2025 Specification 01800-1.4
Specification section 01800, 1.4.1.1 states “The Contractor shall perform test pits, vacuum excavating and utility potholing as required to determine the exact locations of underground utilities” however existing utility surveys are provided in the RFP. Please confirm the utilities surveys provided in the RFP are to be used for bidding purposes and deviations from the provided information encountered on site will be treated as a differing site condition?
Negative. The contractor is required to perform a topographic and utility survey for the site, which will be used for the design.
44 6/23/2025 Specification 01800-1.12
Specification section 01800, 1.12.1.3.7, Radiant floor heating (electric or hydronic) is required for all bathrooms. The Room requirements, page 3 of 4 for Master Bathroom in Appendix F, Full Bathroom and Half-bathroom notes auxiliary heating (lamp or fan-forced coil) is needed. Please verify both radiant floor and auxiliary heating are both required?
Confirmed. Both radiant and auxiliary heating are required.
45 6/23/2025 Appendix F Outdoor areas (patios) do not require fire protection or sprinkler system per the Appendix F Individual Space Criteria Sheets. Please verify sprinkler systems are not required for the Patios?
The need for fire protection or sprinkler systems for outdoor areas (patios) shall be determined by the DOR. For bidding purposes, the USCG has assumed outdoor areas (patios) do not require fire protection or sprinkler systems.
46 6/23/2025 Specification 01800-1.4
Specification section 01800, 1.4.10 states the contractor shall coordinate with the natural gas utility company to install new gas laterals to service the family housing units. Natural gas will be used for residential appliances (ranges/stoves and dryers), mechanical and plumbing equipment. The local utility company does not provide drawings, specifications, or cost until they receive a purchase order for this work after project award. Can the Government please confirm the allowances established in Base Item 0002, Bid Option 1, Item 002, Bid Option 2, Item 2, Bid Option 3, Item 2, and Bid Option 4, Item 2 is to be used for the gas distribution work including disconnection and connection?
Confirmed, yes.
47 6/23/2025 Specification 01800-1.12
Specification section 01800, 1.12.5, please verify Testing, Adjusting and Balancing does not need to be 1st tier sub to Contractor?
Testing and Balancing is required per the RFP. The government takes no determination on the tier level.
48 6/23/2025 Specification 01800-1.5
Specification section 01800, 1.5.3 states "For bidding purposes, the Contractor shall assume the foundation is a steel reinforced concrete continuous (or linear) strip footers with a depth sufficient to overcome soil movement, as required by code." Specification section 01800, 1.5.4 states "The contractor shall bear all costs of the foundation provided. This includes, but is not limited to site preparation, site protection, removal of topsoil, organics, debris, frozen soil, loose or disturbed soil and other unsuitable materials from the proposed construction, dewatering, and shall include all compacted fill to establish adequate bear capacity and any required foundation drainage systems." Please confirm that if it is determined that strip footings alone will not be sufficient to support the buildings after a post award geotechnical analysis is completed, the contractor will be compensated for additional costs associated with the increased foundation scope as an unforeseen condition?
For bidding purposes, the Contractor is to provide the foundation system as stated in the RFP using the information provided in the RFP. If the Contractor's post-award geotechnical site investigation materially differs from the information in RFP, the Contactor may be entitled to compensation under a claim of Differing Site Conditions.
49 6/23/2025 Specification 01800-1.7 &
1.12
Appendix F
Specification section 01800, 1.7.5.1.4 and 1.12.1.3.5 for Overhead Insulated Garage and Shop (Service) Doors specifies insulated panels, R-7 minimum.
However Appendix F for Building Type - Duplex - 3 Bedroom and 4 Bedroom and Building Type - Townhouse - 3 Bedroom and 4 Bedroom states to provided insulated panels, R-13 minimum. Please confirm R-7 insulated panels for garage doors is acceptable?
See Amendment. R-7 is correct. The Amendment corrects the Appendix F Individual Space Criteria Sheets for the Duplex and Townhouse 3 Bedroom and 4 Bedroom Garage units.
50 6/23/2025 Specification 01800-1.13
Specification section 01800, 1.13.11.1.2 states ceiling fans are noted to be included in bedroom, living / family room, and dining room areas. The 3 - Bedroom Accessible - Duplex Plan (A-103) and 4 - Bedroom Accessible - Duplex Plan (A-104) kitchens shows a ceiling fan, please confirm a ceiling fan is required in these kitchens too?
See Amendment.
51 6/23/2025 Specification 01800-1.15
Specification section 01800, 1.15.2 states "The Contractor shall make arrangements with and shall coordinate the system installation with the local CATV (Cable Television, Telephone, and Residential Internet) service supplier.
The Contractor shall pay all utility fees and costs directly to the utility company." The local utility company does not provide drawings, specifications, or cost until they receive a purchase order for this work after project award.
Can the Government please confirm the allowances established in Base Item 0002, Bid Option 1, Item 002, Bid Option 2, Item 2, Bid Option 3, Item 2, and Bid Option 4, Item 2 is to be used for the service providers costs for Cable Television, Telephone, and Internet service?
Confirmed, yes.
52 6/23/2025 Specification 01800-1.10
Specification section 01800, 1.10, please confirm the type/style of fire department connection (FDC) for the new housing units.
Type/style of the FDC is up to the DOR.
53 6/23/2025 Specification 01800-1.10
UFC 3-600-01 section 9-18 .7.4.1 states manual pull stations are required to be provided at all exits, regardless of occupancy. Please confirm if this requirement applies to this project at every egress door?
Confirmed. Follow the UFC criteria for manual pull station requirements.
54 6/23/2025 Specification 01800-1.10
UFC 3-600-01 section 9-18 .7.4.1 states manual pull stations are required to be provided at all exits, regardless of occupancy. Please clarify if manual pull stations are required for the fire alarm system if UFC 3-600-01 is to be followed?
Confirmed. Follow the UFC criteria for manual pull station requirements.
55 6/23/2025 Specification 01800-1.11
Please confirm the intent is to provide separate domestic and fire services to each housing unit?
Provide separate domestic and fire services. The DOR shall be responsible for determining final demand of their design and that shall be measured against the existing capacity.
56 6/23/2025 Specification 01800-1.11
Please confirm if each dwelling unit will require a dedicated fire water lateral, backflow preventer, and riser assembly, or if the dwelling units in the multiplex building is to share a single fire water lateral and backflow preventer, but have separate riser assemblies in each unit utility room?
The system is a compilation of compatible components utilizing both wired and wireless components. DOR shall investigate and design a system utilizing components that are compatible with the existing system.
57 6/23/2025 Drawings A-101 & A-
Per the provided RFP Drawings (A-101 & A-102), the wall between adjoining units are noted as a firewall, but according to IRC Section R302.2, only a fire-resistance-rated wall assembly is necessary for this application. Please confirm we are only required to provide a fire-resistance-rated wall assembly to meet above referenced code?
Provide fire protection in accordance with NFPA 101 and per RFP (including RFP drawings.)
58 6/23/2025 Specification 01800-1.7
Specification section 01800, 1.7.2.1 indicates an R-value of exterior walls to be R-20. For this climate zone and wood framed walls, Energy Star/ IECC allows insulation to be R-20 continuous OR R-13 cavity insulation + R-5 continuous insulation. Confirm if R-13 cavity + R-5 continuous is acceptable per IECC 2018 and the New York State Energy Code 2020?
Confirmed at wood construction. The proposed insulation recommendation is an acceptable alternative to the prescriptive R-20 standard and is indicated in IECC 2018 and the New York State Energy Code 2020 to be acceptable at wood stud construction.
59 6/23/2025 Attachment G
There is conflicting information provided Attachment G documents "New Building Design and Construction" and the "CSTO Family Housing Design CSTO (Rev B)” regarding landscape irrigation. Please confirm permanent irrigation system is not a requirement of the project scope?
Permanent irrigation is not a requirement for this project.
60 6/23/2025 Specification 01800-1.5
Specification section 01800, 1.5.1 states to use boring logs provided in the RFP.
Section 1.5.3 states to use continuous strip footers for bidding purposes.
Specification section 1.5.4 states the contractor shall bear all costs for the required foundations based upon the geotechnical data produced post award.
Since the soil stratum can vary significantly in NY, for bidding purposes please confirm that the RFP soil boring closest to the foundation in question is to be used for bidding purposes and if the post award geotechnical borings find that the soil conditions vary and require different foundation type that this will be handled as a differing site condition?
For bidding purposes, the Contractor is to provide the foundation system as stated in the RFP using the information provided in the RFP. The Contractor shall make the best use of the available boring information provided. If the Contractor's post-award geotechnical site investigation materially differs from the information in RFP, the Contactor may be entitled to compensation under a claim of Differing Site Conditions.
61 6/23/2025 Specification 01800-1.5
Specification section 01800, 1.5.1 states to use boring logs provided in the RFP.
For bidding purposes, please confirm none of the site utilities require any foundation support besides compacted subgrade?
Confirmed.
62 6/23/2025 Specification 01800-1.5
Specification section 01800, 1.5.1 states to use boring logs provided in the RFP.
For bidding purposes, please confirm the contractor’s proposal design and pricing shall assume groundwater will not be encountered and if groundwater is encountered it will be handled as a differing site condition?
For bidding purposes, the Contractor shall use the Groundwater levels stated in the RFP Attachment D - Ft Wadsworth Watershed Study 1020, Test Pit Logs (starting on PDF Page 170 of 207).
63 6/23/2025 Specification 01110-1.7
Specification section 01110, 1.7 provides the allowed work hours for the project. Please confirm if there are any noise restriction that will be required during regular work hours (M-F from 0700 to 1700)?
There are no noise restrictions during the authorized work hours stated in 1.7 Work Hours.
64 6/23/2025 Specification 01110-1.7
Specification section 01110, 1.7 states work outside of the regular hours requires Contracting Officer approval.
Please confirm if there are any noise restriction that will be required during work outside regular work hours (evenings / nights, weekends, or Federal holidays)?
Noise restrictions may be required for evenings / nights, weekends, or Federal holidays.
Requirements will be determined during construction on a case by case basis.
65 6/23/2025 Specification 01110-1.5
Specification section 01110, 1.5 states no work on weekends or Federal holidays is not allowed unless authorized by the Contracting Officer. Please provide list of the non-work holidays?
For bidding purposes, refer to 'www.OPM.gov' for a list of observed Federal Holidays.
66 6/23/2025 Fire Protection & Life Health
Saftey
Please confirm who the Authority Having Jurisdiction (AHJ) will be for final inspection of the fire protection / life safety systems (sprinkler & fire alarm) for the project? Being a Federal project, does NY state and local AHJ / jurisdictions apply?