Amendment 5-Responses to Questions 05.14.20.pdf

PDF 354 KB Posted

Attached to
Calibration and Repair Services Federal contract opportunity
Solicitation number
70Z03820QE0000007
Issued by
Department of Homeland Security US Coast Guard

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

70Z03820QE0000007

Responses to Questions

Answers provided 14 May 2020 Amendment 5

This document provides United States Coast Guard (USCG) responses for questions that have been asked regarding solicitation 70Z03820QE0000007. Question numbers are provided simply as a reference and in no way infer a prioritization of the questions.

Number Question USCG Response 1 We are requesting clarification on the language in the Factor 5-Price definition in the T's and C's file Attachment+3- +Terms+and+Conditions+inluding+Evaluation+Criteria.pdf. "Failure to quote pricing for the base period and the option periods on individual line items may result in a quotation being excluded from further consideration." We assume the statement "... on individual line items ..." refers to the UNIT PRICE cells E7 and E10 in the BASE worksheet (CLIN 0001 and 0002) and the UNIT PRICE cells E5 and E18 in worksheets Option 1 through Option 4 respectively (CLINs 2001, 2002, 3001, 3002, 4001 and 4002) in the Excel workbook file Attachment+1+Schedule+of+Services-+70Z03820QE0000007.xlsx.

We assume only those ten (10) price cells are expected to be completed by the offeror.

Some of the cells are incorrectly stated in the question. Complete the highlighted areas on Attachment 1- Schedule of Services 70Z03820QE0000007, providing a unit price for CLINS 0001, 0002, 1001, 1002, 2001, 2002, 3001, 3002, 4001, and 4002 which covers the base and option periods one (1) through four (4).

2 The statement "Failure to quote pricing for the base period and the option periods on individual line items ..." does not refer to pricing of the 4,304 individual line items in Amendment+1- Attachment+4+Calibrated+and+Repair+Items+List.xlsx.

Correct, the vendor is not required to price each item on Attachment 4- Calibrated and Repair Items List.