This document contains design coordination review comments for a construction project. The comments identify items in the 65% design submittal that do not appear to comply with requirements, including potential code issues and discipline coordination problems. The contractor must address all comments, including those marked as critical, within seven calendar days of receipt by contacting the project manager to discuss with reviewers. The project involves renovating and expanding sector facilities in Houston and Galveston, Texas.
This federal contract opportunity notice is for a design/build project to construct 4 to 8 single family housing units on undeveloped U.S. Coast Guard property in Perry, Maine. The solicitation will be issued by the Coast Guard Shore Infrastructure Logistics Center Facilities Design and Construction Center. The fixed-price contract has a base item and three option items for additional housing. The pre-solicitation posting provides advance notice for the forthcoming solicitation numbered 70Z04720REASPOR00.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN COORDINATION REVIEW COMMENTS
FACILITIES DESIGN & CONSTRUCTION CENTER
[Project Name, Location and SFRL#]
*Action code: c Concur with comments and will incorporate in next submittal If Contractor disagrees with comment or feels that further discussion is required, then Contractor shall contact the FDCC Project Manager and resolve the issue before proceeding with design. Resubmission of the design shall be based on the resolution reached between the Contractor and Government.
Comments by: Team Phone: Date:
xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX)
Civil Structural Architect Mechanical Electrical Construction
LEED
Telecomms
757.852.34xx 757.852.34xx 757.852.34xx 757.852.34xx 757.852.34xx
757. xxx-xxxx 757.852.34xx 757.xxx.xxxx xx-xx-2012
Project Title and Location Type of Review
Project No.:
Relocation of Sector Houston-Galveston 08-3047134 –Ellington Field 65%
Station Houston Phase 2 08-3101726 –Galena Park xxxxxxxx Design dated xx-xx-xx
Final
Cmt By:
Dwg No:
Cmt No
Comments Action Taken*
General xx 01 We do not consider these review comments to constitute a change to your contract. If, in your opinion, work beyond the scope of services is required, please contact XXXXXXXXX, Contract Specialist, at (757) 852- 34xx.
xx 02 The primary purpose of these review comments is to identify items that do not appear to be in compliance with the RFP requirements. It is not the intent of the review to provide a coordination review with other disciplines;
a code compliance review, etc. although potential conflicts or questions concerning code compliance may be included for the designer’s information/action. Compliance with the RFP specification 01158, 01159 and 01160 is required regardless of whether or not an RFP required item is shown on the drawings or if apparent non-compliance is not noted in
If Contractor disagrees with comment or feels that further discussion is required, then Contractor shall contact the FDCC Project Manager and resolve the issue before proceeding with design. Resubmission of the design shall be based on the resolution reached between the Contractor and Government.
review comments.
The review is largely limited to what has been submitted, recognizing that this is identified as being a XX% xxxxxxx submittal [and that the design is not complete or fully coordinated].
03 The contractor is required to comply with the RFP requirements regardless of whether or not a review a comment was made on what could be considered as an “unapproved” deviation from the RFP requirements. It is not the intent of the review to identify where the design exceeds RFP requirements, although comments may be made where it appears that there may be a misinterpretation of the RFP requirements.
Comments contained within cells with yellow fill are considered “critical” and shall be responded to within 7 calendar days.
Contractor should contact the FDCC Project Manager to arrange discussions with reviewers.
DRAWINGS
General
Civil
If Contractor disagrees with comment or feels that further discussion is required, then Contractor shall contact the FDCC Project Manager and resolve the issue before proceeding with design. Resubmission of the design shall be based on the resolution reached between the Contractor and Government.
Architectural
Plumbing
HVAC
Electrical
If Contractor disagrees with comment or feels that further discussion is required, then Contractor shall contact the FDCC Project Manager and resolve the issue before proceeding with design. Resubmission of the design shall be based on the resolution reached between the Contractor and Government.