Updated Statement of Work Bldg 210 Replace 2 Boilers August 9 2022.pdf
PDF 381 KB Posted
- Attached to
- Replace Boilers at Bldg. 210
- Solicitation number
- 70LGLY22BSSB00002
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Law Enforcement Training Center Building 210 Replace 2 Boilers
. Page 1
SECTION 01 11 00
STATEMENT OF WORK
Updated 8/9/22
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E 2114 (2008) Standard Terminology for Sustainability Relative to the Performance of Buildings
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E 2114, and as specified.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.
c. "Operational performance" is the functional behavior of the building as a whole or of the building components.
d. "Sustainability" is the balance of environmental, economic, and societal considerations.
1.3 SUBMITTALS
Government approval is required for all submittals. See section 01 33 00 for submittal procedures.
Submittals for this project include:
1. Bonding and Insurance Certificates
2. AHA/CPL
3. Project Schedule
4. Product Data
5. O&M Data
6. Warranty Data
Federal Law Enforcement Training Center Building 210 Replace 2 Boilers
. Page 2
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Project Description
The contractor shall field verify all existing conditions and notify the contracting officer immediately of any discrepancies. The Contractor shall provide all necessary parts and labor to supervise, direct, and accomplish the work described below. Only one boiler shall be taken offline at a time in order to support facility operation. Exact location of work to be identified by Contracting Officer’s Representative (COR) during site visit. Key personnel to be provided by the prime contractor for this job shall consist of a single superintendent/safety/quality manager.
The contractor’s key personnel must be present when sub-contractors are working. The contractor shall:
1. Demo, remove, and dispose of existing boilers in accordance with all contract documents and applicable codes.
Boiler 1: Cemline Model # VB450FTB640C3-RL Serial # 42303 Boiler 2: Cemline Model # VB450FTB640C3-RL Serial # 42302
2. Cut/unbolt abandoned condenser water lines as shown in figure 1 below. Remove and dispose of piping.
3. Provide 2 new like-in-kind boilers that meet or exceed all existing boiler specifications.
a. Cemline M VB450FTB640C3-RL or equivalent
b. 480VAC, 3phase
c. 450 gallon hot water storage tank
d. 125 psi water pressure
e. 640KW
f. 240 dF max water temperature
4. Install new boilers per manufacturer’s specifications, ensuring all manufacturer warranty conditions are met and warranties remain intact.
5. Provide necessary modifications to existing piping, wiring, power, and controls as necessary to insure complete and useable equipment operation.
6. FLETC maintains a sole source contract with Certified Controls Systems for the campus controls system. Certified Controls is the only company authorized to install/alter the control system at the FLETC. The intent of this project is to use existing controls equipment to operate the new boilers.
The contractor shall coordinate all controls work with Certified Controls.
7. Perform equipment start-up and test procedure in accordance with manufacturer’s instructions.
8. Ensure all work is done in accordance with manufacturer’s installation and start-up instructions and maintains all manufacturer warranties.
9. Provide one (1) year warranty on all workmanship.
10. Provide 2 hour training to plant personnel on sequence of operation and periodic maintenance.
Federal Law Enforcement Training Center Building 210 Replace 2 Boilers
. Page 3
Figure 1. Remove abandoned line to these locations.
1.4.2 Location
The work shall be located at building 210 on the FLETC, Glynco campus approximately as indicated.
The exact location will be shown by the Contracting Officer.
1.5 NOT USED
1.6 WORK SCHEDULING
Federal Law Enforcement Training Center Building 210 Replace 2 Boilers
. Page 4
Normal duty hours for work shall be from 7:00 a.m. to 5:30 p.m., Monday through Friday. Requests for additional work shall require written approval from the Contracting Officer 7 days in advance of the proposed work period.
1.7 PROJECT ENVIRONMENTAL GOALS
Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporates the principles of sustainability. Specifically:
a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion.
Minimize offsite environmental impact.
b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.
c. Use environmentally preferable products and decrease toxicity level of materials used.
d. Use renewable energy and material resources.
e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended. Consider the durability, maintainability, and flexibility of building systems.
f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.
g. Reduce construction waste through reuse, recycling, and supplier take-back.
1.8 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.9 ON-SITE PERMITS
1.9.1 Utility Outage Requests and Utility Connection Requests
Federal Law Enforcement Training Center Building 210 Replace 2 Boilers
. Page 5
Notify the Contracting Officer at least 48 hours prior to starting excavation work. Contractor is responsible for marking and verifying all utilities not marked.
The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed. But indicated in locations to be traversed by piping, ducts, and other work to be installed.
Work shall be scheduled to hold outages to a minimum.
Requests for utility outages and connections shall be made in writing to the Contracting Officer at least 2 calendar days in advance of the time required. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.10 LOCATION OF UNDERGROUND FACILITIES
1.10.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work. Contact Georgia and Glynn county utility locate organizations 48 hours prior to excavating. Contractor is responsible for marking all utilities not marked by locate service.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Contractor shall have a total of 90 days from notice to proceed to complete the work. Photos of job site, equipment and piping shown below for reference.
Federal Law Enforcement Training Center Building 210 Replace 2 Boilers
. Page 6
-- End of Section --
File details come from the government source that posted it. Updated .