This statement of work outlines requirements for a communication management system to be provided to the U.S. Coast Guard Polar Security Cutter program. The contractor will design, test, and deliver up to three communication management systems over five years, including a red and black switching system, common end-user terminals, and communication management software. Key activities include kickoff and design review meetings, preliminary and final design with testing, and delivery of systems for the first, second, and third cutters if the optional CLINs are exercised by the Coast Guard in years one through five. The contractor must meet requirements for interfaces, documentation, licensing, and configuration management throughout the design and testing process.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
70Z02320RAPB02300 1
1. General Information
1.1. Scope. The scope of this Statement of Work (SOW) is to provide a Communication
Management System (CMS) to include; a Red (classified) Switching System, a Black
(unclassified) Switching System, Common End-User Terminals (CEUTs), and
Communication Management Software for the U.S. Coast Guard (USCG) Polar
Security Cutter (PSC) Program. Combined, they provide point-to-point connections for information flow between radios, modems, cryptographic, classified communication capable user terminals, recording devices and Internal Voice Network (IVN) equipment.
The CMS also provides management of Exterior Communication System (XCS) radios.
1.2. Period of Performance: Five years from date of award.
2. References
2.1. Reserved
3. CLIN 0001 – Design and Testing of CMS
3.1. Kick Off Meeting
3.1.1. The Contractor shall conduct a Kick off meeting at its facility within 2 weeks after contract award.
3.1.2. The Contractor shall accommodate up to 5 Government attendees.
3.1.3. The Contractor shall provide a Project Plan and Schedule. [DI-018]1
3.1.4. The Contractor shall provide a Quality Assurance Plan. [DI-013]
3.1.5. The Contractor shall identify schedule and technical risks.
3.2. Preliminary Design
3.2.1. The Contractor shall provide a Network Architecture Report. [DI-011]
3.2.2. The Contractor shall provide a Schematic Block Diagram. [DI-002]
3.2.3. The Contractor shall provide Electronic System Elementary Wiring Diagrams.
[DI-003]
3.2.4. The Contractor shall provide a Test and Evaluation Program Plan. [DI-012]
3.2.5. The Contractor shall provide Interface Requirements Specifications. [DI-019]
3.3. Formal Design Review (FDR) The Contractor shall conduct a Formal Design Review with Government representatives in attendance.
3.3.1. FDR shall be at the Contractor’s facility.
3.3.2. The Contractor shall accommodate up to 5 Government attendees.
3.3.3. The Contractor shall conduct FDR when the CMS design:
3.3.3.1. Is technically feasible of complying with Attachment A.
3.3.3.2. Is a complete and integrated design that will satisfy all technical requirement.
3.3.3.3. Accurately captures all integration and interfaces between the CMS, Government furnished systems (e.g., data networks, internal voice networks, radios) as defined in the GFI.
3.3.3.4. Demonstrates complete representation of all interfaces defined in the CMS
Specification and GFI.
1Refers to Contract Data Requirements List (CDRL).
70Z02320RAPB02300 2
3.3.4. The Contractor shall conduct the FDR within 2 weeks after Government acceptance of the following Preliminary Design data items (3.2 above).
3.3.5. During FDR, the Contractor shall provide data and narrative in sufficient detail for the Government to verify:
3.3.5.1. The design is producible per the Contractor’s build strategy.
3.3.5.2. The design is Technology Readiness Level (TRL) 7+.
3.3.5.3. The Requirements Traceability and Verification Matrix. [DI-021]
3.3.5.4. The Contractor’s Configuration Status Accounting (CSA).[DI-017]
3.3.5.4.1. The CSA shall establish the configuration baseline that uniquely identifies end items, repairable components, replaceable components, software items, and firmware items.
3.3.5.4.2. CSA shall include all components valued at $3,000 or greater.
3.3.5.4.3. The CSA shall include serialized items even if they are valued under
$3,000
3.3.5.5. The design satisfies contract requirements.
3.3.5.6. System and component material selections meet contract performance requirements.
3.3.5.7. Software development processes are fully defined and accepted as appropriate for coding and test.
3.3.5.8. Interfaces between all configuration items both internal and external to the system are defined and stable.
3.3.5.9. Software user interfaces are identified, including critical formats and interactions.
3.4. Final Design and Test
3.4.1. The Contractor shall ensure that its CMS meets each technical requirement in the Technical Specification, Attachment A.
3.4.1.1. Test plans, procedures, and reports shall include either a formal certificate of compliance, or formal testing to validate compliance with:
3.4.1.1.1. MIL-STD-167-1A
3.4.1.1.2. MIL-STD-461
3.4.1.1.3. MIL-STD-464
3.4.2. The Contractor shall provide a Test Plan. [DI-014]
3.4.3. The Contractor shall provide Test Procedures. [DI-015]
3.4.4. The Contractor shall provide Test Reports. [DI-020]
3.4.5. Test Administration and Testing
3.4.5.1. Test Dates and Details. The Contractor shall schedule testing to occur within 2 weeks after approval of Test Procedures. [DI-016].
3.4.5.2. The Contractor shall perform the tests necessary to demonstrate compliance with the requirements of Attachment A.
3.4.5.3. The Contractor shall execute approved test procedures in the presence the Government.
3.4.5.4. The Contractor shall start tests only with permission of the Government.
3.4.5.5. The Contractor shall perform each test using the current approved or accepted test procedure.
3.4.5.6. While conducting tests, the Contractor shall not align or adjust the equipment being tested except as required by the test procedure.
70Z02320RAPB02300 3
3.4.5.7. The Contractor shall perform tests at a facility of their choosing.
3.4.5.8. The Contractor shall accommodate up to 5 Government attendees.
3.4.5.9. Configuration Management. The Contractor shall perform configuration management functions to ensure that no changes or deviations to the system design, components, or software occur without prior Government approval.
3.4.5.10. The Contractor shall submit an Engineering Change Proposal (ECP), for approval before changing the configuration baseline. [DI-016]
3.4.5.11. The Contractor shall maintain configuring control of everything in the configuration baseline from FDR to delivery.
3.4.5.12. The Contractor shall place software under configuration control immediately following unit test.
3.4.5.13. The Contractor shall provide a Software Version Description [DI-006].
3.4.6. The Contractor shall provide fully paid, non-expiring software licenses, for all software items necessary for the operation, use, and maintenance of contractor furnished equipment.
3.4.7. Reserved
3.4.8. Reserved
3.4.9. The Contractor shall provide Installation Control Drawings. [DI-004]
3.4.10. The Contractor shall provide Software User Manuals. [DI-005]
4. CLIN 1001 – Communications Management System for PSC #1 (OPTION)
If the Government exercises this option, it will be in year 1 of the period of performance.
4.1. The Contractor shall provide one complete CMS.
4.2. The Contractor shall provide an Information Assurance Plan. [DI-009]
4.3. The Contractor shall provide an Information Assurance Design Review Information
Package. [DI-010]
4.4. The Contractor shall provide a Bill of Materials. [DI-001]
4.5. The Contractor shall provide Technical Manuals. [DI-007]
4.6. The Contractor shall provide a Software Product Specifications [DI-008].
4.7. Reserved.
5. CLIN 10002 –Reserved
5.1. Reserved.
6. CLIN 2001 – Communications Management System for PSC #2 (OPTION)
If the Government exercises this option, it will be in year 2 or 3 of the period of performance.
6.1. The Contractor shall deliver one complete CMS.
7. CLIN 3001 – Communications Management System for PSC #3 (OPTION)
If the Government exercises this option, it will be in year 4 or 5 of the period of performance.
7.1. The Contractor shall deliver one complete CMS.