This document contains design coordination review comments for a construction project. The comments identify items in the 65% design submittal that do not appear to comply with requirements, including potential code issues and discipline coordination problems. The contractor must address all comments, including those marked as critical, within seven calendar days of receipt by contacting the project manager to discuss with reviewers. The project involves renovating and expanding sector facilities in Houston and Galveston, Texas.

This federal contract opportunity notice is for a design/build project to construct 4 to 8 single family housing units on undeveloped U.S. Coast Guard property in Perry, Maine. The solicitation will be issued by the Coast Guard Shore Infrastructure Logistics Center Facilities Design and Construction Center. The fixed-price contract has a base item and three option items for additional housing. The pre-solicitation posting provides advance notice for the forthcoming solicitation numbered 70Z04720REASPOR00.

View the file

Other files

File Type Posted
Final Amendment 0006.pdf PDF
Final Amendment 0005.pdf PDF
Final Amendment 0004.pdf PDF
Eastport1.zip ZIP file
Heavy Wage Determination.pdf PDF
040920 REV Eastport_PRICE PROPOSAL FORM_pja.pdf PDF
Appendix I O M Pt 2EquipEnrollment.xlsx XLSX spreadsheet
Amendment Form 4 Pages.pdf PDF
Residential Wage Determination.pdf PDF
Appendix J O M Pt3 SAMJobPlan.pdf PDF
J.6 Site_Pics.pdf PDF
J.7 House Pics.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Appendix B -ElectDeliv-Sept2012.pdf PDF
Appendix P_BSD-135_Ice Dams.pdf PDF
_6841069_Eastport Housing-Final RFP.pdf PDF
Appendix D - Design Narrative-Sept2012.pdf PDF
Appendix K -Exterior Wall Detail.pdf PDF
Attachment B USCG Eastport Housing Site Development Report.pdf PDF
USCG_Survey_Report_PerryME.pdf PDF
USCG Eastport Housing Site Development Report final_costs removed.pdf PDF
Full_PDF_Final-Draft_Eastport_EA_07192019.pdf PDF
Attachment A_Site Photos.pdf PDF
Appendix N-Individual Space Criteria Sheets.pdf PDF
Appendix R_PMDS_Eastport_ReCap_FamilyHousing.pdf PDF
Appendix A-ComputerGenDrwgs-Sept2012.pdf PDF
Appendix L- HERS Report (NOT USED).pdf PDF
70Z04720REASPOR00 RFP.pdf PDF
Residential Wages.pdf PDF
Appendix Q_Radon tipsheet.pdf PDF
Appendix E - Industry Standards for Const Docs-Sept2012.pdf PDF
Heavy Wages.pdf PDF
Appendix G- DS(1) Design Submission Transmittal Form.pdf PDF
Appendix C -FDCC File Naming-SEP 2014.pdf PDF
Appendix M- LEED for HOMES.pdf PDF
Appendix O_ Roof Design.pdf PDF
Appendix H-OandM-Part1UniformaMeansSAMSCorrelationCrosswalk Table1.pdf PDF
Appendix S_Typical_Metal Bldg Section.pdf PDF
021320 Pre Solicitation.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DESIGN COORDINATION REVIEW COMMENTS

FACILITIES DESIGN & CONSTRUCTION CENTER

[Project Name, Location and SFRL#]

*Action code: c Concur with comments and will incorporate in next submittal If Contractor disagrees with comment or feels that further discussion is required, then Contractor shall contact the FDCC Project Manager and resolve the issue before proceeding with design. Resubmission of the design shall be based on the resolution reached between the Contractor and Government.

Comments by: Team Phone: Date:

xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX) xxxxxx (XX)

Civil Structural Architect Mechanical Electrical Construction

LEED

Telecomms

757.852.34xx 757.852.34xx 757.852.34xx 757.852.34xx 757.852.34xx

757. xxx-xxxx 757.852.34xx 757.xxx.xxxx xx-xx-2012

Project Title and Location Type of Review

Project No.:

Relocation of Sector Houston-Galveston 08-3047134 –Ellington Field 65%

Station Houston Phase 2 08-3101726 –Galena Park xxxxxxxx Design dated xx-xx-xx

Final

Cmt By:

Dwg No:

Cmt No

Comments Action Taken*

General xx 01 We do not consider these review comments to constitute a change to your contract. If, in your opinion, work beyond the scope of services is required, please contact XXXXXXXXX, Contract Specialist, at (757) 852- 34xx.

xx 02 The primary purpose of these review comments is to identify items that do not appear to be in compliance with the RFP requirements. It is not the intent of the review to provide a coordination review with other disciplines;

a code compliance review, etc. although potential conflicts or questions concerning code compliance may be included for the designer’s information/action. Compliance with the RFP specification 01158, 01159 and 01160 is required regardless of whether or not an RFP required item is shown on the drawings or if apparent non-compliance is not noted in

If Contractor disagrees with comment or feels that further discussion is required, then Contractor shall contact the FDCC Project Manager and resolve the issue before proceeding with design. Resubmission of the design shall be based on the resolution reached between the Contractor and Government.

review comments.

The review is largely limited to what has been submitted, recognizing that this is identified as being a XX% xxxxxxx submittal [and that the design is not complete or fully coordinated].

03 The contractor is required to comply with the RFP requirements regardless of whether or not a review a comment was made on what could be considered as an “unapproved” deviation from the RFP requirements. It is not the intent of the review to identify where the design exceeds RFP requirements, although comments may be made where it appears that there may be a misinterpretation of the RFP requirements.

Comments contained within cells with yellow fill are considered “critical” and shall be responded to within 7 calendar days.

Contractor should contact the FDCC Project Manager to arrange discussions with reviewers.

DRAWINGS

General

Civil

If Contractor disagrees with comment or feels that further discussion is required, then Contractor shall contact the FDCC Project Manager and resolve the issue before proceeding with design. Resubmission of the design shall be based on the resolution reached between the Contractor and Government.

Architectural

Plumbing

HVAC

Electrical

If Contractor disagrees with comment or feels that further discussion is required, then Contractor shall contact the FDCC Project Manager and resolve the issue before proceeding with design. Resubmission of the design shall be based on the resolution reached between the Contractor and Government.