SECTION 22 30 00 Plumbing Equipment (Boiler Spec).pdf

PDF 263 KB Posted

Attached to
Replace Boilers at Bldg. 210
Solicitation number
70LGLY22BSSB00002
Issued by

View the file

Other files

File Type Posted
FINAL RFI Question and Answers.pdf PDF
FINAL RFI Question and Answers.pdf PDF
70LGLY22BSSB00002 Amendment 1.pdf PDF
Updated Statement of Work Bldg 210 Replace 2 Boilers August 9 2022.pdf PDF
RFI Question and Answers.pdf PDF
Attachment 9 - WH 347 - Wage and Hour Division.pdf PDF
Attachment 13b - USCIS Form I-9.pdf PDF
Attachment 5 - Format for Irrevocable Letter of Credit.pdf PDF
Attachment 13a - Instructions for Employment Eligibility Verification Form.pdf PDF
Attachment 12 - FLETC Tier 1 Badging Packet.pdf PDF
Attachment 25 - WH 1321 - DOL Poster.pdf PDF
Attachment 21- SF 24 - Bid Bond.pdf PDF
Attachment 24 - DHS 700-3 - Contractor Release Form.pdf PDF
Attachment 18 - GA Construction Requirements Statute Wage Determination Building GA20220315 (20220722).pdf PDF
Attachment 26 - FLETC Form 121-00-02 Visitor Access Request.pdf PDF
Attachment 8 - Instruction for Completing WH-347.pdf PDF
2.2.1 Solicitation Revised Bid Schedule Exhibit A.xlsx XLSX spreadsheet
Attachment 4 - SF 28 - Affidavit of Individual Surety.pdf PDF
Attachment 7 - FTC.FMD -70 Invoice Cover Sheet.pdf PDF
2.2.1 70LGLY22BSSB00002 Remove and Replace Boilers in Bldg. 210 Solicitation.pdf PDF
Attachment 1 - Statement of Work and Specifications.pdf PDF
Attachment 17 - Security Training List.pdf PDF
Attachment 23 - Financial Questionnaire.pdf PDF
Attachment 2 - SF 25 - Performance Bonds.pdf PDF
Attachment 20 - SF 1444 - Request for Authorization of Additional Classification and Rate.pdf PDF
Attachment 6 - Format for Financial Institution.pdf PDF
Attachment 22 - SF LLC - Disclosure of Lobbying Activities.pdf PDF
Attachment 3 - SF 25A - Payment Bonds.pdf PDF
Attachment 10 - FMD 42 - Daily Report.pdf PDF
Attachment 15 - SF 85 - Questionnaire for Non-Sensitive Positions.pdf PDF
Attachment 19 - SF1413 Statement and Acknowledgment.pdf PDF
Attachment 16 - Security Handout.pdf PDF
Attachment 14 - OF 306 - Contractors Declaration of Federal.pdf PDF
Attachment 11 - DHS 11000-6 - Non-Disclosure Agreement.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPLACE BOILERS IN BUILDING 210

FLETC, GLYNCO GA

AUGUST 9, 2022 PLUMBING EQUIPMENT 22 30 00 - 1

SECTION 22 30 00 - PLUMBING EQUIPMENT

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Domestic hot water storage tanks.

1.02 RELATED REQUIREMENTS

A. Electrical characteristics and wiring connections.

B. Requirements for water storage tanks specified by this section.

C. Product requirements for water storage tanks for placement by this Section.

1.03 REFERENCE STANDARDS

A. ABMA STD 9 - Load Ratings and Fatigue Life for Ball Bearings 2015.

B. ABMA STD 11 - Load Ratings and Fatigue Life for Roller Bearings 2014.

C. ASME BPVC-VIII-1 - Boiler and Pressure Vessel Code, Section VIII, Division 1 - Rules for Construction of Pressure Vessels 2017.

D. ICC (IPC) - International Plumbing Code Most Recent Edition Adopted by Authority Having Jurisdiction, Including All Applicable Amendments and Supplements.

E. NFPA 70 - National Electrical Code Most Recent Edition Adopted by Authority Having Jurisdiction, Including All Applicable Amendments and Supplements.

1.04 SUBMITTALS

A. Product Data:

1. Provide electrical characteristics and connection requirements.

B. Shop Drawings:

1. Indicate dimensions of tanks, tank lining methods, anchors, attachments, lifting points, tappings, and drains.

C. Project Record Documents: Record actual locations of components.

D. Operation and Maintenance Data: Include operation, maintenance, and inspection data, replacement part numbers and availability, and service depot location and telephone number.

E. Warranty Documentation: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer.

Replace Boiler B210 FLETC, Glynco GA

22 30 00 - 2 PLUMBING EQUIPMENT FEBRUARY 1, 2022

F. Project Record Documents: Record actual locations of components.

1.05 QUALITY ASSURANCE

A. Manufacturer Qualifications: Company specializing in manufacturing the type of products specified in this section, with minimum three years of documented experience.

B. Certifications:.

1. Water Tanks: ASME labeled to ASME BPVC-VIII-1.

1.06 DELIVERY, STORAGE, AND HANDLING

A. Provide temporary inlet and outlet caps. Maintain caps in place until installation.

1.07 WARRANTY

A. Provide manufacturer warranty for domestic water heater storage tanks.

PART 2 PRODUCTS

2.01 DOMESTIC HOT WATER STORAGE TANKS

A. Manufacturers:

1. Cemline (or approved substitute)

B. Tank: 450 gallon Glass-Lined, Jacketed & Insulated ASME Tanks, Lock-Temp Design Locks Hot Water at Top, Cold Water at Bottom.

C. Openings: Up to 3 inches (75 mm), copper-silicone threaded; over 4 inches (100 mm), flanged; flanged collar for heat exchanger; manway fitting.

D. Accessories: Provide the following: tank drain, water inlet and outlet, thermometer with range of 40 to 200 degrees F (4 to 93 degrees C), ASME pressure relief valve suitable for maximum working pressure.

2.02 ELECTRICAL WORK

A. Supply manual or automatic control and protective or signal devices required for the operation specified, and any control wiring required for controls and devices not shown.

PART 3 EXECUTION

3.01 INSTALLATION

A. Install plumbing equipment in accordance with manufacturer's instructions, as required by code, and complying with conditions of certification, if any.

REPLACE BOILERS IN BUILDING 210

FLETC, GLYNCO GA

AUGUST 9, 2022 PLUMBING EQUIPMENT 22 30 00 - 3

B. Coordinate with plumbing piping and related fuel piping work to achieve operating system.

C. Domestic Water Storage Tanks:

1. Provide steel pipe support, independent of building structural framing members.

2. Clean and flush prior to delivery to site. Seal until pipe connections are made.

3. Provide piping insulation on all hot water piping between new storage tanks.

END OF SECTION 22 30 00