This document outlines a quality assurance surveillance plan (QASP) for a federal indefinite delivery, indefinite quantity contract to provide national cross docking and incident support base services. The contractor will be responsible for establishing and managing cross dock sites, empty trailer yards, and incident support bases/forward staging areas throughout the continental US on an as-needed basis in response to national emergencies. Key requirements include mobilizing cross dock operations within 12 hours, reaching full operational capacity within 72 hours, properly accounting for and processing 500 empty trailers per day through cross docks and 200 trailers per day through ISBs/FSAs, meeting various physical site and resource standards, and deactivating operations within 72-48 hours of notification. The contracting officer's representative will monitor performance using methods such as random sampling, 100% inspections, and customer feedback to ensure outcomes meet standards for timely response, trailer throughput, and other performance objectives.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 00001 Signed.pdf | ||
| ATTCH B CLIN & Pricing Structure - CrossDock & ISB Support 1-24-20.xlsx | XLSX spreadsheet | |
| Q_As FEMA Cross Dock TMB 012220 PM.pdf | ||
| ATTCH D Sample Task Order Price Proposal 12-4-19.xlsx | XLSX spreadsheet | |
| ATTCH F Oral Presentation Instructions - 10-24-19.pdf | ||
| RFP 70FB7020R00000001.pdf | ||
| ATTCH C Sample Task Order - Cross Dock-ISB - 11-08-19.pdf | ||
| QA Template.xlsx | XLSX spreadsheet | |
| ATTCH B CLIN & Pricing Structure - CrossDock & ISB Support 11-08-19.xlsx | XLSX spreadsheet | |
| ATTCH G DHS 700-23 Subcontracting Plan Review Checklist.pdf | ||
| ATTCH A PWS - Cross Dock & ISB Support.pdf | ||
| Synopsis for National Cross Docking and Incident Support Base.pdf | ||
| PWS - CrossDock & ISB Support.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT E
Department of Homeland Security (DHS)
Federal Emergency Management Agency (FEMA)
National Cross Dock & Incident Support Base Contract
Quality Assurance Surveillance Plan (QASP)
December 4, 2019
QUALITY ASSURANCE SURVEILLANCE PLAN
(QASP)
1. INTRODUCTION
The contractor shall perform according to the requirements in the Cross Dock/ISB Performance Work Statement (PWS). Contractor activity will be monitored by the Contracting Officer’s Representative (COR), with assistance from the Technical Monitor and/or other designated staff to ensure full compliance with contract terms and conditions. The contractor’s performance will be evaluated from the inception of the task order issuance until the demobilization of the cross docking or incident support requirement and subsequent dismissal of the shuttle services requirement. This quality assurance surveillance plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) entitled National Cross Docking/Incident Support Base. This plan sets forth the procedures and guidelines Logistics Management Directorate (LMD)/ Distribution Management Directorate (DMD)/ Transportation Management Branch (TMB) will use in ensuring the required performance standards or services levels are achieved by the contractor. Due to the criticality and the nature of this contract in providing assistance to survivors of disasters, FEMA must monitor and evaluate performance to ensure that quality services, supplies, and worked performed are rendered in an expedited manner with nominal impediments. The role of the government is to perform quality assurance to ensure that contract and task order requirements are appropriately achieved.
1.1 Purpose
1.1.1 The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed by the contractor. The QASP provides a means for evaluating whether the contractor is meeting the performance standards/quality levels identified in the PWS and the contractor’s quality control plan (QCP), and to ensure that the government receives the level of quality specified.
1.1.2 This QASP defines the roles and responsibilities of all members of the FEMA integrated project team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality assurance documentation requirements, and describes the analysis of quality assurance monitoring results.
1.2 Performance Management Approach
1.2.1 The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by Logistics Management Directorate (LMD)/ Distribution Management Directorate (DMD)/ Transportation Management Branch (TMB) to monitor and manage the contractor’s performance to ensure the expected outcomes or performance objectives communicated in the PWS are achieved. Performance management rests on developing a capability to review and analyze information generated through performance assessment. The ability to make decisions based on the analysis of performance data is the cornerstone of performance management; this analysis yields information that indicates whether expected outcomes for the project are being achieved by the contractor.
1.2.2 Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach migrates away from scrutiny of compliance with the processes and practices used to achieve the outcome. A performance-based approach enables the contractor to play a large role in how the work is performed, as long as the proposed processes are within the stated constraints. The only exceptions to process reviews are those required by law (federal, state, and local) and compelling business situations, such as safety and health. An “outcomes” driven approach provides the contractor flexibility to continuously improve and innovate over the course of the contract as long as the critical outcomes expected are being achieved and/or the desired performance levels are being met.
1.3 Performance Management Strategy
1.3.1 The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own quality control (QCP) plan. QC is work output, not workers, and therefore includes all work performed under this contract regardless of whether the work is performed by contractor employees or by subcontractors. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. The contractor will develop and implement a performance management system with processes to assess and report its performance to the designated government representative. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. This QASP enables the government to take advantage of the contractor’s QC program.
1.3.2 The government representative(s), chiefly the Contracting Officer Representative (COR) will monitor performance and review performance reports furnished by the contractor to determine how the contractor is performing against communicated performance objectives. The government will make determinations regarding performance measurement metric data outlined in the Key Performance Parameters (KPP’s) and notify the contractor of those decisions. The contractor will be responsible for making required changes in processes and practices to ensure performance is executed effectively.
2. ROLES AND RESPONSIBILITIES
2.1 The Contracting Officer
The contracting officer (CO) is responsible for monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by the LMD/ DMD/ TMB. The CO ensures performance of all requirements of the IDIQ Contract and Task Orders (TO) to ensure compliance with the terms and conditions of the contract and/or TO. The CO safeguards the interest of the government in the contractual relationship.
The CO will receive all discrepancy reports from the COR and forward them to executive management of the contractor for action upon each occurrence of a noted discrepancy for resolution. The number of additional representatives serving as technical inspectors depends on the complexity of the services rendered, as well as the contractor’s performance, and must be identified and designated by the CO.
2.2 The Contracting Officer’s Representative
The COR is appointed in writing by the CO to act as his or her authorized representative to assist in administering a contract. COR limitations are contained in the written appointment letter. The COR is responsible for technical administration of the project and ensures proper government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the government’s behalf.
Any changes that the contractor deems may affect contract price, terms, or conditions shall be referred to the CO for action. The COR will have the responsibility for completing QA monitoring form used to document the inspection and evaluation of the contractor’s work performance. An alternate COR will be appointed as well to the overall IDIQ. Some task orders will have a different COR than the overall IDIQ COR, but they will also represent the government per the direction contained in the written appointment letter. Government surveillance may occur under the inspection of services clause for any service relating to the contract.
3. IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY
LEVELS
The required performance standards and/or quality levels are included in the PWS under section 13, “Key Performance Parameters.”
4. METHODOLOGIES TO MONITOR PERFORMANCE
4.1 Surveillance Techniques
In an effort to minimize the performance management burden, simplified surveillance methods shall be used by the government to evaluate contractor performance when appropriate. The primary methods of surveillance are:
Random Sampling, which shall be performed by the COR upon the issuance of a tsk order.
100% Inspection –The COR, shall inspect and evaluate performance each time a task is performed.
Reports Work Orders or Task Orders Property Transfer Reports (PTR) Actual receipt of repairs Call Logs Contractor Maintenance/Deactivation logs and/or phone
4.2 Customer Feedback
The contractor is expected to establish and maintain professional communication between its employees and customers. The primary objective of this communication is customer satisfaction.
Customer satisfaction is the most significant external indicator of the success and effectiveness of all services provided and can be measured through customer complaints.
Performance management drives the contractor to be customer focused through initially and internally addressing customer complaints and investigating the issues and/or problems, but the customer always has the option to communicate complaints to the CO, as opposed to the contractor.
Customer complaints, to be considered valid, must set forth clearly and in writing, the detailed nature of the complaint, which must be signed, and forwarded to the CO/COR. The CO/COR will accept those customer complaints and investigate using the Quality Assurance Monitoring Form, identified in Attachment 1.
4.3 Acceptable Level of Service
The minimum Acceptable Quality Level (AQL) for contractor performance (included in the Key Performance Parameters (KPPs)) is “Complete Compliance”. There is no monetary reward or penalty proposed, rather adherence or noncompliance to the KPPs will be reflected in the contractor’s CPARS rating. All items contained in the KPPs are deemed critical activities, such as those involving obtaining a cross docking facility and acquiring the Fully Operational Capacity (FOC) levels of resources, the desired performance level is established at 100 percent.
5. QUALITY ASSURANCE DOCUMENTATION
5.1 The Performance Management Feedback Loop
The performance management feedback loop begins with the communication of expected outcomes. Performance standards are expressed in the PWS and are assessed using the performance monitoring techniques shown in the KPP.
5.2 Monitoring Forms
The government’s QA surveillance accomplished by the COR, will be reported using the monitoring forms in Attachment 1. The forms, when completed, will document the government’s assessment of the contractor’s performance under the contract to ensure that the required results are being achieved.
5.2.1 The COR will retain a copy of all completed QA surveillance forms.
6. ANALYSIS OF QUALITY ASSURANCE ASSESSMENT
6.1 Determining Performance
6.1.1 Government shall use the monitoring methods cited to determine whether the performance objectives/service levels have been met. If the contractor has not met the minimum requirements, the contractor will be asked to develop a corrective action plan to show how and by what date it intends to bring performance up to the required levels. Additionally, failure to meet the performance objectives/service levels will result in the contractor’s dismissal from the task order award process.
6.2 Quality Assurance Reporting
6.2.1 At the conclusion of each task order execution, the COR will prepare written reports summarizing the overall results of the quality assurance surveillance of the contractor’s performance. These written reports will include the contractor’s submitted report and the completed quality assurance monitoring form (Attachment 1), which will become part of the QA documentation. These reports enable the government to demonstrate whether the contractor is meeting the stated objectives and/or performance standards, including scope/cost/scheduling objectives.
6.3 Reviews and Resolution
6.3.1 The COR may require the contractor’s project manager, or a designated alternate, to meet with the CO and other government personnel as deemed necessary to discuss performance evaluation. The CO or COR will define a frequency of in-depth reviews with the contractor, including appropriate self-assessments by the contractor; however, if the need arises, the contractor will meet with the COR as often as required or per the contractor’s request. The agenda of the reviews may include:
Monthly performance assessment data and trend analysis Issues and concerns of both parties Projected outlook for upcoming task orders and progress against expected trends, including a corrective action plan analysis Recommendations for improved efficiency and/or effectiveness
6.3.2 The CO must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance.
6.3.3 The COR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service levels, procedures, and metrics will be approved by the CO and incorporated as a contract modification.
ATTACHMENT 1: SAMPLE QUALITY ASSURANCE
MONITORING FORM
SERVICE or STANDARD:
SURVEY PERIOD:
SURVEILLANCE METHOD (Check):
Random Sampling 100% Inspection Periodic Inspection Customer Complaint
LEVEL OF SURVEILLANCE (Check):
Monthly Weekly As needed
PERCENTAGE OF ITEMS SAMPLED DURING SURVEY PERIOD: ______ %
ANALYSIS OF RESULTS:
Observed Service Provider Performance Measurement Rate: ______%
Service Provider’s Performance (Check): Meets Standards Does Not Meet Standards
Narrative of Performance During Survey Period:
PREPARED BY: ___________________________________ DATE: _________________
ATTACHMENT 2: KEY PERFORMANCE PARAMETERS
The Key Performance Parameters are defined as those attributes or characteristics of this requirement that we consider critical or essential in performance of this contract. They are required to successfully meet the mission of FEMA.
a. Activation/Mobilization: Key Performance Parameters
Performance Objective
PWS Ref. Performance Standard
Acceptable Quality Level
Respond to Task Order RFQ
3.1.3 c Respond with proposal within 24 hours
Complete Compliance terms of the IDIQ PWS & Task Order
PWS.
Initialize cross dock/empty trailer yard operations
3.1.3 e/ 3.2.2 d Within 12 hours of task order award
Complete Compliance terms of the IDIQ PWS & Task Order
PWS.
Reach full empty trailer yard operational capacity
3.2.2 e. Within 72 hours of task order award
Complete Compliance terms of the IDIQ PWS & Task Order
PWS.
Mobilization Plan 3.3.2 e. Respond with plan within 24 hours
Complete Compliance terms of the IDIQ PWS & Task Order
PWS.
Reach full ISB/FSA operational capacity
3.3.2 f. Within 72 hours of task order award
Complete Compliance terms of the IDIQ PWS & Task Order
PWS.
b. Physical Requirements: Key Performance Parameters
Objective
PWS Ref. Performance Standard
Acceptable Quality Level
Cross docking site supports FEMA’s physical requirements
3.1.1 The Contractor’s
cross dock site meets all the location and physical requirements as detailed in the overall IDIQ PWS, and further specified in the task order.
(Examples: electrical power and water supply, ingress and
Complete Compliance terms of the IDIQ egress for trucks, 10 inbound & outbound dock doors, etc.)
Empty trailer yard supports FEMA’s physical requirements
3.2.1 The Contractor’s
Empty Trailer Yard meets all the location and physical requirements as detailed in the overall IDIQ PWS, and further specified in the task order.
(Examples: MHEs, Wraparound Services, Security, etc.)
Complete Compliance terms of the IDIQ PWS & Task Order
PWS.
ISB/FSA Location & Physical Requirements
3.3.1 The Contractor’s
ISB/FSA site meets all the location and physical requirements as detailed in the overall IDIQ PWS, and further specified in the task order.
(Examples: electrical power and water supply, available space for 200 trailers, 24 hour office space area, etc.)
Complete Compliance terms of the IDIQ
c. Cross Docking Operations: Key Performance Parameters
Objective
PWS Ref. Performance Standard
Acceptable Quality Level
Trailer Accountability 3.1.2b Trailers must be properly accounted for in LSCMS
Complete Compliance terms of the IDIQ PWS & Task Order
PWS.
Cross Docking Operational Tempo
3.1.2.a Trailers must be physically cross docked within 1 hour, and must depart for ISB/FSA within 1.5 hours.
Complete Compliance terms of the IDIQ PWS & Task Order
Data Collection and 3.1.2c The information listed Complete Compliance
Transfer din 6.1C must be collected and transmitted electronically to the FEMA COR and
FEMA LSCMS SME.
terms of the IDIQ
d. ISB/FSA Operations: Key Performance Parameters
Objective
PWS Ref. Performance Standard
Acceptable Quality Level
Material Handling Equipment
3.3.1f Must have on-hand the proper MHE to run the operation
Complete Compliance terms of the IDIQ PWS & Task Order PWS.
Support Personnel 3.3.1j Must provide all the support personnel necessary to run the site, to include ground support personnel, general logistics support personnel, and dock laborers.
Complete Compliance terms of the IDIQ PWS & Task Order PWS.
Commodity Maintenance
3.3.1k Commodities must be maintained separately.
Complete Compliance terms of the IDIQ PWS & Task Order PWS.
e. Trailers: Key Performance Parameters
PWS Ref. Performance Standard
Acceptable Quality Level
Trailer Quantities - Cross Dock
3.1.1.d Minimum of 500 empty trailers to be positioned
Complete Compliance terms of the IDIQ PWS & Task Order PWS.
Trailer Quantities -
ISB/FSA
3.3.1 e Support and distribute 200 trailers per day
Complete Compliance terms of
f. Transponders: Key Performance Parameters
PWS Ref. Performance Standard
Acceptable Quality Level
Transponders 6 All trailers used in these operations will have FEMA GPS-enabled ITV transponders attached before leaving the site
Complete Compliance terms of the IDIQ
g. Shuttle Service and Drivers: Key Performance Parameters
PWS Ref. Performance Standard
Acceptable Quality Level
Appropriate Number of Shuttle Drivers
7 Two sets of shuttle drivers as detailed in the PWS.
Complete Compliance terms of
h. Deactivation: Key Performance Parameters
PWS Para. Performance Standard
Acceptable Quality Level
Deactivate Cross Docking Operation
8.1 Within 72 hours of
notification
Complete Compliance terms of the IDIQ PWS & Task Order
PWS.
Deactivate ISB Operation
8.1 Within 48 hours of
notification
Complete Compliance terms of the IDIQ
| 1. INTRODUCTION |
| 1. INTRODUCTION |
| 1.1 Purpose |
| 1.1 Purpose |
| 1.1.1 The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed by the contractor. The QASP provides a means for evaluating whether the contra... |
| 1.1.1 The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed by the contractor. The QASP provides a means for evaluating whether the contra... |
| 1.1.2 This QASP defines the roles and responsibilities of all members of the FEMA integrated project team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes qual... |
| 1.1.2 This QASP defines the roles and responsibilities of all members of the FEMA integrated project team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes qual... |
| 1.2 Performance Management Approach |
| 1.2 Performance Management Approach |
| 1.2.1 The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by... |
| 1.2.1 The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by... |
| 1.2.2 Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach mi... |
| 1.2.2 Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach mi... |
| 1.2.2 Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach mi... |
| 1.3 Performance Management Strategy |
| 1.3 Performance Management Strategy |
| 1.3.1 The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own quality control (QCP) plan. QC is work output, not workers, and therefore includes all work performed under th... |
| 1.3.1 The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own quality control (QCP) plan. QC is work output, not workers, and therefore includes all work performed under th... |
| 2. ROLES AND RESPONSIBILITIES |
| 2. ROLES AND RESPONSIBILITIES |
| 2.1 The Contracting Officer |
| 2.1 The Contracting Officer |
| 2.2 The Contracting Officer’s Representative |
| 2.2 The Contracting Officer’s Representative |
| 3. IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS |
| 3. IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS |
| 4. METHODOLOGIES TO MONITOR PERFORMANCE |
| 4. METHODOLOGIES TO MONITOR PERFORMANCE |
| 4.1 Surveillance Techniques |
| 4.1 Surveillance Techniques |
| 4.2 Customer Feedback |
| 4.2 Customer Feedback |
| 4.3 Acceptable Level of Service |
| 4.3 Acceptable Level of Service |
| 5. QUALITY ASSURANCE DOCUMENTATION |
| 5. QUALITY ASSURANCE DOCUMENTATION |
| 5.1 The Performance Management Feedback Loop |
| 5.1 The Performance Management Feedback Loop |
| 5.2 Monitoring Forms |
| 5.2 Monitoring Forms |
| 5.2.1 The COR will retain a copy of all completed QA surveillance forms. |
| 5.2.1 The COR will retain a copy of all completed QA surveillance forms. |
| 6. ANALYSIS OF QUALITY ASSURANCE ASSESSMENT |
| 6. ANALYSIS OF QUALITY ASSURANCE ASSESSMENT |
| 6.1 Determining Performance |
| 6.1 Determining Performance |
| 6.1.1 Government shall use the monitoring methods cited to determine whether the performance objectives/service levels have been met. If the contractor has not met the minimum requirements, the contractor will be asked to develop a corrective action p... |
| 6.1.1 Government shall use the monitoring methods cited to determine whether the performance objectives/service levels have been met. If the contractor has not met the minimum requirements, the contractor will be asked to develop a corrective action p... |
| 6.2 Quality Assurance Reporting |
| 6.2 Quality Assurance Reporting |
| 6.2.1 At the conclusion of each task order execution, the COR will prepare written reports summarizing the overall results of the quality assurance surveillance of the contractor’s performance. These written reports will include the contractor’s subm... |
| 6.2.1 At the conclusion of each task order execution, the COR will prepare written reports summarizing the overall results of the quality assurance surveillance of the contractor’s performance. These written reports will include the contractor’s subm... |
| 6.3 Reviews and Resolution |
| 6.3 Reviews and Resolution |
| 6.3.1 The COR may require the contractor’s project manager, or a designated alternate, to meet with the CO and other government personnel as deemed necessary to discuss performance evaluation. The CO or COR will define a frequency of in-depth reviews... |
| 6.3.1 The COR may require the contractor’s project manager, or a designated alternate, to meet with the CO and other government personnel as deemed necessary to discuss performance evaluation. The CO or COR will define a frequency of in-depth reviews... |
| 6.3.2 The CO must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance. |
| 6.3.2 The CO must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance. |
| 6.3.3 The COR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service levels, procedures, and metrics wil... |
| 6.3.3 The COR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service levels, procedures, and metrics wil... |